In: Accounting
Figure 4-10 The Manoli Company has collected the following data for use in calculating product costs: Activity Data: (expected and actual) rug cleaners sweepers total units produced 100,000 250,000 350,000 prime costs $200,000 $584,000 $784,000 direct labor hours 10,000 40,000 50,000 machine hours 20,000 10,000 30,000 number of setups 25 75 100 inspection hours 1,600 2,400 4,000 number of moves 140 160 300 Departmental Data: (expected and actual) molding assembly total direct labor hours rug cleaners 5,000 5,000 10,000 sweepers 5,000 35,000 40,000 total 10,000 40,000 50,000 |
||
machine hours rug cleaners 17,000 3,000 20,000 sweepers 3,000 7,000 10,000 total 20,000 10,000 30,000 overhead costs machining $130,000 $ 40,000 $170,000 moving materials 50,000 40,000 90,000 setting up 80,000 20,000 100,000 inspecting products 30,000 40,000 70,000 total 290,000 $140,000 $430,000 |
||
25. Refer to Figure 4-10. Manoli Company uses departmental overhead rates: Molding uses machine hours and Assembly uses labor hours. What is the unit product cost for sweepers if departmental overhead rates are used?
A) 3.50
B) 8.50
c) 2.59
D)1.40
26. Refer to Figure 4-10. What are the consumption ratios for rug cleaners and sweepers respectively for the inspection of products activity?
a) 3;7
b) 2:8
c)4:6
d) 67: 33
27. Refer to Figure 4-10. What are the consumption ratios for rug cleaners for the departments on the basis of the departmental drivers (molding; assembly)?
a) .33, .87
b) .85, .125
c) .33, .25
d) .85, .5
Solution 25:
Predetermined overhead rate of Molding = Estimated overhead / Estimated machine hours
= $290,000 / 20000 = $14.50 per machine hour
Predetermined overhead rate of assembly = Estimated overhead / Estimated direct labor hours
= $140,000 / 40000 = $3.50 per labor hours
Computation of Unit Product cost - Sweeper | |
Particulars | Amount |
Prime cost | $584,000.00 |
Overhead - Molding (3000*$14.50) | $43,500.00 |
Overhead - Assembly (35000*$3.50) | $122,500.00 |
Total cost | $750,000.00 |
Nos of units | 250000 |
Cost per unit | $3.00 |
Solution 26:
Consumption ratio of rug cleaners and sweepers respectively for the inspection of products activity = Consumption ratio of inspection hours = 1600 : 2400 = 4:6
Hence option c is correct.
Solution 27:
Consumption ratio of rug cleaner for the department on basis fo departmental drivers
Modling = Nos of machine hours for rug cleaner / Total machine hours = 17000/20000 = 0.85
Assembly = Nos of labor hours for rug cleaner / Total labor hours = 5000 / 40000 = 0.125
Hence option b is correct.