Question

In: Accounting

When would a variance be labeled as favorable? A. When standard costs are less than actual...

When would a variance be labeled as favorable?

A. When standard costs are less than actual costs

B. When estimated costs are greater than actual costs

C. When actual costs are less than standard costs

D. When standard costs are equal to actual costs

Solutions

Expert Solution

The Correct answer is C - When actual costs are less than standard costs.

Actual Costs - These costs are incurred by the company while performing day to day operations.

Standard Costs - These are the estimates of cost that would be incurred while manufacturing a product or while providing services. Standard costs are predetermined. These costs are used in estimating future income of a company.

Whenever Actual costs would be lower than Standard costs the variance will be Favorable.

A company usually sets the standard cost before entering into actual production process. Therefore the company sets what the future costs should be so that their financial planning can be achieved. However the actual costs would be those costs that would actually incur during the production process. It may be higher or lower as compared to the Standard Cost. When Actual costs will be less than Standard cost it would mean that company has actually saved on cost. The company was expecting cost to be higher but in actual they were lower as compared to their estimates. Thereby resulting into a Favorable Variance.

Thus it can be concluded that when actual costs are less than standard costs a variance would be labeled as favorable.


Related Solutions

32. An example of a favorable variance is ________. A) actual revenues are less than expected...
32. An example of a favorable variance is ________. A) actual revenues are less than expected revenues B) actual expenses are less than expected expenses C) actual material prices are greater than expected material prices D) expected labor costs are less than actual labor costs 36. The activity-based budgeting system emphasizes ________. A) the resources needed by a company B) the preparation of budgets by function C) the attainment of long-range goals D) activities and their consumption of resources 39....
10. LO 8.2When is the material quantity variance favorable? when the actual quantity used is greater...
10. LO 8.2When is the material quantity variance favorable? when the actual quantity used is greater than the standard quantity when the actual quantity used is less than the standard quantity when the actual price paid is greater than the standard price when the actual price is less than the standard price 12. LO 8.3What are some possible reasons for a labor rate variance? hiring of less qualified workers an excess of material usage material price increase utilities usage change...
We have learned about Standard costs and associated variances in this chapter. Can a favorable variance...
We have learned about Standard costs and associated variances in this chapter. Can a favorable variance be a bad thing? Describe a realistic scenario where a favorable variance could be detrimental(have unwanted consequences elsewhere in the business).
A favorable direct materials price variance indicates which of the​ following: A. The actual quantity of...
A favorable direct materials price variance indicates which of the​ following: A. The actual quantity of material used was less than the standard quantity of material used. B. The standard cost of materials purchased was greater than the actual cost of materials purchased. C. The actual cost of materials purchased was greater than the standard cost of materials purchased. D. The standard cost of materials purchased was less than the actual cost of materials purchased.
T/F The variance of an asset's return can be less than the standard deviation of that...
T/F The variance of an asset's return can be less than the standard deviation of that asset's return. If an investor owns two stocks, one whose standard deviation is 0.21 and the other whose standard deviation is 0.10, the required return will be higher for the stock with the higher standard deviation. Different investors have different degrees of risk aversion, and the result is that investors with greater risk aversion tend to hold securities with lower risk (and therefore a...
Difference Manufacturing Costs Budget Actual Favorable Unfavorable Neither Favorable nor Unfavorable Variable costs    Direct materials $50,840...
Difference Manufacturing Costs Budget Actual Favorable Unfavorable Neither Favorable nor Unfavorable Variable costs    Direct materials $50,840 $49,840 $1,000 Favorable    Direct labor 55,800 52,500 3,300 Favorable    Indirect materials 27,280 27,480 200 Unfavorable    Indirect labor 18,600 18,180 420 Favorable    Utilities 18,600 18,460 140 Favorable    Maintenance 9,920 10,220 300 Unfavorable       Total variable 181,040 176,680 4,360 Favorable Fixed costs    Rent 11,700 11,700 –0– Neither Favorable nor Unfavorable    Supervision 18,600 18,600 –0– Neither Favorable nor Unfavorable    Depreciation 7,700 7,700 –0– Neither Favorable nor Unfavorable       Total...
1. Identify the situation below that will result in a favorable variance. Multiple Choice Actual revenue...
1. Identify the situation below that will result in a favorable variance. Multiple Choice Actual revenue is higher than budgeted revenue. Actual revenue is lower than budgeted revenue. Actual income is lower than expected income. Actual costs are higher than budgeted costs. Actual expenses are higher than budgeted expenses. 2 Hassock Corp. produces woven wall hangings. It takes 2 hours of direct labor to produce a single wall hanging. Hassock’s standard labor cost is $12 per hour. During August, Hassock...
1. A variance caused by using more or less than the standard amount of direct materials...
1. A variance caused by using more or less than the standard amount of direct materials to produce your product. Labor efficiency variance labor rate variance materials usage variance materials price variance 2. What details future plans for the acquisition of assets? Cash budget sales budget operating budget capital budget 3. A variance caused by using more or less than the standard amount of direct labor hours to produce your product. materials price variance materials usage variance labor rate variance...
Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come...
Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come from material costs that are higher or lower than expected, material usage that is not what was expected, higher or lower labor costs than expected, or more or less time spent to produce an item than expected. Overhead cost and volume variances are another cause for costs to be higher or lower than what was expected. The total manufacturing variance can be broken down...
The standard costs and actual costs for direct materials for the manufacture of 2,700 actual units...
The standard costs and actual costs for direct materials for the manufacture of 2,700 actual units of product are Standard Costs Direct materials (per completed unit) 1,040 kilograms @$8.64 Actual Costs Direct materials 2,700 kilograms @ $8.20 Round your final answer to the nearest dollar. The amount of direct materials price variance is a.$458 favorable b.$458 unfavorable c.$1,188 unfavorable d.$1,188 favorable
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT