Question

In: Accounting

PROBLEM 5 BBB Inc. is employing normal costing for its job orders. The overhead is applied...

PROBLEM 5

BBB Inc. is employing normal costing for its job orders. The overhead is applied using a predetermined overhead rate. The following information relates to BBB Inc. for the year ended December 31, 2019:

Job No. 101

Job No. 102

Job No. 103

Job in Process, 01/01/2019

Direct Materials

P80,000

P60,000

P0

Labor

120,000

80,000

0

Factory Overhead

60,000

40,000

0

Costs added during 2019

Materials

P40,000

P20,000

P200,000

Labor

200,000

400,000

800,000

Factory Overhead

200,000

200,000

400,000

Additional information:

  1. Actual overhead for the year 2019 amounted to P800,000.
  2. Jobs No. 101 and 102 were completed and transferred to finished goods during year 2019.
  3. Job No. 102 was sold during 2019.
  4. The gross profit rate based on cost is 20%.

Compute: (6 pts)

  1. Total manufacturing cost
  2. Cost of goods manufactured for 2019
  3. Cost of goods sold 2019
  4. Gross profit for 2019
  5. Work-in process for December 31, 2019
  6. Cost of finished goods for December 31, 2019

PROBLEM 6

CCC Inc. has completed Job 101, containing 1,100 shoes, during 2016 at the following unit costs:

Direct Materials – 2,000 Direct Labor – 1,000

Factory Overhead (including an allowance of P300 for spoiled work - 1,300

Final inspection of Job 101 disclosed 100 spoiled shoes which were sold to a department store for P200,000.

  1. What is the unit cost of the good shoes produced on Job 101 if spoilage loss is charged to all production? (2 pts)
  2. What is the unit cost of the good shoes produced on Job 101 if spoilage loss is charged specifically to Job 101? (2 pts)

Solutions

Expert Solution

TOTAL MANUFACTURING COST
DIRECT MATERIAL 400000
DIRECT LABOR 1600000
MANUFACTURING OVERHEAD 900000
TOTAL 2900000
W/N
DM DL MOH
80000 120000 60000
60000 80000 40000
40000 200000 200000
20000 400000 200000
200000 800000 400000
400000 1600000 900000
COST OF GOODS MANUFACTURED FOR 2019
OPENING WORK IN PROCESS 140000
MANUFACTURING COST 2900000
ENDING WORK IN PROCESS(-) 1400000
TOTAL 1640000

NOTE:

OPENING WORK IN PROCESS = SUM OF DM,DL &MOH ON 01/01/2019
ENDING WORK IN PROCESS = SUM OF DM,DL &MOH OF JOB NO.103
(JOB 103 IS STILL IN PROGRESS AND NOT YET COMPLETED)
COST OF GOODS SOLD FOR 2019 (JOB102)
DM 80000
DL 480000
MOH 240000
TOTAL 800000
GROSS PROFIT (20% ON COST)
800000*20%
160000
WORK IN PROCESS FOR DECEMBER 2019 (JOB 103)
DM 200000
DL 800000
MOH 400000
TOTAL 1400000
COST OF FNISHED GOODS FOR DECEMBER 2019(JOB101)
DM 120000
DL 320000
MOH 260000
TOTAL 700000
UNIT COST OF GOOD SHOES PRODUCED
DM 2000
DL 1000
MOH 1000
TOTAL 4000

HERE SPOILAGE LOSS IS CHARGED TO ALL PRODUCTION NOT SPECIFICALLY TO JOB 101 .THEREFORE IT WILL NOT BE ADDED WITH THE UNIT COST

UNIT COST OF GOOD SHOES PRODUCED
DM 2000
DL 1000
MOH 1300
TOTAL 4300

HERE SPOILAGE LOSS IS SPECIFICALLY CHARGED TO JOB101.HENCE IT WILL BE ADDED TO THE UNIT COST OF JOB101.


Related Solutions

Overhead Applied to Jobs, Departmental Overhead Rates Xania Inc. uses a normal job-order costing system. Currently,...
Overhead Applied to Jobs, Departmental Overhead Rates Xania Inc. uses a normal job-order costing system. Currently, a plantwide overhead rate based on machine hours is used. Xania’s plant manager has heard that departmental overhead rates can offer significantly better cost assignments than a plantwide rate can offer. Xania has the following data for its two departments for the coming year: Department A Department B Overhead costs (expected) $80,000 $78,000 Normal activity (machine hours) 14,500 10,800 Required: 1. Compute a predetermined...
Overhead Applied to Jobs, Departmental Overhead Rates Xania Inc. uses a normal job-order costing system. Currently,...
Overhead Applied to Jobs, Departmental Overhead Rates Xania Inc. uses a normal job-order costing system. Currently, a plantwide overhead rate based on machine hours is used. Xania’s plant manager has heard that departmental overhead rates can offer significantly better cost assignments than a plantwide rate can offer. Xania has the following data for its two departments for the coming year: Department A Department B Overhead costs (expected) $80,000 $83,000 Normal activity (machine hours) 16,000 2,800 Required: 1. Compute a predetermined...
Lin Corporation uses a job order costing system and normal costing, with overhead being applied on...
Lin Corporation uses a job order costing system and normal costing, with overhead being applied on the basis of direct labor cost. There were no jobs in process at the start of the period. During the month, the company worked on 3 jobs, with the following information: Alpha Beta Gamma Direct Labor ($8/hour) $24,000 $8,800 Direct Materials $42,000 $61,000 Overhead Applied $23,940 $6,160 During the month, only job Alpha was completed and transferred to finished goods inventroy. The ending balance...
Arensky Company uses normal costing to account for overhead in its job costing system. There are...
Arensky Company uses normal costing to account for overhead in its job costing system. There are 2 departments in the company: Designing and Machining. The Designing Dept. is labor intensive; the Machining Dept. is machine intensive. (OH= Overhead; DLH= Direct Labor Hours; MH= Machine Hours.) The budget for 2019 is as follows: Designing   Machining Est. OH $2,000,000 $5,600,000 Est DLH 40,000 Hours 10,000 Hours Est MH. 20,000 Hours 70,000 Hours Actual Results are as follows: Designing Machining Actual OH $2,100,000...
Curtis Inc. uses a job order costing system. Manufacturing overhead is applied on the basis of...
Curtis Inc. uses a job order costing system. Manufacturing overhead is applied on the basis of direct labor cost. Total manufacturing overhead was estimated to be $60,680 for the year; direct labor was estimated to total $151,700. Raw Materials Inventory (1/1) $ 10,700 (12/31) $ 13,700 Work in Process Inventory (1/1) $ 23,900 (12/31) $ 18,500 Finished Goods Inventory (1/1) $ 34,100 (12/31) $ 40,000 The following transactions have occurred during the year. Raw materials purchases $ 107,000 Direct materials...
Deer Lake Inc. uses a job order costing system with manufacturing overhead applied to products at...
Deer Lake Inc. uses a job order costing system with manufacturing overhead applied to products at a rate of 150% of direct labor cost. Treating each case independently, find the missing amounts (Input all amounts as positive values.): Case 1 Case 2 Case 3 Direct materials used $20,600 $10,000 Direct labor $26,800 Manufacturing overhead applied $44,100 Total manufacturing costs $97,000 $30,000 Beginning Work in Process $10,300 $7,200 Ending Work in process $7,600 $9,500 Cost of goods manufactured $94,400 $34,100 Beginning...
X Corporation, which uses a normal job costing system and dispose the over/under applied manufacturing overhead...
X Corporation, which uses a normal job costing system and dispose the over/under applied manufacturing overhead using write-off method, had two jobs in process at the start of 20x2: Job No. 59, WIP Balance$66,500Job No. 60, WIP Balance$139,500X applies manufacturing overhead on the basis of machine hours.At the beginning of the 20x2, X corporation estimated its manufacturing overhead during the first quarter would total $231,250and its budgeted machine hours would total 6250Manufacturing overhead incurred during the first quarter of 20x2...
Predetermined Overhead Rate, Applied Overhead, Unit Cost Ripley, Inc., costs products using a normal costing system....
Predetermined Overhead Rate, Applied Overhead, Unit Cost Ripley, Inc., costs products using a normal costing system. The following data are available for last year: Budgeted:       Overhead      $343,000       Machine hours      88,000       Direct labor hours      9,800 Actual:       Overhead      $342,200       Machine hours      85,800       Direct labor hours       9,580       Prime cost      $1,464,700       Number of units      180,000 Overhead is applied on the basis of direct labor hours. Required: 1. What was the predetermined overhead rate? $fill in the...
Job Order Costing: Wadadli Products uses a job-order costing system Overhead costs are applied to jobs...
Job Order Costing: Wadadli Products uses a job-order costing system Overhead costs are applied to jobs on the basis of machine-hours. At the beginning of the year, management estimated that 170,000 machine-hours would be required for the periods estimated level of production. The company also estimated $212,500 of fixed manufacturing overhead expenses for the coming period and variable manufacturing overhead of $1.50 per machine hour. Required: 1. Compute the company’s predetermined overhead rate. 2. Assume that during the year of...
The company uses a job-order costing system in which overhead is applied to jobs on the...
The company uses a job-order costing system in which overhead is applied to jobs on the basis of direct labor cost. Its predetermined overhead rate is based on a cost formula that estimated $94,500 of manufacturing overhead for an estimated activity level of $45,000 direct labor dollars. At the beginning of the year, the inventory balances were as follows: Raw materials $ 10,800 Work in process $ 4,400 Finished goods $ 8,900 During the year, the following transactions were completed:...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT