Question

In: Accounting

On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,330,000. During 2021, costs of $2,110,000 were incurred with estimated costs of $4,110,000 yet to be incurred. Billings of $2,610,000 were sent, and cash collected was $2,360,000.

In 2022, costs incurred were $2,610,000 with remaining costs estimated to be $3,765,000. 2022 billings were $2,860,000 and $2,585,000 cash was collected. The project was completed in 2023 after additional costs of $3,910,000 were incurred. The company’s fiscal year-end is December 31. Arrow recognizes revenue over time according to percentage of completion.

Required:
1. Compute the amount of revenue and gross profit or loss to be recognized in 2021, 2022, and 2023 using the percentage of completion method.
2a. Prepare journal entries for 2021 to record the transactions described (credit "various accounts" for construction costs incurred).
2b. Prepare journal entries for 2022 to record the transactions described (credit "various accounts" for construction costs incurred).
3a. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2021.
3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2022.

Solutions

Expert Solution

Solution 1:
Percentage of Completion
Choose Numerator / Choose Denominator = % of completion to date
Cost incurred to date / Total estimated costs = % of completion to date
2021 $2,110,000 / $6,220,000 = 33.92%
2022 $4,720,000 / $8,485,000 = 55.63%
2023 $8,630,000 / $8,630,000 = 100.00%
2021
To Date Recognized in Prior Years Recognized in 2021
Construction revenue $2,825,772 $0 $2,825,772
Construction expense $2,110,000 $0 $2,110,000
Gross Profit (Loss) $715,772 $0 $715,772
2022
To Date Recognized in Prior Years Recognized in 2022
Construction revenue $4,633,777 $2,825,772 $1,808,006
Construction expense $4,788,777 $2,110,000 $2,678,777
Gross Profit (Loss) -$155,000 $715,772 -$870,772
2023
To Date Recognized in Prior Years Recognized in 2023
Construction revenue $8,330,000 $4,633,777 $3,696,223
Construction expense $8,630,000 $4,788,777 $3,841,223
Gross Profit (Loss) -$300,000 -$155,000 -$145,000
Solution 2a:
Journal Entries - Arrow Construction Company - 2021
Event Particulars Debit Credit
1 Construction in Progress Dr $2,110,000
       To Various Accounts $2,110,000
(To record construction cost incurred)
2 Accounts receivables Dr $2,610,000
       To Billings on construction contract $2,610,000
(To record progress billings)
3 Cash Dr $2,360,000
       To Accounts receivables $2,360,000
(To record collection from customer)
4 Construction in Progress Dr $715,772
Cost of construction Dr $2,110,000
       To Revenue from long term contracts $2,825,772
(To record revenue and gross profit)
Solution 2b:
Journal Entries - Arrow Construction Company - 2022
Event Particulars Debit Credit
1 Construction in Progress Dr $2,610,000
       To Various Accounts $2,610,000
(To record construction cost incurred)
2 Accounts receivables Dr $2,860,000
       To Billings on construction contract $2,860,000
(To record progress billings)
3 Cash Dr $2,585,000
       To Accounts receivables $2,585,000
(To record collection from customer)
4 Cost of construction Dr $2,678,777
       To Construction in Progress $870,772
       To Revenue from long term contracts $1,808,006
(To record revenue and gross profit)
Solution 3a & 3b:
Arrow construction company
Balance Sheet (Partial)
As on December 31
Particulars 2021 2022
Assets:
Current Assets:
Accounts Receivables
2021 - $2,610,000 - $2,360,000
2022 - $250,000 + $2,860,000 - $2,585,000
$250,000 $525,000
Cost and Profit in excess of billing
2021 - $2,825,772 - $2,610,000
$215,772
Liabilities and stockholder's equity:
Current liabilities:
Billings in excess of costs and profits
($2,860,000 - $2,610,000 + $870,772 - $215,772)
$905,000

Related Solutions

On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,050,000. During 2021, costs of $2,020,000 were incurred, with estimated costs of $4,020,000 yet to be incurred. Billings of $2,524,000 were sent, and cash collected was $2,270,000. In 2022, costs incurred were $2,524,000 with remaining costs estimated to be $3,630,000. 2022 billings were $2,774,000, and $2,495,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,225,000. During 2021, costs of $2,090,000 were incurred, with estimated costs of $4,090,000 yet to be incurred. Billings of $2,608,000 were sent, and cash collected was $2,340,000. In 2022, costs incurred were $2,608,000 with remaining costs estimated to be $3,735,000. 2022 billings were $2,858,000, and $2,565,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,480,000. During 2021, costs of $2,160,000 were incurred with estimated costs of $4,160,000 yet to be incurred. Billings of $2,660,000 were sent, and cash collected was $2,410,000. In 2022, costs incurred were $2,660,000 with remaining costs estimated to be $3,840,000. 2022 billings were $2,910,000 and $2,635,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,375,000. During 2021, costs of $2,150,000 were incurred, with estimated costs of $4,150,000 yet to be incurred. Billings of $2,680,000 were sent, and cash collected was $2,400,000. In 2022, costs incurred were $2,680,000 with remaining costs estimated to be $3,825,000. 2022 billings were $2,930,000, and $2,625,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,150,000. During 2021, costs of $2,050,000 were incurred with estimated costs of $4,050,000 yet to be incurred. Billings of $2,550,000 were sent, and cash collected was $2,300,000. In 2022, costs incurred were $2,550,000 with remaining costs estimated to be $3,675,000. 2022 billings were $2,800,000 and $2,525,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,475,000. During 2021, costs of $2,190,000 were incurred, with estimated costs of $4,190,000 yet to be incurred. Billings of $2,728,000 were sent, and cash collected was $2,440,000. In 2022, costs incurred were $2,728,000 with remaining costs estimated to be $3,885,000. 2022 billings were $2,978,000, and $2,665,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,175,000. During 2021, costs of $2,070,000 were incurred, with estimated costs of $4,070,000 yet to be incurred. Billings of $2,584,000 were sent, and cash collected was $2,320,000. In 2022, costs incurred were $2,584,000 with remaining costs estimated to be $3,705,000. 2022 billings were $2,834,000, and $2,545,000 cash was collected. The project was completed in 2023 after additional costs of...