Question

In: Accounting

Formetal Engineering submitted to Presto a sample and specifications for precut polyurethane pads to be used...

Formetal Engineering submitted to Presto a sample and specifications for precut polyurethane pads to be used in making air-conditioning units. Formetal paid for the goods as soon as they were delivered but subsequently discovered that the pads did not conform to the sample and specifications in that there were incomplete cuts, color variances, and faulty adherence to the pad’s paper backing. Formetal then informed Presto of the defects and notified Presto that it would reject the pads and return them to Presto, but they were not returned for 125 days. Presto argued that it was denied the right to cure because the goods were not returned until some 125 days after Formetal promised to do so. Was there a breach of the contract? Did the buyer (Formetal) do anything wrong in seeking its remedies?

Solutions

Expert Solution

Facts of the Case: Formetal Engineering (Buyer) bought goods from Presto (Seller) insisting on the quality check of samples. However Buyer later found that the goods delivered are not as specified by it and not in a condition to use. Hence, it informed to seller that they will return the goods as they are not similar to sample provided. But, buyer returned goods to seller after 125 days from the date of intimation.

Conclusion: Presto (Seller) delivered the goods to Formetal (Buyer) which are different from the samples provided by it. In this case it is clearly evident that seller breached the contract as goods are delivered with incomplete cuts, color variances and faulty paper backings. Seller is liable to accept the returned goods from buyer.

However, if the agreement between buyer and seller mentions time for return of goods, they should be returned within the prescribed time period. And even if the agreement doesn't include the time period for return of goods, they should be returned within a reasonable time as per industry practices, otherwise buyer may lose the right to return the goods.


Related Solutions

Construction codes and specifications Discuss the importance of documentation in the construction and civil engineering industry....
Construction codes and specifications Discuss the importance of documentation in the construction and civil engineering industry. What method(s) are used to ensure proper documentation during construction?
A part must be 600 mm +2 mm long to meet engineering specifications. There has been...
A part must be 600 mm +2 mm long to meet engineering specifications. There has been a chronic problem with part lengths being out of specification − a problem that has caused poor-fitting assemblies down the production line and high scrap and rework rates. You are asked to do a capability analysis for two shifts. Using Minitab run Process Capability Analysis > Normal for each shift. Shift 1 Shift 2 599.62 600.28 600.47 600.14 600.83 601.21 599.85 599.58 600.54 599.57...
Specifications for a piece of material used in the manufacture of a bed mattress require that...
Specifications for a piece of material used in the manufacture of a bed mattress require that the piece be between a Lower and Upper value (in inches) centered around the process mean. The process that produces the piece yields a mean of 52 and a standard deviation of 0.7 inches. The distribution of output is normal. Within what values will 85.2 percent of sample means fall, if samples of n = 13 are taken and the process is in control?...
Specifications for a piece of material used in the manufacture of a bed mattress require that...
Specifications for a piece of material used in the manufacture of a bed mattress require that the piece be between a Lower and Upper value (in inches) centered around the process mean. The process that produces the piece yields a mean of 49 and a standard deviation of 1 inches. The distribution of output is normal. Within what values will 91.83 percent of sample means fall, if samples of n = 8 are taken and the process is in control?...
Specifications for a piece of material used in the manufacture of a bed mattress require that...
Specifications for a piece of material used in the manufacture of a bed mattress require that the piece be between a Lower and Upper value (in inches) centered around the process mean. The process that produces the piece yields a mean of 25 and a standard deviation of 0.6 inches. The distribution of output is normal. Within what values will 94.87 percent of sample means fall, if samples of n = 10 are taken and the process is in control?...
A sample of biological culture was submitted to a chemical laboratory for analysis of the percentage...
A sample of biological culture was submitted to a chemical laboratory for analysis of the percentage by weight of each major element. The composition of the cells by weight was found to be 48.9% C, 5.2% H, 24.8% O, 9.46% N, and 9.2% ash. Prepare an empirical formula for the cells Determine the COD/organic weight ratio for the cell Determine the theoretical oxygen demand including both COD and NOD (nitrification oxygen demand) If the organics are 80% biodegradable, what is...
A soil sample has been submitted to the lab for analysis and found to have a...
A soil sample has been submitted to the lab for analysis and found to have a total weight of 52 lbs, a total volume of 0.40 ft3, Weight of solids of 46 lbs and a specific gravity of 2.76. What is the void ratio? Prepare a phase diagram as well
The building specifications in a certain city require that the sewer pipe used in residential areas...
The building specifications in a certain city require that the sewer pipe used in residential areas have a mean breaking strength of more than 2500 pounds per lineal foot. A manufacturer who would like to supply the city with sewer pipe has submitted a bid and provided the following information: An independent contractor randomly selected seven sections of the manufacturer’s pipe and tested each for breaking strength. The results (pounds per lineal foot) are as follows: 2610, 2750, 2420, 2510,...
Make a search about a materials used on engineering (Civil Engineering), the search must includes: The...
Make a search about a materials used on engineering (Civil Engineering), the search must includes: The type of materials which used to fabricate the device The structure type The composition The function The advantage The disadvantage The limitation of used The problem in service The new research on the field
PAGE 1 Table 11-1 Boat Specifications Spring 2020 Group_Project MET 405 - Economic Analysis for Engineering...
PAGE 1 Table 11-1 Boat Specifications Spring 2020 Group_Project MET 405 - Economic Analysis for Engineering and Technology Total points: 100 Due Date: April 23, 2020 by 11:59 pm Project Case: Harbor Delivery Service (HDS) is an over the water delivery service operating in several large port/metropolitan areas. Each branch office has from 5 to 15 boats in its fleet. Currently, each branch office purchases its boats locally based on the branch manager’s preferences. This has resulted in each branch...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT