In: Accounting
The answer to the following question with an example:
Absorption Costing
1.Absorption Costing allocates all the costs to the individual production units .
2.It incurs cost in the form of material ,labor and overheads to produce units.
3.The unit cost is arrived at by dividing the number of units to the unit cost of production.
4.It takes into account all the costs involved like the variable and the fixed cost also.
Consider the following example of a Company XYZ
Direct Material Cost per unit $10
Direct Labour Cost per unit $30
Variable Overhead cost per unit $50
Total Variable Cost per unit $90
Fixed Overhead $100000
Units of Production 10000
Fixed OH per unit $10
Total Cost Per Unit $100
This is a straight forward method and there are concerns about whether this method can give accurate results.
The drawbacks of traditional or the absorption costing is that how can it handle the allocation of the fixed overheads Since the overhead costs are not directly traceable to production as there can be increase and decrease of production levels.So there is concern about the fixed overheads which can allocated based on the labour or the machine hrs as there can be under or overabsorption of overheads
Activity Based Costing.
It is costing method which can overcome the problems of the traditional costing and there can be bases based on which the overhead costs can be allocated to different activities in the production process.which are called the drivers.Following are the steps
Step a. To determine the activities which are identified as key
Step b To determine the driver for each key activity
Step c To calculate the cost of every key activities
Step d To Calculate the allocation rate for each activity by dividing the activity cost by the allocation proprtions.
Step e To allocate the cost to the cost via this allocation proportions.
Example X is a manufacuturer and incurs the following activties and costs
Activity $ Cost Driver $ Cost per Cost Driver
Assembly 76000 Number of labour
hrs 15750 4.8 /labor hrs
Cutting and
Sewing 85000 No of Machine
hrs 18630 4.56/machine hrs
Finishing 11600 No of Units 6500 1.78 /unit
It receives an order to produce and ship 1500 units .The overhead cost for this order is calculated as below:
Activity Activity usuage Cost per Cost Driver Total Overhead Cost
Assembly 2250 4.8 /labour hr 10800
Cutting and
Sewing 3084 4.6 /machine hr 14186
Finishing 1500 1.8 /unit 2700
27686
using the multiple allocation rates makes more accuracy in the calculation and it results in better cost control and decision making.Suppose if the shipping costs are allocated on the basis of number of labor units it will not be justifiable since it is not labor intensive and shipping charges can be allocated on the number of units shipped.