Question

In: Finance

Perform a sensitivity analysis for the effects of key variables (e.g., sales growth rate, cost of...

Perform a sensitivity analysis for the effects of key variables (e.g., sales growth rate, cost of capital, unit costs, sales price) on the estimated NPV or IRR in order to demonstrate the sensitivity of the model. The Scenario analysis of several variables simultaneously is encouraged (but not required).

Solutions

Expert Solution

Several steps are involved in sensitivity analysis of a project.

1. Determine input and output variables.

2. Calculate the baseline value of the output variable using the baseline input variables value.

3. Change the value of one of the input variables while others remain constant, and calculate the new value of the output variable.

4. Calculate the percentage change of both output and input variable compared to baseline values.

5. Calculate the sensitivity of the output variable to the change in the input variable using the formula below.

Formula

Sensitivity =

% change in output

% change in input

Steps three through five should be repeated for the other input variables.

Sensitivity analysis allows identification of input variables that represent the greatest vulnerability for the project.

Example

A company is considering a project with initial costs of $500,000 involving purchase of new machinery with a useful life of 5 years. The after-tax cost of capital is 16%, and the marginal tax rate is 30%. The other key parameters of a project are presented in the table below.

The depreciation expense of $40,000 per annum is included in fixed costs.

The management of a company will conduct sensitivity analysis of a project.

Solution

Step 1

Management designates the net present value (NPV) and the internal rate of return (IRR) as outputs. The inputs are:

· Fixed costs

· Sales in units

· Sales price per unit

· Variable costs per unit

Step 2

Let’s find the baseline NPV and IRR. The calculation of discounted cash flows is shown in the table below.

The calculation of discounted net cash flow for designated Year 1 is shown below.

S = 20,000 × $35 = $700,000

TVC = 20,000 × $22 = $440,000

EBT = $700,000 - $440,000 - $100,000 = $160,000

T = $160,000 × 30% = $48,000

NI = $160,000 - $48,000 = $112,000

NCF = $112,000 + $40,000 = $152,000

DNCF =

$152,000

= $131,034

(1+0.16)1

The discounted net cash flows in other designated years are calculated in the same manner.

The baseline net present value of a project is as follows:

Baseline NPV = -$500,000 + $131,034 + $136,891 + $160,164 + $137,686 + $111,030 = $176,805

The baseline IRR is 29.03%.

Step 3

Let’s assume that fixed costs will be 5% higher than baseline values. Provided other inputs remain constant, the discounted net cash flows will be as follows:

NPV = -$500,000 + $128,017 + $134,238 + $157,810 + $135,579 + $109,113 = $164,757

% change in NPV =

$164,757 - $176,805

= -6.81%

$176,805

Sensitivity of NPV =

-6,81%

= -1.362

5%

This means that with an increase in fixed costs of 1%, the NPV of a project will decrease by 1.362%, and vice versa, if fixed costs are reduced by 1%, the NPV will increase by 1.362%.

The new value of IRR is 28.17%

% change in IRR =

28.17%-29.03%

= -2.96%

29.03%

Sensitivity of IRR =

-2.96%

= -0.592

5%

Step 4

Let’s assume that sales in units will be 5% higher than baseline values. Provided other inputs remain constant, the discounted net cash flows will be as follows:

Please note that the change in the number of units sold affects both sales and total variable costs figures!

NPV = -$500,000 + $138,879 + $144,902 + $169,246 + $145,573 + $117,545 = $216,145

% change in NPV =

$216,145 - $176,805

= 22.25%

$176,805

Sensitivity of NPV =

22.25%

= 4.450

5%

Thus, an increase in sales by 1% will cause an increase in NPV by 4.450% and vice versa.

The new value of IRR is 31.73%

% change in IRR =

31.73%-29.03%

= 9.30%

29.03%

Sensitivity of IRR =

9.30%

= 1.860

5%

Step 5

Let’s assume that the sales price of a unit will be 5% higher than baseline values. Provided other inputs remain constant, the discounted net cash flows will be as follows:

Please note that the change in sales price affects sales figures only!

NPV = -$500,000 + $152,155 + $157,491 + $183,170 + $157,896 + $128,277 = $278,989

% change in NPV =

$278,989-$176,805

= 57.79%

$176,805

Sensitivity of NPV =

57.79%

= 11.558

5%

An increase in the sales price by 1% will result in an increase in the NPV by 11.558%, and if the sales price drops by 1%, the NPV of a project will decrease by 11.558%.

The new value of IRR is 35.95%

% change in IRR =

35.95%-29.03%

= 23.84%

29.03%

Sensitivity of IRR =

9.30%

= 4.768

5%

Step 6

Let’s assume that variable costs per unit will be 5% higher than baseline values. Provided other inputs remain constant, the discounted net cash flows will be as follows:

NPV = -$500,000 + $117,759 + $124,301 + $146,240 + $125,363 + $100,298 = $113,961

% change in NPV =

$113,961 - $176,805

= -35.54%

$176,805

Sensitivity of NPV =

-35,54%

= -7.109

5%

An increase in the variable costs per unit by 1% will result in an decrease in the NPV by 7.109% and vice versa.

The new value of IRR is 24.57%

% change in IRR =

24.57% - 29.03%

= -15.36%

29.03%

Sensitivity of IRR =

-15.36%

= -3.072

5%

Results of sensitivity analysis

Sensitivity analysis shows that the NPV and IRR of a project are most vulnerable to the change in the sales price and variable costs per unit and less vulnerable to the change in fixed costs and sales in units.


Related Solutions

Why perform sensitivity analysis? Of what use is sensitivity analysis where good probability estimates are difficult...
Why perform sensitivity analysis? Of what use is sensitivity analysis where good probability estimates are difficult to obtain?
Sensitivity analysis is used to identify the variables that are most important for a project’s success....
Sensitivity analysis is used to identify the variables that are most important for a project’s success. Discuss.
I always rate! Show Excel work, please You have been asked to perform scenario analysis, sensitivity...
I always rate! Show Excel work, please You have been asked to perform scenario analysis, sensitivity analysis, and break even analysis for producing a new golf ball. These new golf balls will sell from $2 a piece. In the best case scenario you think you will sell 750,000 balls, in the most likely case you will sell 500,000 balls and in the worst case you will sell 300,00 balls. Your variable cost is 35% and you have $300,000 in fixed...
1. Perform sensitivity analysis on the following project by first finding the NPV for the base...
1. Perform sensitivity analysis on the following project by first finding the NPV for the base case, then for a 10% decline in quantity sold and a 10% increase in quantity sold.       Investment = $270,000 Straight line depreciation                                      over 3 years       quantity sold per year = 20,000       Price per unit = $20       Operating Cost = $10 per unit (all variable)       Tax rate 25%   cost of capital 10%       Project will have a 3-year life...
Discuss the determinants of future dividends and growth rate in dividends, and the sensitivity of the...
Discuss the determinants of future dividends and growth rate in dividends, and the sensitivity of the stock price to estimates of those two factors.
A key skill of consultants is to be able to perform a strategic analysis. Often this...
A key skill of consultants is to be able to perform a strategic analysis. Often this involves forecasting what the future will bring to a sector or an industry based on specific assumptions and giving advice on the basis of those scenarios. Based upon what you know of existing trends in the consultancy industry what forecasts can you make about the next ten years? If you were leading KPMG’s advisory business: 1 What trends would be central to their strategic...
What does it mean to say that the key to the entire budget (e.g., the sales...
What does it mean to say that the key to the entire budget (e.g., the sales budget)is the forecast of operating activity?
Perform a value chain cost analysis of Amazon
Perform a value chain cost analysis of Amazon
Multivariate analysis Using the data provided, perform the following analysis: Determine the explanatory and response variables....
Multivariate analysis Using the data provided, perform the following analysis: Determine the explanatory and response variables. Run a multivariate regression analysis on all three variables. Interpret the results by answering the following questions: What is the calculated correlation coefficient? Do the sales figures correlate with the marketing expenditure and price? Comment on the coefficient of determination. What percentage of the response data can be explained by the explanatory variables? Determine the multiple regression line equation in the form: sales^ =...
To address the increasing key sizes and create a linear key growth rate, comparable with symmetrics...
To address the increasing key sizes and create a linear key growth rate, comparable with symmetrics keys, public-key cryptography applied [answer] mathematics to their approach.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT