In: Finance
Harry's Inc. is considering a project that has the following cash flow and WACC data. What is the project's NPV? Note that if a project's projected NPV is negative, it should be rejected. WACC: 13.25%
Year 0 1 2 3 4 5 Cash flows -$1,000 $300 $300 $300 $300 $300
NPV is calculated as follows:
Year | CF | Discount Factor | Discounted CF | ||
0 | $-1,000.00 | 1/(1+0.135)^0= | 1 | 1*-1000= | $ -1,000.00 |
1 | $ 300.00 | 1/(1+0.135)^1= | 0.881057269 | 0.881057268722467*300= | $ 264.32 |
2 | $ 300.00 | 1/(1+0.135)^2= | 0.776261911 | 0.776261910768693*300= | $ 232.88 |
3 | $ 300.00 | 1/(1+0.135)^3= | 0.683931199 | 0.683931198915148*300= | $ 205.18 |
4 | $ 300.00 | 1/(1+0.135)^4= | 0.602582554 | 0.602582554110263*300= | $ 180.77 |
5 | $ 300.00 | 1/(1+0.135)^5= | 0.530909739 | 0.530909739304196*300= | $ 159.27 |
NPV = Sum of all Discounted CF | $ 42.42 |
NPV is 42.42 and the project should be selected because the NPV is positive