In: Finance
Gilton Co. is evaluating a project with the following cash flows. The firm does not have any debt and all the required financing for the project is through stockholders.
Table 1: Cash flows of the project
Year |
Cash flow (£) |
(45,000) |
|
1 |
14,000 |
2 |
16,000 |
3 |
17,000 |
4 |
20,000 |
Table 2: Risk and Return
Expected Return |
Standard Deviation |
Beta |
|
Gilton Co. |
? |
30% |
1.3 |
FTSE 500 |
13% |
12% |
|
Risk Free Asset |
2% |
0% |
Using the provided information in Table 2 and assuming that CAPM holds:
Calculate the expected return of the firm.
Using the estimated expected return, evaluate the project using the following criteria (Table 3) and decide if you accept/reject project based on each criterion (the last column of table 3).
Hint: You can use excel to find out IRR of the project.
Hint: Consider the managers’ threshold for PB, DPP and PI.
Please provide NPV profile of the project.
Hint: Use excel to draw the graph and then paste in the word file.
Table 3: Project criteria
Criteria |
Value |
Managers’ Threshold |
Accept/Reject |
NPV |
|||
IRR |
|||
Payback Period (PB) |
2.5 year |
||
Discounted Payback Period (DPB) |
4 year |
||
Profitability Index (PI) |
0.5 |
Considering estimated criteria, provide your insight about this project as an independent analyst. ( 5 marks)
EXEL CAN BE USED
a)
The required rate of return R(e) is calculated by CAPM model
R(e) = r(f) + Beta*(R(m) - r(f))
R(m) is the market return =13%
r(f) is the risk-free rate = 2%
Beta = 1.3
R(e) = 0.02+1.3*(0.13-0.02)
R(e) = 0.163= 16.3%
b) We calculate the NPV, IRR using excel
We discount the cash-flows by 16.3% to get NPV
Year | Cash flow (£) |
-45,000 | |
1 | 14,000 |
2 | 16,000 |
3 | 17,000 |
4 | 20,000 |
NPV | 606.5791771 |
NPV Formula | B2+NPV(16.3%,B3:B6) |
IRR | 16.94% |
IRR Forula | IRR(B2:B6) |
Payback period is the time taken in year for the cumulative cash-flows to become 0
Discounted Payback period is the time taken in year for the cumulative discounted cash-flows to become 0
We observe that sometime after year 2, cumulative cash-flows become 0
Sometime after year 3, discounted cumulative cash-flows become 0
Year | Cash flow (£) | Cumulative cash-flows | Discounted cash-flows | Cumulative discounted cash-flows |
-45,000 | -45,000 | -45000 | -45000 | |
1 | 14,000 | -31,000 | 12037.8332 | -32962.16681 |
2 | 16,000 | -15,000 | 11829.3411 | -21132.82576 |
3 | 17,000 | 2,000 | 10807.1151 | -10325.71065 |
4 | 20,000 | 22,000 | 10932.2898 | 606.5791771 |
Payback period (in years) | 2.8824 | Discounted payback (in years) | 3.944514902 |
Profitability Index = PV of future cash-flows/Initial investment = 45606.58/45000 = 1.01348
Criteria | Value | Managers’ Threshold | Accept/Reject |
NPV | 606.58 | 0 | Accept |
IRR | 16.94% | 16.30% | Accept |
Payback Period (PB) | 2.8824 years | 2.5 year | Reject |
Discounted Payback Period (DPB) | 3.94 years | 4 year | Accept |
Profitability Index (PI) | 1.01348 | 0.5 | Accept |
NPV Profile
We find the NPV form different interest rates
Interest rate | NPV |
1% | 20,266 |
2% | 18,601 |
3% | 17,001 |
4% | 15,463 |
5% | 13,985 |
6% | 12,563 |
7% | 11,194 |
8% | 9,876 |
9% | 8,607 |
10% | 7,383 |
11% | 6,203 |
12% | 5,066 |
13% | 3,968 |
14% | 2,908 |
15% | 1,885 |
16% | 897 |
17% | -59 |
18% | -982 |
19% | -1,875 |
20% | -2,739 |
21% | -3,575 |
22% | -4,385 |
23% | -5,169 |
24% | -5,928 |
25% | -6,664 |
26% | -7,377 |
27% | -8,069 |
28% | -8,740 |
29% | -9,391 |
30% | -10,023 |
Insights
All the criterion except payback period is acceptable. We have a positive NPV and an IRR greater than the expected return. Also, the discounted payback period is within the acceptable range. The profitability Index is well above the threshold. Hence, the project must be undertaken.