In: Accounting
please show your work and write out your solutions in detail by giving formulas and a short summary at the end. Please do not just post about financial calc or excel without explaining how you got the answer. thank you!
Consider the following mutually exclusive projects:
| 
 T=0  | 
 1  | 
 2  | 
 3  | 
|
| 
 Project X:  | 
 -100  | 
 20  | 
 30  | 
 90  | 
| 
 Project Y:  | 
 -100  | 
 80  | 
 30  | 
 20  | 
| A | B | C | D | E | F | G | ||
| 1 | Year 0 | Year 1 | Year 2 | Year 3 | Formula | IRR | ||
| 2 | Project X: | -100 | 20 | 30 | 90 | IRR(B2:E2) | 14.64% | IRR of Project X | 
| 3 | Project Y: | -100 | 80 | 30 | 20 | IRR(B3:E3) | 19.23% | IRR of Project Y | 
| 4 | Project X (-) Project Y: | 0 | -60 | 0 | 70 | IRR(B4:E4) | 8.01% | Cross-over Rate | 
3. Preparing NPV Graph :
| Rate | NPV -Project X | NPV -Project Y | 
| 5% | $24.00 | $20.68 | 
| 10% | $10.59 | $12.55 | 
| 15% | ($0.75) | $5.40 | 
| 20% | ($10.42) | ($0.93) | 

D. Project X is better at NPV of less than 8% (cross-over rate) and
Project Y is better at NPV of more than 8%.
Hope it helps you in your studies.Kindly give a thumbs up
if you like it. ?