In: Finance
The Camel Company is considering two mutually exclusive projects with the following cash flows. Assume discount rate of 12%.
Compute NPV, IRR, PI. Assume the discount rate is 12%. Please recommend the firm which project(s) to choose under the following scenarios:
| Year | Project A cash flow | Project B Cash flow | 
| 0 | -75,000 | $-60,000 | 
| 1 | $30,000 | $25,000 | 
| 2 | $35,000 | $30,000 | 
| 3 | $35,000 | $25,000 | 
| A | B | C | |
| 1 | Year | Project A cash flow | Project B Cash flow | 
| 2 | 0 | -$75,000.00 | -$60,000.00 | 
| 3 | 1 | $30,000 | $25,000 | 
| 4 | 2 | $35,000 | $30,000 | 
| 5 | 3 | $35,000 | $25,000 | 
| 6 | Rate | 0.12 | |
| NPV | $4,599.81 | $4,031.75 | |
| Using Excel formula | NPV(12%,B3:B5) | NPV(12%,C3:C5) | |
| PI | 1.06 | 1.07 | |
| Using Excel formula | 1+4599.81/75000 | 1+4031.75/60000 | |
| IRR | 15.44% | 15.86% | |
| Using Excel formula | IRR(B2:B5) | IRR(C2:C5) | 
a) If independent project then both projects should be chosen
because NPV are both positive.
If the budget has 80,000 Project A should be accepted because NPV
of A is higher
b)If mutually exclusive project then Project A should be accepted.
If Budget is 80,000 Project A must be accepted because NPV is
higher.
c)
| Year | 0 | 1 | 2 | 3 | 
| Project A cash flow | -$75,000.00 | $30,000 | $35,000 | $35,000 | 
| Cumulative Cash flow | -$75,000.00 | -45000.00 | -10000.00 | 25000.00 | 
| Pay Back Period | $2.29 | (Formula=2+10000/35000) | ||
| Project B Cash flow | -$60,000.00 | $25,000 | $30,000 | $25,000 | 
| Cumulative Cash flow | -$60,000.00 | -35000.00 | -5000.00 | 20000.00 | 
| Pay Back Period | $2.20 | (Formula=2+5000/25000) | 
Please Discuss in case of Doubt
Best of Luck. God Bless
Please Rate Well