In: Accounting
Feeders manufactures bird feeders for wild bird specialty stores. In? September,
WilsonWilson
Feeders received an order from Wild? Birds, Inc., for
3232
platform bird feeders. The order from Wild? Birds, Inc., became Job Number 1102 at
WilsonWilson
Feeders. A materials requisition for Job 1102 is presented to the right. In addition to the materials?requisition, the labor time records? (partial) for the week during which these feeders were made are presented. Other products were also being produced during that? week, so not all of the labor from that week belongs to Job 1102.??
LOADING...
?(Click the icon to view the materials? requisition.)
LOADING...
?(Click the icon to view the labor time? records.)
LOADING...
?(Click the icon to view the job cost? record.)Read the requirements
LOADING...
.
Requirement 1. Calculate the total for the Materials Requisition form. Post the information? (cost and requisition? number) from the Materials Requisition form to the Job Cost Record in the appropriate boxes.
Complete the Materials Requisition form. In Requirement 3 you will post the information? (cost and requisition? number) from the Materials Requisition form to the Job Cost Record in the appropriate boxes.
Materials Requisition |
|||||
Number: #1250 |
|||||
Date: |
9/14 |
||||
Job: |
1102 |
||||
Part number |
Description |
Quantity |
Unit Cost |
Amount |
|
WOCD06 |
Rough-hewn cedar planks |
42 |
$2.00 |
$84 |
|
SSF0304 |
Stainless steel fasteners |
84 |
$0.50 |
42 |
|
AS222 |
Reinforced aluminum screens |
20 |
$1.50 |
30 |
|
Total |
$156 |
Requirement 2. Complete the labor time records for each of the employees. Once the labor time record is? completed, post the information relevant to Job 1102 to the Job Cost Record for Job Cost 1102.
Complete the labor time records for each of the employees. In Requirement 3 you will post the information relevant to Job 1102 to the Job Cost Record for Job Cost 1102. Begin with employee Greg Henderson.
Labor Time Record |
||||||
Employee: |
Greg Henderson |
Week: |
9/14-9/20 |
|||
Hourly Wage Rate: |
$14 |
Record #: |
912 |
|||
Date |
Job number |
Start Time |
End Time |
Hours |
Cost |
|
9/14 |
1102 |
8:00 |
12:00 |
4 |
$56 |
|
9/14 |
1103 |
12:00 |
4:00 |
4 |
$56 |
|
9/15 etc. |
Now complete the labor time record for employee Andrew Peck.
Labor Time Record |
||||||
Employee: |
Andrew Peck |
Week: |
9/14-9/20 |
|||
Hourly wage rate: |
$7 |
Record #: |
913 |
|||
Date |
Job number |
Start Time |
End Time |
Hours |
Cost |
|
9/14 |
1101 |
8:00 |
1:00 |
5 |
$35 |
|
9/14 |
1102 |
1:00 |
4:00 |
3 |
$21 |
|
9/15 |
1103 |
8:00 |
10:00 |
2 |
$14 |
|
9/15 etc. |
Requirement 3. Manufacturing overhead has already been added to the Job Cost Record. Complete the Job Cost Record by calculating the total job cost and the cost per unit. Remember that this job consisted of
3232
feeders?(units).Post the direct material information? (cost and requisition? number) from the Materials Requisition form and direct labor information relevant to Job 1102 to the Job Cost Record for Job Cost 1102. Complete the Job Cost Record by calculating the total job cost and the cost per unit. Remember that this job consisted of
3232
feeders? (units). ?(Round the cost per unit to the nearest? cent.)View the completed labor time records
LOADING...
.
Job Cost Record |
|||
Job Number: |
1102 |
||
Customer: |
Wild Birds, Inc. |
||
Job description: |
32 Model 3F (platform bird feeders) |
||
Date Started: |
Sep. 14 |
Date Completed: |
|
Manufacturing Cost Information: |
Cost Summary |
||
Direct Materials |
|||
Req. # : |
1250 |
$156 |
|
Direct Labor |
|||
No. # |
912 |
||
No. # |
913 |
||
Manufacturing Overhead |
|||
7 hours x $2 per direct labor hour |
$14 |
||
Total Job Cost |
|||
Number of Units |
÷ |
32 |
|
Cost per Unit |
Labor Time Record | ||||||
Employee: | Greg Henderson | Week: | 9/14-9/20 | |||
Hourly Wage Rate: | $14 | Record #: | 912 | |||
Date | Job number | Start Time | End Time | Hours | Cost | |
14-Sep | 1102 | 8:00 | 12:00 | 4 | $56 | |
14-Sep | 1103 | 12:00 | 4:00 | 4 | $56 | |
9/15 etc. | Total | $112 | ||||
Now complete the labor time record for employee Andrew Peck. | ||||||
Labor Time Record | ||||||
Employee: | Andrew Peck | Week: | 9/14-9/20 | |||
Hourly wage rate: | $7 | Record #: | 913 | |||
Date | Job number | Start Time | End Time | Hours | Cost | |
14-Sep | 1101 | 8:00 | 1:00 | 5 | $35 | |
14-Sep | 1102 | 1:00 | 4:00 | 3 | $21 | |
15-Sep | 1103 | 8:00 | 10:00 | 2 | $14 | |
9/15 etc. | Total | $70 | ||||
Job Cost Record | ||||||
Job Number: | 1102 | |||||
Customer: | Wild Birds, Inc. | |||||
Job description: | 32 Model 3F (platform bird feeders) | |||||
Date Started: | Sep. 14 | Date Completed: | ||||
Manufacturing Cost Information: | Cost Summary | |||||
Direct Materials | ||||||
Req. # : | 1250 | $156 | ||||
Direct Labor | ||||||
No. # | 912 | $56 | ||||
No. # | 913 | $21 | ||||
Manufacturing Overhead | ||||||
7 hours x $2 per direct labor hour | $14 | |||||
Total Job Cost T | $247 | |||||
Number of Units N | ÷ | 32 | ||||
Cost per Unit T/N | $7.72 | |||||
If any doubt please comment |