Question

In: Accounting

Alden Company uses a two-variance analysis for overhead variances. Practical capacity is defined as 36 setups...

Alden Company uses a two-variance analysis for overhead variances. Practical capacity is defined as 36 setups and 36,000 machine hours to manufacture 7,200 units for the year. Selected data for 2016 follow: Budgeted fixed factory overhead: Setup $ 57,600 Other 265,000 $ 322,600 Total factory overhead incurred $ 494,000 Variable factory overhead rate: Per setup $ 650 Per machine hour $ 4 Total standard machine hours allowed for the units manufactured 24,000 hours Machine hours actually worked 28,000 hours Actual total number of setups 32 Assume that the company uses only machine hours as the activity measure to apply both variable and fixed overhead, and that it includes all setup costs as variable factory overhead. What is the (a) overhead spending variance, (b) efficiency variance, and (c) flexible-budget variance for the year?

Solutions

Expert Solution

Standard machine hour per unit = 36000/7200 5
no of unit manufactured = std allowed machine hour/std machine hour p.u(24000/5) 4800
Budgeted no of unit per set ups = unit/no of setups (7200/36) 200 unit
std no of setup for unit manufactured (4800/200) 24
hence spending variance = (variable oh+fixed oh +actual oh)
variable oh = (650*32)+(28000*4) 132800
fixed overhead 322600
actual overhead 494000
hence spending variance = 132800+322600-494000 = (38600) unfavourable
B) Efficiency variance = (24*650+24000*4+322600-455400)
(21200) unfavourable
C) Flexible bugdet variance = spending variance +efficiency variance
                                                             21200+38600
                                                                59800 unfavourable

Related Solutions

Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 32...
Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 32 setups and 32,000 machine hours to manufacture 6,400 units for the year. Selected data for 2019 follow: Budgeted fixed factory OH Setup cost 57600 other 176000 233600 Total factory OH rate 492000 Variable factory OH rate per setup 750 per machine hour 7 total standard machine hours allowed for the units manufactured 26000 hrs machine hours actually worked 29000 hrs actual total number of...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 124,000 units requiring 496,000 direct labor hours. (Practical capacity is 516,000 hours.) Annual budgeted overhead costs total $818,400, of which $585,280 is fixed overhead. A total of 119,400 units using 494,000 direct labor hours were produced during the year. Actual variable overhead costs for the year were $260,600, and...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 123,000 units requiring 492,000 direct labor hours. (Practical capacity is 512,000 hours.) Annual budgeted overhead costs total $816,720, of which $585,480 is fixed overhead. A total of 119,500 units using 490,000 direct labor hours were produced during the year. Actual variable overhead costs for the year were $261,100, and...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 125,000 units requiring 500,000 direct labor hours. (Practical capacity is 520,000 hours.) Annual budgeted overhead costs total $830,000, of which $585,000 is fixed overhead. A total of 119,300 units using 498,000 direct labor hours were produced during the year. Actual variable overhead costs for the year were $260,000, and...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 130,000 units requiring 520,000 direct labor hours. (Practical capacity is 540,000 hours.) Annual budgeted overhead costs total $842,400, of which $608,400 is fixed overhead. A total of 119,000 units using 518,000 direct labor hours were produced during the year. Actual variable overhead costs for the year were $261,900, and...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 123,000 units requiring 492,000 direct labor hours. (Practical capacity is 512,000 hours.) Annual budgeted overhead costs total $811,800, of which $580,560 is fixed overhead. A total of 119,200 units using 490,000 direct labor hours were produced during the year. Actual variable overhead costs for the year were $260,100, and...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 129,000 units requiring 516,000 direct labor hours. (Practical capacity is 536,000 hours.) Annual budgeted overhead costs total $861,720, of which $608,880 is fixed overhead. A total of 119,300 units using 514,000 direct labor hours were produced during the year. Actual variable overhead costs for the year were $261,800, and...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 129,000 units requiring 516,000 direct labor hours. (Practical capacity is 536,000 hours.) Annual budgeted overhead costs total $861,720, of which $608,880 is fixed overhead. A total of 119,300 units using 514,000 direct labor hours were produced during the year. Actual variable overhead costs for the year were $261,800, and...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 126,000 units requiring 504,000 direct labor hours. (Practical capacity is 524,000 hours.) Annual budgeted overhead costs total $821,520, of which $594,720 is fixed overhead. A total of 119,300 units using 502,000 direct labor hours were produced during the year. Actual variable overhead costs for the year were $260,300, and...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 127,000 units requiring 508,000 direct labor hours. (Practical capacity is 528,000 hours.) Annual budgeted overhead costs total $833,120, of which $604,520 is fixed overhead. A total of 119,400 units using 506,000 direct labor hours were produced during the year. Actual variable overhead costs for the year were $260,300, and...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT