Question

In: Statistics and Probability

M1_IND3. A distributor of fasteners is opening a new plant and considering whether to use a...

M1_IND3. A distributor of fasteners is opening a new plant and considering whether to use a mechanized process or a manual process to package the product. The manual process will have a fixed cost of $36,234 and a variable cost of $2.14 per bag. The mechanized process would have a fixed cost of $84,420 and a variable cost of $1.85 per bag. The company expects to sell each bag of fasteners for $2.75. a) What is the break-even point for the manual process (in units)? b) What is the break-even point for the mechanized process (in units)? c) A point of indifference for two processes is quantity at which each process generates the same amount of profit (review video). What is the point of indifference for the two processes? (Hint: 1) Use equations to set profit of manual process equal to mechanized process – and solve for quantity; 2) (Excel) If you have a break-even for each process – add another cell the calculates the difference for the profits between the two processes and have only one cell that represents quantity that be used to calculates costs/revenues for each process and use Goal Seek to calculate quantity that would set the difference to zero). d) Which process would you select if the quantity that is sold is greater than the quantity calculated as the point of indifference? e) Which process would you select in the quantity sold is less than the quantity calculated as the point of indifference?

Solutions

Expert Solution

Solution

Back-up Theory

BREAKEVEN ANALYSIS

Terminology

F = Fixed cost, v = Variable cost per unit, T = Total cost, r = Revenue per unit, R = Total revenue,

p = Profit per unit, P = Total profit, x = Number of units.

Then,

T = F + vx ……………………………………………………………………………………… (1)

R = rx …………………………………………………………………………………………… (2)

P = R – T = rx – (F + vx) = x(r - v) - F………………………………………………….………… (3)

Break-even units is that value of x at which P = 0, i.e., x(r - v) = F or x = F/(r - v) …….......……..(4)

Break-even value = xr = rF/(r - v) = F/{1- (v/r)}, where x is the break-even units ……………………………(5)

Now, to work out the solution,

Part (a)

For the manual process,F = 36,234; v = 2.14; r = 2.75.

Vide (4),

The break-even point = 36234/0.61

= 58441.94

The break-even point for the manual process (in units) = 58442 Answer 1

Part (b)

For the mechanized process, F = 84,420; v = 1.85; r = 2.75.

Vide (4),

The break-even point = 84420/0.90

= 93577.78

The break-even point for the mechanized process (in units) = 93578   Answer 2

Part (c)

For the point of indifference for two processes, we should have:

Vide (3), x(0.61) – 36234 = x(0.9) – 84420

Or, 0.29x = 48186

Or, x = 166158.62

The point of indifference for the two processes = 166159 Answer 3

Part (d)

Since for neither process, the quantity that is sold is greater than the quantity calculated as the point of indifference, neither process can be selected. Answer 4

Part (e)

Since for both processes, the quantity that is sold is less than the quantity calculated as the point of indifference, either process can be selected. Answer 5

DONE


Related Solutions

You are considering opening a new plant. The plant will cost $103.9 million up front and...
You are considering opening a new plant. The plant will cost $103.9 million up front and will take one year to build. After that it is expected to produce profits of $30.4 million at the end of every year of production. The cash flows are expected to last forever. Calculate the NPV of this investment opportunity if your cost of capital is 7.5%. Should you make the​ investment? Calculate the IRR and use it to determine the maximum deviation allowable...
You are considering opening a new plant. The plant will cost $97.9 million up front and...
You are considering opening a new plant. The plant will cost $97.9 million up front and will take one year to build. After that it is expected to produce profits of $30.4 million at the end of every year of production. The cash flows are expected to last forever. Calculate the NPV of this investment opportunity if your cost of capital is 7.8%. Should you make the​ investment? Calculate the IRR and use it to determine the maximum deviation allowable...
You are considering opening a new plant. The plant will cost $ 95.5 million up front...
You are considering opening a new plant. The plant will cost $ 95.5 million up front and will take one year to build. After that it is expected to produce profits of $ 28.4 million at the end of every year of production. The cash flows are expected to last forever. Calculate the NPV of this investment opportunity if your cost of capital is 8.5 %. Should you make the? investment? Calculate the IRR and use it to determine the...
You are considering opening a new plant. The plant will cost $ 96.2 million up front...
You are considering opening a new plant. The plant will cost $ 96.2 million up front and will take one year to build. After that it is expected to produce profits of $ 29.6 million at the end of every year of production. The cash flows are expected to last forever. Calculate the NPV of this investment opportunity if your cost of capital is 8.2 % Should you make the​ investment? Calculate the IRR and use it to determine the...
Fibertech is deciding on opening a new plant. The new plant will be located on the...
Fibertech is deciding on opening a new plant. The new plant will be located on the existing land, which the company purchased 2 years ago for $1 million. The company has also spent $300,000 for market research. If the plant is not opened the company will rent out the land for $200,000 per year. The expected sales of the new plant are $2.3 million per year for the next 5 years. The new plant's construction costs are $2 million (Year...
Dew Little Co. is considering opening a new plant to produce lawnmowers. The initial cost of...
Dew Little Co. is considering opening a new plant to produce lawnmowers. The initial cost of the project is $6 million. This cost will be depreciated straight-line to a zero book value over the 15-year life of the project. The net income of the project is expected to be $137,000 a year for the first four years and $538,000 for years 5 through 15, respectively. What is the average accounting return on this project?
Coca Cola Inc. is considering opening a new bottling plant in the Southeastern U.S. It anticipates...
Coca Cola Inc. is considering opening a new bottling plant in the Southeastern U.S. It anticipates that this plant will increase sales by $8 million per year over the next 15 years. Costs to operate the plant are estimated to be $3 million per year. The company estimates that the cost of constructing the plant along with the cost of the equipment will be $30 million. These costs can be depreciated using straight-line depreciation. At the end of 15 years,...
You are considering opening a new plant. The plant will cost $101.8 million up front and will take one year to build.
You are considering opening a new plant. The plant will cost $101.8 million up front and will take one year to build. After that it is expected to produce profits of $30.9 million at the end of every year of production. The cash flows are expected to last forever. Calculate the NPV of this investment opportunity if your cost of capital is 7.8%.Should you make the investment? Calculate the IRR and use it to determine the maximum deviation allowable in...
You are considering opening a new plant. The plant will cost $99.5 million up front and will take one year to build.
Please show all work and how to input it into a fin calculator You are considering opening a new plant. The plant will cost $99.5 million up front and will take one year to build. After that it is expected to produce profits of$28.9 million at the end of every year of production. The cash flows are expected to last forever. Calculate the NPV of this investment opportunity if your cost of capital is 8.2%. Should you make the​ investment?...
Badger Billing is considering opening a new production facility in Madison, Wisconsin. In deciding whether to...
Badger Billing is considering opening a new production facility in Madison, Wisconsin. In deciding whether to proceed with the project, the company has gathered the follwing information: The estimated up-front cost of constructing the new facility at t=0 is $12 million. For tax purposes, the facility will be depreciated on a straight-line basis of 5 years (eg: $2.4 million/year) Badger will operate the facility for four (4) years. The company estimates that the facility can be sold at the end...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT