Question

In: Accounting

Feeders manufactures bird feeders for wild bird specialty stores. In? September, WilsonWilson Feeders received an order...

Feeders manufactures bird feeders for wild bird specialty stores. In? September,

WilsonWilson

Feeders received an order from Wild? Birds, Inc., for

3232

platform bird feeders. The order from Wild? Birds, Inc., became Job Number 1102 at

WilsonWilson

Feeders. A materials requisition for Job 1102 is presented to the right. In addition to the materials?requisition, the labor time records? (partial) for the week during which these feeders were made are presented. Other products were also being produced during that? week, so not all of the labor from that week belongs to Job 1102.??

LOADING...

?(Click the icon to view the materials? requisition.)                                   

LOADING...

?(Click the icon to view the labor time? records.)

LOADING...

?(Click the icon to view the job cost? record.)Read the requirements

LOADING...

.

Requirement 1. Calculate the total for the Materials Requisition form. Post the information? (cost and requisition? number) from the Materials Requisition form to the Job Cost Record in the appropriate boxes.

Complete the Materials Requisition form. In Requirement 3 you will post the information? (cost and requisition? number) from the Materials Requisition form to the Job Cost Record in the appropriate boxes.

Materials Requisition

Number: #1250

Date:

9/14

Job:

1102

Part number

Description

Quantity

Unit Cost

Amount

WOCD06

Rough-hewn cedar planks

42

$2.00

$84

SSF0304

Stainless steel fasteners

84

$0.50

42

AS222

Reinforced aluminum screens

20

$1.50

30

Total

$156

Requirement 2. Complete the labor time records for each of the employees. Once the labor time record is? completed, post the information relevant to Job 1102 to the Job Cost Record for Job Cost 1102.

Complete the labor time records for each of the employees. In Requirement 3 you will post the information relevant to Job 1102 to the Job Cost Record for Job Cost 1102. Begin with employee Greg Henderson.

Labor Time Record

Employee:

Greg Henderson

Week:

9/14-9/20

Hourly Wage Rate:

$14

Record #:

912

Date

Job number

Start Time

End Time

Hours

Cost

9/14

1102

8:00

12:00

4

$56

9/14

1103

12:00

4:00

4

$56

9/15 etc.

Now complete the labor time record for employee Andrew Peck.

Labor Time Record

Employee:

Andrew Peck

Week:

9/14-9/20

Hourly wage rate:

$7

Record #:

913

Date

Job number

Start Time

End Time

Hours

Cost

9/14

1101

8:00

1:00

5

$35

9/14

1102

1:00

4:00

3

$21

9/15

1103

8:00

10:00

2

$14

9/15 etc.

Requirement 3. Manufacturing overhead has already been added to the Job Cost Record. Complete the Job Cost Record by calculating the total job cost and the cost per unit. Remember that this job consisted of

3232

feeders?(units).Post the direct material information? (cost and requisition? number) from the Materials Requisition form and direct labor information relevant to Job 1102 to the Job Cost Record for Job Cost 1102. Complete the Job Cost Record by calculating the total job cost and the cost per unit. Remember that this job consisted of

3232

feeders? (units). ?(Round the cost per unit to the nearest? cent.)View the completed labor time records

LOADING...

.

Job Cost Record

Job Number:

1102

Customer:

Wild Birds, Inc.

Job description:

32 Model 3F (platform bird feeders)

Date Started:

Sep. 14

Date Completed:

Manufacturing Cost Information:

Cost Summary

Direct Materials

Req. # :

1250

$156

Direct Labor

No. #

912

No. #

913

Manufacturing Overhead

7 hours x $2 per direct labor hour

$14

Total Job Cost

Number of Units

÷

32

Cost per Unit

Solutions

Expert Solution

Labor Time Record
Employee: Greg Henderson Week: 9/14-9/20
Hourly Wage Rate: $14 Record #: 912
Date Job number Start Time End Time Hours Cost
14-Sep 1102 8:00 12:00 4 $56
14-Sep 1103 12:00 4:00 4 $56
9/15 etc. Total $112
Now complete the labor time record for employee Andrew Peck.
Labor Time Record
Employee: Andrew Peck Week: 9/14-9/20
Hourly wage rate: $7 Record #: 913
Date Job number Start Time End Time Hours Cost
14-Sep 1101 8:00 1:00 5 $35
14-Sep 1102 1:00 4:00 3 $21
15-Sep 1103 8:00 10:00 2 $14
9/15 etc. Total $70
Job Cost Record
Job Number: 1102
Customer: Wild Birds, Inc.
Job description: 32 Model 3F (platform bird feeders)
Date Started: Sep. 14 Date Completed:
Manufacturing Cost Information: Cost Summary
Direct Materials
Req. # : 1250 $156
Direct Labor
No. # 912 $56
No. # 913 $21
Manufacturing Overhead
7 hours x $2 per direct labor hour $14
Total Job Cost T $247
Number of Units N ÷ 32
Cost per Unit T/N $7.72
If any doubt please comment

Related Solutions

Bluebird Mfg. has received a special one-time order for 15,000 bird feeders at $2.10 per unit....
Bluebird Mfg. has received a special one-time order for 15,000 bird feeders at $2.10 per unit. Bluebird currently produces and sells 75,000 units at $6.10 each. This level represents 80% of its capacity. These bird feeders would be marketed under the wholesaler’s name and would not affect Bluebird’s sales through its normal channels. Production costs for these units are $3.45 per unit, which includes $1.80 variable cost and $1.65 fixed cost. If Bluebird accepts this additional business, the effect on...
A customer’s order is delivered (received by the customer) on September 10, 2019. This order was...
A customer’s order is delivered (received by the customer) on September 10, 2019. This order was placed with the company on June 5, 2019, and received by the manufacturing department on June 20, 2019. Actual production on the order began on July 10, 2019, and was completed August 10, 2019. Based on this information, calculate the following for this order: (a) total customer-response time (CRT), (b) order receipt time, (c) manufacturing lead (cycle) time, (d) manufacturing wait time, (e) manufacturing...
With this case, the specialty of several specialty retail stores is reviewed. The companies reviewed, and...
With this case, the specialty of several specialty retail stores is reviewed. The companies reviewed, and the year-end dates are as follows: 1. Abercrombie & Fitch Co. (January 31, 2009—52-week; February 2, 2008—52-week; February 3, 2007—53-week) “Abercrombie & Fitch Co…. is a specialty retailer that operates stores and websites selling casual sportswear apparel.” {10-K} 2. Limited Brands, Inc. (January 31, 2009—52-week; February 2, 2008—52-week; February 3, 2007—53-week) “We operate in the highly competitive specialty retail business.” {10-K} 3. GAP, Inc....
At the end of September, Northern Manufacturing received another special order from USD International. This special...
At the end of September, Northern Manufacturing received another special order from USD International. This special order offers to buy 750 ft2 of leather for $12.75 per square feet in October. However, since accepting this special order will exceed the leather processing capacity of Northern Manufacturing, another machine will be required to increase the capacity to 4,000 ft2 per month which will increase the fixed manufacturing costs by $3,000. Upon review of October’s production data of Northern Manufacturing, you have...
Firenza Company manufactures specialty tools to customer order. Budgeted overhead for the coming year is: Purchasing...
Firenza Company manufactures specialty tools to customer order. Budgeted overhead for the coming year is: Purchasing $40,000 Setups 37,500 Engineering 45,000 Other 40,000 Previously, Sanjay Bhatt, Firenza Company's controller, had applied overhead on the basis of machine hours. Expected machine hours for the coming year are 50,000. Sanjay has been reading about activity-based costing, and he wonders whether or not it might offer some advantages to his company. He decided that appropriate drivers for overhead activities are purchase orders for...
Overhead Rates, Unit Costs Folsom Company manufactures specialty tools to customer order. There are three producing...
Overhead Rates, Unit Costs Folsom Company manufactures specialty tools to customer order. There are three producing departments. Departmental information on budgeted overhead and various activity measures for the coming year is as follows: Welding Assembly Finishing Estimated overhead $220,000 $62,000 $150,000 Direct labor hours 4,500 10,000 6,000 Direct labor cost $90,000 $150,000 $120,000 Machine hours 5,000 1,000 2,000 Currently, overhead is applied on the basis of machine hours using a plantwide rate. However, Janine, the controller, has been wondering whether...
Concrete Creations manufactures concrete bird baths that are sold through retail outlets nationwide. The bird baths...
Concrete Creations manufactures concrete bird baths that are sold through retail outlets nationwide. The bird baths are made in a two-stage process. In the Forming Department, the concrete is poured into silicone molds where it is allowed to cure and set. Once set, the birdbaths are removed from the mold and sent to the Finishing Department where any imperfections are removed and the birdbaths are sprayed with a special sealant. Information for the Forming Department for the month of May...
1- Special Order Pope Company manufactures a variety of hiking boots and has received a special...
1- Special Order Pope Company manufactures a variety of hiking boots and has received a special one-time-only order from a new customer. Pope has sufficient idle capacity to accept the special order to manufacture 500 pairs of boots at a price of $45.00 per pair. Pope’s normal selling price is $65.00 per pair of boots. Variable manufacturing costs are $35.00 per pair and fixed manufacturing costs are $12.00 a pair. Pope’s variable selling expense for its normal line of boots...
Question text Special Order Pope Company manufactures a variety of hiking boots and has received a...
Question text Special Order Pope Company manufactures a variety of hiking boots and has received a special one-time-only order from a new customer. Pope has sufficient idle capacity to accept the special order to manufacture 1,500 pairs of boots at a price of $55.00 per pair. Pope’s normal selling price is $65.00 per pair of sneakers. Variable manufacturing costs are $35.00 per pair and fixed manufacturing costs are $12.00 a pair. Pope’s variable selling expense for its normal line of...
The Bancroft Company manufactures skateboards. Several weeks ago, the firm received a special-order inquiry from the...
The Bancroft Company manufactures skateboards. Several weeks ago, the firm received a special-order inquiry from the Kiger company. Kiger wants to market a skateboard similar to one of Bancroft’s models and has offered to purchase 11,000 units if the order can be completed in three months. The cost data for Bancroft’s model no. 5 skateboard follows: Cost Direct material(per unit) $8.20 Direct labor(per unit) $2.25 Total manufacturing overhead (per unit) $10.00 Total (per unit) $20.45 Additional Data: The normal selling...