Question

In: Accounting

List of tasks: Meet with each of the managers at the company(5 days) Conduct a series...

List of tasks:

  • Meet with each of the managers at the company(5 days)
  • Conduct a series of interviews (5 days)
  • Review company records (3 days) and observe business operations (8 days)
  • Analyze MyBookkeeper data account software (5 days) and study a sample of sales and billing transactions (2 days)
  • Prepare the final report (1 days)

1. Identify the dependent tasks and identify what predecessor tasks are required.

2. Construct a PERT or CPM chart from the information.

3. Find the overall durations of the project and determine the critical path.

Solutions

Expert Solution

In the first part of the solution calculates dependent tasks and predeccessor tasks in the project.

in the second part of the solution construct an PERT chart from the given information. the chart is prepared by using the activity on arrow (AOA)method.

in the third part of the solution find out the critical path of the project and the overall duration of the project. the overall duration of the project is also the duartion of the critical path of the project. it is the longest time taking path of the chart.

please Like if you are satisfied with this answer....


Related Solutions

Times (days) Activity Optimistic Most Likely Pessimistic Preceding Tasks 1 8 10 13 - 2 5...
Times (days) Activity Optimistic Most Likely Pessimistic Preceding Tasks 1 8 10 13 - 2 5 6 8 - 3 13 15 21 2 4 10 12 14 1,3 5 11 20 30 4 6 4 5 8 5 7 2 3 4 5 8 4 6 10 7 9 2 3 4 8,6 Draw the AON Network Diagram Compute the expected activity time Using the expected activity times, compute the early start, early finish, late start, late finish, and...
QUESTION 1 The Jubail Bicycle Shop operates 7 days per week, closing 5 days each for...
QUESTION 1 The Jubail Bicycle Shop operates 7 days per week, closing 5 days each for Eid-ul-Fitr and Eid- Ul -Adah (this gives 355 working days in a year). The shop pays SAR 600 for a particular bicycle purchased from the manufacturer. The annual holding cost per bicycle is estimated to be 25% of the SAR value of inventory. The shop sells an average of 25 bikes per week. Frequently, the dealer does not have a bike in stock when...
The Jubail Bicycle Shop operates 7 days per week, closing 5 days each for Eid-ul-Fitr and...
The Jubail Bicycle Shop operates 7 days per week, closing 5 days each for Eid-ul-Fitr and Eid- Ul -Adah (this gives 355 working days in a year). The shop pays SAR 600 for a particular bicycle purchased from the manufacturer. The annual holding cost per bicycle is estimated to be 25% of the SAR value of inventory. The shop sells an average of 25 bikes per week. Frequently, the dealer does not have a bike in stock when a customer...
1. List 5 important factors as to why one would conduct a research online banking. 2....
1. List 5 important factors as to why one would conduct a research online banking. 2. What are 5 advantages of online banking? 3. Why should one consider exploring online banking?
Use a 5 percent discount rate to compute the NPV of each of the following series...
Use a 5 percent discount rate to compute the NPV of each of the following series of cash receipts and payments: Use Appendix A and Appendix B. $6,200 received now (year 0), $1,890 paid in year 3, and $4,000 paid in year 5. $10,000 paid now (year 0), $12,690 paid in year 2, and $31,000 received in year 8. $20,000 received now (year 0), $13,500 paid in year 5, and $7,500 paid in year 10. (For all requirements, round discount...
Use a 5 percent discount rate to compute the NPV of each of the following series...
Use a 5 percent discount rate to compute the NPV of each of the following series of cash receipts and payments: Use Appendix A and Appendix B. $6,200 received now (year 0), $1,890 paid in year 3, and $4,000 paid in year 5. $10,000 paid now (year 0), $12,690 paid in year 2, and $31,000 received in year 8. $20,000 received now (year 0), $13,500 paid in year 5, and $7,500 paid in year 10. (For all requirements, round discount...
Use a 5 percent discount rate to compute the NPV of each of the following series...
Use a 5 percent discount rate to compute the NPV of each of the following series of cash receipts and payments: Use Appendix A and Appendix B. $6,200 received now (year 0), $1,890 paid in year 3, and $4,000 paid in year 5. $10,000 paid now (year 0), $12,690 paid in year 2, and $31,000 received in year 8. $20,000 received now (year 0), $13,500 paid in year 5, and $7,500 paid in year 10.
List 5 intentional torts, and explain the elements needed to prove each. List and explain the...
List 5 intentional torts, and explain the elements needed to prove each. List and explain the elements to prove negligence. What is the difference between negligence per se and comparative negligence? What is the relationship between contributory negligence and res ispa loquitor? What are the differences in the 3 types of damages available in a tort case?
list 5 policies for medicare and identify what goals each each adresss
list 5 policies for medicare and identify what goals each each adresss
Conduct a hypothesis test for each problem, using the traditional method. Show the 5 steps and...
Conduct a hypothesis test for each problem, using the traditional method. Show the 5 steps and all work for each hypothesis test. Be sure you select the correct test to use for each problem. 2. A college statistics instructor claims that the mean age of college statistics students is 25. A random sample of 98 college statistics students revealed a mean age of 23.1. The population standard deviation is known to be 3.21 years. Test his claim at the 0.05...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT