In: Accounting
Umanzor Corporation uses activity-based costing to assign overhead costs to products. Overhead costs have already been allocated to the company's three activity cost pools as follows: Processing, $50,500; Supervising, $28,600; and Other, $24,700. Processing costs are assigned to products using machine-hours (MHs) and Supervising costs are assigned to products using the number of batches. The costs in the Other activity cost pool are not assigned to products. Activity data appear below: |
MHs (Processing) | Batches (supervising) | |
Product S5 | 10,900 | 1,420 |
Product F5 | 890 | 510 |
Total |
11,790 |
1,930 |
What is the overhead cost assigned to Product S5 under activity-based costing? (Round your intermediate calculations to 2 decimal places.) |
a.$21,044.40
b. $67,696.40
c. $52,228.40
d. $46,652.00
Umanzor Corporation uses activity-based costing to assign overhead costs to products. Overhead costs have already been allocated to the company's three activity cost pools as follows: Processing, $51,500; Supervising, $35,800; and Other, $26,600. Processing costs are assigned to products using machine-hours (MHs) and Supervising costs are assigned to products using the number of batches. The costs in the Other activity cost pool are not assigned to products. Activity data appear below: |
MHs (Processing) | Batches (supervising) | |
Product S5 | 15,300 | 1,060 |
Product F5 | 1,180 | 820 |
Total |
16,480 |
1,880 |
The activity rate for the Processing activity cost pool under activity-based costing is closest to: |
$2.81 per MH
$3.43 per MH
$3.13 per MH
$7.56 per MH
Calculation of Activity Rate
No. of activity drivers |
||||||
Overheads |
Amount (A) |
Activity driver |
Product S5 |
Product F5 |
Total no of drivers (B) |
Activity rate (A/B) |
Processing |
50500 |
MHs |
10900 |
890 |
11790 |
4.28 |
Supervising |
28600 |
Batches |
1420 |
510 |
1930 |
14.82 |
Other |
24700 |
N/A |
0 |
0 |
N/A |
Calculation of cost assigned on the basis of above Activity Rate
Product S5 |
|||
Cost |
Rate per driver |
No of driver |
Cost assigned |
Processing |
4.28 |
10900 |
46652 |
Supervising |
14.82 |
1420 |
21044.4 |
Other |
0 |
0 |
0 |
Total cost assigned |
67696.4 |
Hence, the correct answer is $67696.40 (OPTION – B)
Calculation of Activity rate
No. of activity drivers |
||||||
Overheads |
Amount (A) |
Activity driver |
Product S5 |
Product F5 |
Total no of drivers (B) |
Activity Rate (A/B) |
Processing |
51500 |
MHs |
15300 |
1180 |
16480 |
3.125 |
Supervising |
35800 |
Batches |
1060 |
820 |
1880 |
19.04255 |
Other |
26600 |
N/A |
0 |
0 |
N/A |
Since, the activity rate for PROCESSING is asked which is coming as $3.125 per MHs, the CORRECT ANSWER is OPTION – C $3.13 per MH as it is the closest to the figure calculated above.