In: Finance
The Camel Company is considering two mutually exclusive projects with the following cash flows. Assume discount rate of 12%.
Compute NPV, IRR, PI. Assume the discount rate is 12%. Please recommend the firm which project(s) to choose under the following scenarios:
Year | Project A cash flow | Project B Cash flow |
0 | -75,000 | $-60,000 |
1 | $30,000 | $25,000 |
2 | $35,000 | $30,000 |
3 | $35,000 | $25,000 |
A | B | C | |
1 | Year | Project A cash flow | Project B Cash flow |
2 | 0 | -$75,000.00 | -$60,000.00 |
3 | 1 | $30,000 | $25,000 |
4 | 2 | $35,000 | $30,000 |
5 | 3 | $35,000 | $25,000 |
6 | Rate | 0.12 | |
NPV | $4,599.81 | $4,031.75 | |
Using Excel formula | NPV(12%,B3:B5) | NPV(12%,C3:C5) | |
PI | 1.06 | 1.07 | |
Using Excel formula | 1+4599.81/75000 | 1+4031.75/60000 | |
IRR | 15.44% | 15.86% | |
Using Excel formula | IRR(B2:B5) | IRR(C2:C5) |
a) If independent project then both projects should be chosen
because NPV are both positive.
If the budget has 80,000 Project A should be accepted because NPV
of A is higher
b)If mutually exclusive project then Project A should be accepted.
If Budget is 80,000 Project A must be accepted because NPV is
higher.
c)
Year | 0 | 1 | 2 | 3 |
Project A cash flow | -$75,000.00 | $30,000 | $35,000 | $35,000 |
Cumulative Cash flow | -$75,000.00 | -45000.00 | -10000.00 | 25000.00 |
Pay Back Period | $2.29 | (Formula=2+10000/35000) | ||
Project B Cash flow | -$60,000.00 | $25,000 | $30,000 | $25,000 |
Cumulative Cash flow | -$60,000.00 | -35000.00 | -5000.00 | 20000.00 |
Pay Back Period | $2.20 | (Formula=2+5000/25000) |
Please Discuss in case of Doubt
Best of Luck. God Bless
Please Rate Well