Question

In: Finance

PART I: Suppose a firm is considering the following project (all figures in $ thousands): To...

PART I:

Suppose a firm is considering the following project (all figures in $ thousands):

To undertake the project the firm will need to make a one-time investment of $137,500 in year 0. This specialized equipment can be depreciated using the straight-line method over the seven years, with a salvage value of $5,600 in year 7.

Your sales and marketing team tell you that they estimate sales of 7,500 units in year 1, rising by roughly 35% per year through year 5, then declining by 45% each year through year 7. They assume the product is dead at that point, with 0 units demanded/sold in year 8.

The inflation rate is forecast to be 1.5% in year 1, rising by a constant to 2.8% in year 5, then leveling off. The firm’s real cost of capital is forecast to be 9.3% in year 1 and projected to increase by 2.5% each year through year 7. The tax rate is estimated to be a level 39%.

Sales revenue per unit is expected to be $15.30 in year 1. Variable cost per unit is estimated at $10.20 in year 1. Cash fixed costs will be $17,940 in year 1. All will grow with inflation.

What is the project NPV under these assumptions?

PART II:

Consider the same problem as above, but modify it as follows:

Direct labor, materials, selling expenses, and other variable costs are forecast to be $5.20, $4.70, $2.30, and $0.80, respectively in year 1 and grow with inflation.

Lease payment, property taxes, administration, advertising, and other cash fixed costs are expected to be $6,100, $1730, $4680, $2,120, and $2730, respectively in year 1 and grow with inflation.

What are the Total Variable Cost per Unit and Total Cash Fixed Costs?

PART III:

Consider the same problem as in Part II. Assume that the product life-cycle of seven years is a reasonable bet, but you are concerned about the real demand for your product. This is a fairly new product, and demand may be more or less than your sales team believes. Further, if this (and other) risky projects take longer than expected, the firm’s cost of capital may increase (because you are a ‘riskier’ borrower to your creditors).

Analyze the sensitivity of your project (NPV) to the unit sales factor and to the cost of capital. Draw some conclusions about the project given your sensitivity analysis. Your boss wants to know whether it’s a go or not, why you think so, and about which assumptions you are most concerned. Please explain.

** This was all the information given

Solutions

Expert Solution

PART 1:

1 2 3 4 5 6 7
Sales (Units) 7500.000 10125.000 13668.750 18452.813 24911.297 13701.213 7535.667
inflation 0.01500 0.01825 0.02150 0.02475 0.02800 0.02800 0.02800
cost of capital 0.0930 0.1180 0.1430 0.1680 0.1930 0.2180 0.2430
Tax rate 0.39 0.39 0.39 0.39 0.39 0.39 0.39
Sales/unit 15.300 15.579 15.914 16.308 16.765 17.234 17.717
VC/unit 10.200 10.386 10.609 10.872 11.176 11.489 11.811
FC 17940.000 18267.405 18660.154 19121.993 19657.409 20207.816 20773.635
Depriciation 18842.857 18842.857 18842.857 18842.857 18842.857 18842.857 18842.857
Sales (Amount) 114750 157739.6531 217526.9252 300929.4673 417629.9148 236127.9538 133506.7451
VC 76500 105159.7688 145017.9501 200619.6449 278419.9432 157418.6359 89004.49672
TC 94440.000 123427.174 163678.104 219741.638 298077.352 177626.452 109778.132
Profit before tax 1467.143 15469.622 35005.964 62344.972 100709.706 39658.645 4885.756
Profit after tax 894.95723 9436.469649 21353.63794 38030.43318 61432.92052 24191.77324 2980.3113
Salvage Value 5600.000
Taxes due to disposal of asset 2184.000
Incremental Net Cash Flows 19737.814 28279.327 40196.495 56873.290 80275.778 43034.630 25239.168
DCF 18058.384 22624.83691 26918.41559 30558.84828 33218.67474 13180.57468 5505.251186
NPV 12564.986

PART 2:

Year 1 2 3 4 5 6 7
VC/unit 13.000 13.237 13.522 13.857 14.244 14.643 15.053
VC 97500 134027.1563 184826.7991 255691.7043 354848.9472 200631.5947 113437.1037
FC 17360 17676.82 18056.87163 18503.7792 19021.88502 19554.4978 20102.02374

PART 3:

Yes with lesser sales as expected and higher cost of capital, the NPV will reduce. The factor which is most crucial for the project is demand of the product and the cost of the capital.


Related Solutions

A firm reported the following income statement (all figures arein thousands of dollars):Net Sales...
A firm reported the following income statement (all figures are in thousands of dollars):Net Sales1,100-operating costs200-depreciation & amortization230=Operating Income (EBIT)?-interest76=Earnings Before Taxes (EBT)?-taxes81=Net Income?What is the operating income of this firm?NOTE: the - and = in red have been added to serve as a hint on how to compute each item of interest.A firm reported the following income statement (all figures are in thousands of dollars):Net Sales1,550-operating costs200-depreciation & amortization220=Operating Income (EBIT)?-interest77=Earnings Before Taxes (EBT)?-taxes70=Net Income?What is the net income...
Part 1. Suppose your firm is considering investing in a project with the cash flows shown...
Part 1. Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 11 percent, and that the maximum allowable payback and discounted payback statistics for your company are 3 and 3.5 years, respectively. Time: 0 1 2 3 4 5 Cash flow: –$235,000 $65,800 $84,000 $141,000 $122,000 $81,200 Use the NPV decision rule to evaluate this project. (Do not round intermediate calculations...
A firm is considering the following investment project: Year Before Tax Cash Flow (thousands) 0 -1,000...
A firm is considering the following investment project: Year Before Tax Cash Flow (thousands) 0 -1,000 1 500 2 340 3 244 4 100 5 100 125 Salvage Value The project has a 5 year useful life with a $125,000 salvage value as shown. Double declining balance depreciation will be used. The combined income tax rate is 24% (21% federal, and 3% state). If the firm requires a 10% after tax rate of return, should this project be undertaken?
Imperium Chemicals Limited (ICL) is considering a new production project (all figures in $000s). The machine...
Imperium Chemicals Limited (ICL) is considering a new production project (all figures in $000s). The machine involved has an installed purchase price of $180. The machine will be depreciated straight-line over its life of 3 years, at the end of which time it will have a salvage value of $40. Cash sales from this new project will be $200 per year and cash costs will run to $110 per year. The firm will need to invest $70 in inventory when...
A firm is considering a project with the following information: Project will require purchase of a...
A firm is considering a project with the following information: Project will require purchase of a machine for $92,101.00 that is MACRS depreciable over a five-year schedule. (no depreciation until end of year 1). Project will require immediate non-depreciable expenses of $25,021.00 TODAY (year 0). Project will have the following projected balance sheet values of NWC: YEAR 0 1 2 NWC Level $4,000 9.00% of sales 8.00% of sales Sales for the project will be $54,556.00 per year, with all...
Porto Berhad is an all-equity firm. The company is considering the following projects: Project Beta Expected...
Porto Berhad is an all-equity firm. The company is considering the following projects: Project Beta Expected return Barcelona 0.70 11% Juventus 0.85 14% PSG 1.30 16% Chelsea 1.50 18% The T-bill rate is 9 percent and the expected return on the market is 12 percent. a.Evaluate which projects have higher expected return than the firm’s 12 percent cost of capital b. Assess which projects would be incorrectly accepted or rejected if the firm’s overall cost of capital were used as...
Suppose you have the following aircraft part failure time data (in thousands of hours). Part XRR-012...
Suppose you have the following aircraft part failure time data (in thousands of hours). Part XRR-012 failure times: 10.03 11.61 6.13 12.24 42.10 6.66 38.59 22.09 33.34 23.56 17.82 10.47 20.80 16.51 4.86 23.64* 40.50* 45.07* 41.57* 80.48* 12.48* 21.93* 45.03* 10.75* 7.76* 8.18* 38.20* 28.28* 18.55* 24.44* Where the asterisk (*) indicates the part is still active on an aircraft (that is, the part is in current use and has not failed yet). Describe how you would fit a...
Suppose you have the following aircraft part failure time data (in thousands of hours). Part XRR-012...
Suppose you have the following aircraft part failure time data (in thousands of hours). Part XRR-012 failure times: 10.03​​11.61​​ 6.13​​12.24​​42.10 6.66​​38.59​​22.09​​33.34​​23.56 17.82​​10.47​​20.80​​16.51​​ 4.86 23.64*​40.50*​45.07*​41.57*​80.48* 12.48*​21.93*​45.03*​10.75*​ 7.76* 8.18*​38.20*​28.28*​18.55*​24.44* Where the asterisk (*) indicates the part is still active on an aircraft (that is, the part is in current use and has not failed yet). a) Describe how you would fit a gamma distribution to the first 15 data points (first 3 rows of data). b) Your manager asks you to fit...
.   Suppose your firm is considering investing in a project with the cash flows shown as...
.   Suppose your firm is considering investing in a project with the cash flows shown as follows, that the required rate of return on projects of this risk class is 8 percent, and that the maximum allowable payback and discounted payback statistic for the project are three and three and a half years, respectively. Time 0 1 2 3 4 5 Cashflow -100,000 30,000 45,000 55,000 30,000 10,000 Calculate the payback and use the payback decision rule to evaluate this...
Suppose an all-equity financed firm has a cost of capital of 9.5%. The firm is considering...
Suppose an all-equity financed firm has a cost of capital of 9.5%. The firm is considering to invest in a new production facility to manufacture inputs for one of its core products, and has determined that the IRR of this investment equals 7.5%. Alternatively, the firm can acquire a supplier that makes the inputs. The acquisition would require an investment of $90 million and generate a free cash flow of $6.5 million indefinitely. The beta of both alternatives equals 0.9....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT