In: Accounting
Question 2 Alexia Muchala Ltd has two production departments, A and B, and two service departments, X and Y. The budgeted activity levels for June 2020 were thus: A 2000 hours N$ 80,000 B 12,000 hours N$ 48,000 The service departments are apportioned thus: X 70% to A 20% to B 10% to Y Y 50% to A 30% to B 20% to X During June 2020 the actual results were: A 2100 hours N$ 60,000 B 11,500 hours N$ 40,000 X N$ 25,000 Y N$ 15,000 2 Required: a) Calculate the budgeted overhead absorption rate per hour for each of the production departments. b) Calculate the amount of overhead to be charged to each of the production departments. c) Calculate the Actual overhead absorption rate per hour for each of the production departments. d) Calculate the amount of under or over absorption of overhead for each of the production departments. (Total 25 marks)
a) the budgeted overhead absorption rate per hour for each of the production departments is calculated as :
for department A: total budgeted OH = 80000 + 70% of 25000 + 50% of 15000 = 105000
activity level budgeted = 2000
budgeted overhead absorption rate per hour = total budgeted overhead/activity level = 105000/2000 = 52.5
for department B: total budgeted OH = 48000+20% of 25000+30% of 15000 = 57500
activity level budgeted = 12000
budgeted overhead absorption rate per hour = total budgeted overhead/activity level =57500/12000= 4.79
b) the amount of overhead to be charged to each of the production departments is calculated as :
for A: 70% of 257000+ 50% of 15000 + 60000 = 85000
for B: 20% of 25000+30% of 15000+40000 = 49500
c) the Actual overhead absorption rate per hour for each of the production departments is calculated as:
for A: 85000/ 2100 = 40.48
for B: 49500/11500 =4.3
d) the amount of under or over absorption of overhead for each of the production departments can be calculated as:
for department A: total budgeted OH = 80000 + 70% of 25000 + 50% of 15000 = 105000
actual OH = 70% of 257000+ 50% of 15000 + 60000 = 85000
the amount of under or over absorption of overhead = actual OH - budgeted OH = 85000-105000 = -20000 over absorbed.
for department B: total budgeted OH = 48000+20% of 25000+30% of 15000 = 57500
actual OH = 20% of 25000+30% of 15000+40000 = 49500
the amount of under or over absorption of overhead = actual OH - budgeted OH = 49500-57500 = -8000 over absorbed.
NOTE: If the absorbed overheads at predetermined rates are greater than actual overheads, this is known as OVER-ABSORPTION. Conversely, if absorbed overheads are less than the actual overheads, this is known as UNDERABSORPTION.