Question

In: Accounting

X Company's accountant uses account analysis to estimate costs for each month, with direct labor hours...

X Company's accountant uses account analysis to estimate costs for each month, with direct labor hours as the independent variable. In July, she did the following cost behavior analysis for three specific cost items:

Cost Item Total Cost Variable Cost
Utilities $364,632 $267,728
Rent 329,000 0
Supplies 371,084 371,084

In July, direct labor hours were 11,600. If direct labor hours in November are expected to be 12,500, what are expected total costs for these three cost items in November?

Solutions

Expert Solution

ANSWER :-

July :-

Cost item Total Cost Variable Cost

Fixed Cost

Fixed cost = Total - Variable cost

Utilites $ 3,64,632 $ 2,67,728 $ 96,904
Rent $3,29,000 $ 0 $ 3,29,000
Supplies $ 3,71,084 $ 3,71,084 $ 0
TOTAL COST $ 10,64,716

Variable Cost per Labour hour :-

Utilites $ 2,67,728 / 11,600 23.08 per hour
Supplies $ 3,71,084 / 11,600 31.99 per hour

Now in November :-

Now direct labour hour expected in November to be 12,500

Utilites $ 2,88,500 23.08 per hour * 12,500
Supplies $ 3,99,875 31.99 per hour * 12,500

Noember Expected Total Cost :-

Cost item Total Cost

Variable Cost

Fixed Cost

Fixed cost = Total - Variable cost

Utilites $ 3,85,404 $ 2,88,500 $ 96,904
Rent $ 3,29,000 $ 0 $ 3,29,000
Supplies $ 3,99,875 $ 3,99,875 $ 0
TOTAL COST $ 11,14,279
  • So when Increasing Direct labour so total cost Increased by $49,563 in November
  • ( Utilites 20772 + 28791 Supplies = $49,563 )
  • Variable Cost per Hour is Fixed.

Related Solutions

Data on Gantry Company's direct labor costs are given below: Standard direct-labor hours 50,000 Actual direct-labor...
Data on Gantry Company's direct labor costs are given below: Standard direct-labor hours 50,000 Actual direct-labor hours 49,000 Direct-labor efficiency variance-favorable $ 5,200 Direct-labor rate variance-favorable $ 9,800 Total direct labor payroll $ 245,000 What was Gantry's actual direct labor rate?
MAnufacturing overhead is applied on the basis of direct labor hours. The direct labor hours for...
MAnufacturing overhead is applied on the basis of direct labor hours. The direct labor hours for the period are 500 and the estimated manufacturing overhead is 2000. actual direct labor hours were 160 and actual overhead was 1000. Compute the manufacturing overhead applied during this period.
Overhead is applied on the basis of direct labor hours. Three direct labor hours are required...
Overhead is applied on the basis of direct labor hours. Three direct labor hours are required for each product unit. Planned production for the period was set at 8,000 units. Manufacturing overhead for the period is budgeted at $204,000, of which 30 percent is fixed. The 26,200 hours worked during the period resulted in production of 8,500 units. Manufacturing overhead cost incurred was $220,500. Required: a. Calculate the overhead spending variance: b. Calculate the overhead efficiency variance: c. Calculate the...
Craigmont Company's direct materials costs are $5,000,000, its direct labor costs total $8,800,000, and its factory...
Craigmont Company's direct materials costs are $5,000,000, its direct labor costs total $8,800,000, and its factory overhead costs total $6,800,000. Its prime costs total:
Victory Company uses weighted-average process costing to account for its production costs. Direct labor is added...
Victory Company uses weighted-average process costing to account for its production costs. Direct labor is added evenly throughout the process. Direct materials are added at the beginning of the process. During November, the company transferred 700,000 units of product to finished goods. At the end of November, the goods in process inventory consist of 180,000 units that are 30% complete with respect to labor. Beginning inventory had $420,000 of direct materials and $139,000 of direct labor costs. The direct material...
Victory Company uses weighted-average process costing to account for its production costs. Direct labor is added...
Victory Company uses weighted-average process costing to account for its production costs. Direct labor is added evenly throughout the process. Direct materials are added at the beginning of the process. During November, the company transferred 700,000 units of product to finished goods. At the end of November, the goods in process inventory consists of 180,000 units that are 30% complete with respect to labor. Beginning inventory had $420,000 of direct materials and $139,000 of direct labor cost. The direct material...
At the high and low levels of activity during the month, direct labor hours are 90,000...
At the high and low levels of activity during the month, direct labor hours are 90,000 and 40,000, respectively. The related costs are $165,000 and $100,000. What are the fixed and variable costs at any level of activity?
James Corp. applies overhead on the basis of direct labor hours. For the month of May,...
James Corp. applies overhead on the basis of direct labor hours. For the month of May, the company planned production of 10,000 units (80% of its production capacity of 12,500 units) and prepared the following overhead budget: Operating Levels Overhead Budget 80% Production in units 10,000 Standard direct labor hours 36,000 Budgeted overhead Variable overhead costs Indirect materials $ 21,600 Indirect labor 36,000 Power 7,200 Maintenance 3,600 Total variable costs 68,400 Fixed overhead costs Rent of factory building 20,000 Depreciation—Machinery...
James Corp. applies overhead on the basis of direct labor hours. For the month of May,...
James Corp. applies overhead on the basis of direct labor hours. For the month of May, the company planned production of 10,000 units (80% of its production capacity of 12,500 units) and prepared the following overhead budget: Operating Levels Overhead Budget 80% Production in units 10,000 Standard direct labor hours 26,000 Budgeted overhead Variable overhead costs Indirect materials $ 15,600 Indirect labor 26,000 Power 7,800 Maintenance 2,600 Total variable costs 52,000 Fixed overhead costs Rent of factory building 22,000 Depreciation—Machinery...
James Corp. applies overhead on the basis of direct labor hours. For the month of May,...
James Corp. applies overhead on the basis of direct labor hours. For the month of May, the company planned production of 10,000 units (80% of its production capacity of 12,500 units) and prepared the following overhead budget: Operating Levels Overhead Budget 80% Production in units 10,000 Standard direct labor hours 30,000 Budgeted overhead Variable overhead costs Indirect materials $ 21,000 Indirect labor 30,000 Power 6,000 Maintenance 3,000 Total variable costs 60,000 Fixed overhead costs Rent of factory building 14,000 Depreciation—Machinery...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT