Question

In: Finance

please write all formulas and show your work without using excel Using the information in Question...

please write all formulas and show your work without using excel

Using the information in Question 1, what is the break-even market size for the project? Show your work, and round to the nearest unit.

Refer to question 1:

  1. Consider a project with annual expected income based on approximately $125 million in revenue and approximately $77.5 million in total variable cost. You realize that both of these numbers are projected, and that your projections may be incorrect. Your boss wants you to conduct a sensitivity analysis to determine whether the project is a winner. You are entering an established market, and you know the market size will be 1,000,000 units. You are unsure of your exact market share, the price you will be able to charge, and your variable cost per unit, but have determined a range of possible values for each (in the table below). Your initial investment cost is $165 million, but you already own the plant and equipment, which are fully depreciated. Your fixed costs will be $2 million per year. There are no new NWC requirements, and there will be no salvage value because the project does not have a finite lifetime. The tax rate is 35%. The discount rate is 17%. Use the following table to conduct a full sensitivity analysis for the project. Make sure to include the NPV for the expected outcome in your analysis. Also calculate the best- and worst-case scenarios, but assume that cash flows will increase at 0.5% per year over the life of the project for these two scenarios. What are the results of this analysis?

Pessimistic

Expected

Optimistic

Market Share

3.9%

5.0%

6.1%

Price/unit

$2410

$2500

$2590

VC/Unit

$1980

$1550

$960

Solutions

Expert Solution

1) => Pessimistic Scenario

Market Size = 1,000,000

Market share = 3.9%

Expected Sales in Units = 3.9% * 1,000,000 = 39,000

Price per unit = 2,410 | Total Sales = 39,000 * 2,410 = 93,990,000

Variable Cost per unit = 1,980 | Total Variable Costs = 39,000 * 1,980 = 77,220,000

Contribution Margin = Sales - Variable Costs = 93,990,000 - 77,220,000 = 16,770,000

Fixed Costs = 2,000,000

Operating Profit = Contribution Margin - Fixed Costs = 16,770,000 - 2,000,000 = 14,770,000

Since, there are no new NWC requirements and even though, the initial cost is 165 million, howver, we already own the assets which is fully depreciated. Hence, no NWC and Depreciation will be used in calculation of cashflow.

Cashflow = 14,770,000 * (1 - Tax rate) = 14,770,000 * (1 - 35%) = 9,600,500

Since project has no finite life, we will calculate the cashflow's present value as a Perpetuity

Formula of Perpetuity = CF / R

Discount rate = 17%

PV of the Cashflows = 9,600,500 / 17% = 56,473,529.41

NPV = PV of all cashflows - Initial cost = 56,473,529.41 - 165,000,000

NPV of the Project in Pessimistic Scenario = -108,526,470.59

=> Expected Scenario

Market Size = 1,000,000

Market share = 5%

Expected Sales in Units = 5% * 1,000,000 = 50,000

Price per unit = 2,500 | Total Sales = 50,000 * 2,500 = 125,000,000

Variable Cost per unit = 1,550 | Total Variable Costs = 50,000 * 1,550 = 77,500,000

Contribution Margin = Sales - Variable Costs = 125,000,000 - 77,500,000 = 47,500,000

Fixed Costs = 2,000,000

Operating Profit = Contribution Margin - Fixed Costs = 47,500,000 - 2,000,000 = 45,500,000

Since, there are no new NWC requirements and even though, the initial cost is 165 million, howver, we already own the assets which is fully depreciated. Hence, no NWC and Depreciation will be used in calculation of cashflow.

Cashflow = 45,500,000 * (1 - Tax rate) = 45,500,000 * (1 - 35%) = 29,575,000

Since project has no finite life, we will calculate the cashflow's present value as a Perpetuity

Formula of Perpetuity = CF / R

Discount rate = 17%

PV of the Cashflows = 29,575,000 / 17% = 173,970,588.24

NPV = PV of all cashflows - Initial cost = 173,970,588.24 - 165,000,000

NPV of the Project in Expected Scenario = $ 8,970,588.24

=> Optimistic Scenario

Market Size = 1,000,000

Market share = 6.1%

Expected Sales in Units = 6.1% * 1,000,000 = 61,000

Price per unit = 2,590 | Total Sales = 61,000 * 2,590 = 157,990,000

Variable Cost per unit = 960 | Total Variable Costs = 61,000 * 960 = 58,560,000

Contribution Margin = Sales - Variable Costs = 157,990,000 - 58,560,000 = 99,430,000

Fixed Costs = 2,000,000

Operating Profit = Contribution Margin - Fixed Costs = 99,430,000 - 2,000,000 = 97,430,000

Since, there are no new NWC requirements and even though, the initial cost is 165 million, howver, we already own the assets which is fully depreciated. Hence, no NWC and Depreciation will be used in calculation of cashflow.

Cashflow = 97,430,000 * (1 - Tax rate) = 97,430,000 * (1 - 35%) = 63,329,500

Since project has no finite life, we will calculate the cashflow's present value as a Perpetuity

Formula of Perpetuity = CF / R

Discount rate = 17%

PV of the Cashflows = 63,329,500 / 17% = 372,526,470.6

NPV = PV of all cashflows - Initial cost = 372,526,470.6 - 165,000,000

NPV of the Project in Optimistic Scenario = $ 207,526,470.6

Worst-Case Scenario: Pessimistic Scenario has the lowest NPV of -108,526,470.59, therefore, it is the worst case scenario.

Best-Case Scenario: Optimistic scenario has the highest NPV of 207,526,470.6, therefore, it is the best case scenario.

Using a growth rate of 0.5% for Best and Worst case scenario.

=> Best Case Scenario with 0.5% growth

Cashflow in Best Case or Optimistic Scenario = 63,329,500

Instead of stable perpetuity, we will use growing perpetuity formula

Growing Perpetuity formula = CF0 * (1+growth) / (rate - growth)

PV of the Cashflows = 63,329,500 * (1 + 0.5%) / (17% - 0.5%) = 385,734,227.27

NPV = PV of all cashflows - Initial cost = 385,734,227.27 - 165,000,000

NPV for Best case 0.5% growth in Cashflows = $220,734,227.27

=> Worst Case Scenario with 0.5% growth

Cashflow in Worst Case or Pessimistic Scenario = 9,600,500

Instead of stable perpetuity, we will use growing perpetuity formula

Growing Perpetuity formula = CF0 * (1+growth) / (rate - growth)

PV of the Cashflows = 9,600,500 * (1 + 0.5%) / (17% - 0.5%) = 58,475,772.73

NPV = PV of all cashflows - Initial cost = 58,475,772.73 - 165,000,000

NPV for Worst case 0.5% growth in Cashflows = - $106,524,227.27

2) To find the break-even market size of the project, we need to go in the reverse direction to find the the break-even point.

The break-even point is where project's NPV is 0 (zero).

As NPV = PV of all CFs - Initial cost, therefore, at zero NPV, PV of all CFs = 165,000,000

Using perpetuity formula and discount rate of 17%, we can find the cashflow required for break-even

PV = CF / R

=> 165,000,000 = CF / 17%

Cashflow for breakeven = 28,050,000

As Cashflow for this question = Operating Profit * (1-tax rate)

Therefore, 28,050,000 = OP * (1 - 35%)

Operating Profit = 28,050,000 / 0.65 = 43,153,846.15

Operating Profit = Contribution Margin - Fixed Costs

As Contribution margin = (Price per unit - Variable costs per unit) * Number of units

=> Pessimistic Scenario

Putting values of Pessimistic scenario in the formula

=> 43,153,846.15 = (Price per unit - Variable costs per unit) * Number of units - Fixed costs

=> Fixed costs = (Price per unit - Variable costs per unit) * Number of units

=> 43,153,846.15 + 2,000,000 = (2410 - 1980) * N

=> Number of units for break-even = 45,153,846.15 / 430 = 105,008.9 units or 105,009 units

If we go in reverse and use market share of 3.9%, we can find market size required for break-even

=> Number of units = Market Share * Market Size in units

=> 105,009 = 3.9% * Market Size

Market size for break-even in Pessimistic scenario = 105,009 / 3.9% = 2,692,538.5 or 2,692,539 units

=> Expected Scenario

Putting values of Expected scenario in the formula

=> 43,153,846.15 = (Price per unit - Variable costs per unit) * Number of units - Fixed costs

=> Fixed costs = (Price per unit - Variable costs per unit) * Number of units

=> 43,153,846.15 + 2,000,000 = (2500- 1550) * N

=> Number of units for break-even = 45,153,846.15 / 950 = 47,530.4 or 47,530 units

If we go in reverse and use market share of 5%, we can find market size required for break-even

=> Number of units = Market Share * Market Size in units

=> 47,530 = 5% * Market Size

Market size for break-even in Expected scenario = 47,530 / 5% = 950,600 units

=> Expected Scenario

Putting values of Optimistic scenario in the formula

=> 43,153,846.15 = (Price per unit - Variable costs per unit) * Number of units - Fixed costs

=> Fixed costs = (Price per unit - Variable costs per unit) * Number of units

=> 43,153,846.15 + 2,000,000 = (2590 - 960) * N

=> Number of units for break-even = 45,153,846.15 / 1630 = 27,701.75 or 27,702 units

If we go in reverse and use market share of 6.1%, we can find market size required for break-even

=> Number of units = Market Share * Market Size in units

=> 27,702 = 6.1% * Market Size

Market size for break-even in Optimistic scenario = 27,702 / 6.1% = 454,131.15 or 454,131 units


Related Solutions

PLEASE SHOW ALL WORK IN EXCEL!!!!!!! SHOW CALCULATIONS / FORMULAS IN EXCEL!!!!!!!! Voters arrive at a...
PLEASE SHOW ALL WORK IN EXCEL!!!!!!! SHOW CALCULATIONS / FORMULAS IN EXCEL!!!!!!!! Voters arrive at a polling station at an average of 4 per minute (Poisson) where the service rate is 50 per hour (Poisson). a. What is the average number of voters in the system with 5 voter booths? (10 pts) b. What is the minimum number of voting booths needed to keep the average time in the system under three minutes? (10 pts) PLEASE SHOW ALL WORK IN...
Please use excel and show all work and formulas. (I will give your work a like...
Please use excel and show all work and formulas. (I will give your work a like if you do this) Size (1000s sq. ft) Selling Price ($1000s) 1.26 117.5 3.02 299.9 1.99 139.0 0.91 45.6 1.87 129.9 2.63 274.9 2.60 259.9 2.27 177.0 2.30 175.0 2.08 189.9 1.12 95.0 1.38 82.1 1.80 169.0 1.57 96.5 1.45 114.9 What are the p-values of the t test (for the slope estimate) and F test? What is the coefficient of determination? What is...
Please show all work and formulas Please use the following information to answer this question. State    ...
Please show all work and formulas Please use the following information to answer this question. State     Probability       A                     B                      C Boom   .3                     -10%                5%                   0% Normal            .4                     5                      3                      2                      Bust     .3                     10                    -5                     2 Find the expected return and variance of the portfolio if an investor spent $5000 on A, $8000 on B and $7000 on C.
Please show all work and formulas Please use the following information to answer this question. State    ...
Please show all work and formulas Please use the following information to answer this question. State     Probability       A                     B                      C Boom   .3                     -10%                5%                   0% Normal            .4                     5                      3                      2                      Bust     .3                     10                    -5                     2 Find the expected return and variance of the portfolio if an investor spent $5000 on A, $8000 on B and $7000 on C.
In EXCEL Please: you must show your work in Excel, which includes providing the formulas in...
In EXCEL Please: you must show your work in Excel, which includes providing the formulas in the cells, not just the summary value. You may not earn full points if you do not show your work in detail. JLR Enterprises provides consulting services throughout California and uses a job-order costing system to accumulate the cost of client projects. Traceable costs are charged directly to individual clients; in contrast, other costs incurred by JLR, but not identifiable with specific clients, are...
Please show formulas using excel Build a spreadsheet: Construct an Excel spreadsheet to solve all of...
Please show formulas using excel Build a spreadsheet: Construct an Excel spreadsheet to solve all of the preceding requirements. Show how the solution will change if the following data change: the April 1 work-in-process costs were $66,000 for direct material and $18,000 for conversion. Work in process, April 1—10,000 units: Direct material: 100% complete, cost of .........................................................................................................$ 22,000 Conversion: 20% complete, cost of ................................................................................................................. 4,500 Balance in work in process, April 1 ..................................................................................................................$  26,500 Units started during April ......................................................................................................................................100,000 Units...
Show all work in Excel With formulas used in cells Question Set 2. A manufacturing operation...
Show all work in Excel With formulas used in cells Question Set 2. A manufacturing operation must periodically purchase bulk quantities of washers. The washers are purchased in boxes of 1000 and are consumed at a constant rate. The operation expects to purchase 20,000 boxes over the coming year. Each box costs $120, the annual holding cost per box is $15, and the cost of placing an order is $120 (regardless of the quantity ordered). For the following questions, use...
Please show how to write the formulas for these in Excel. That is what the assignment...
Please show how to write the formulas for these in Excel. That is what the assignment requires and I don't know how to do it. Thank you! All are in column D. Cell numbers that matter are noted on the left. Suppose the risk-free interest rate is 4%. a. Having $200 today is equivalent to having what amount in one year? b. Having $200 in one year is equivalent to having what amount today? c. Which would you prefer, $200...
please show your work and write out your solutions in detail by giving formulas and a...
please show your work and write out your solutions in detail by giving formulas and a short summary at the end. Please do not just post about financial calc or excel without explaining how you got the answer. thank you! Consider the following mutually exclusive projects: T=0 1 2 3 Project X: -100 20 30 90 Project Y: -100 80 30 20 Find IRRs for both projects. Find the cross-over rate. Construct a graph, where you will show the NPV...
Please show all calculations and formulas. If using Escel, please show data/formulas. practice 10: Show the...
Please show all calculations and formulas. If using Escel, please show data/formulas. practice 10: Show the effects of these transactions on the balance sheet equity accounts. Presently the stock price is $20 per share. You started with: common stock ($1 par value) $10,000, capital surplus $100,000, retained earnings $200,000: a. 12% stock dividend b. repurchased 1,000 shares (repurchase price is PV of 20)
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT