Question

In: Accounting

Accessory World makes floor mats for the automobile industry. Finished sets of mats must pass through...

Accessory World makes floor mats for the automobile industry. Finished sets of mats must pass
through two departments: Cutting and Coating. Large sheets of synthetic material are cut to size in
the Cutting Department and then transferred to the Coating Department, where each set is sprayed
with a chemical coating for improved durability. The following information pertains to May activity
in the Cutting Department:
EXERCISE 18.10
Process Costing through
Two Departments:
Department I
LO18-2 through LO18-5
Cost data:
Total cost of beginning inventory on May 1 . . . . . . . . . . . . . . . . . . . . . . . . . $45,300
Direct materials costs incurred in May. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11,925
Conversion costs incurred in May . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84,525
Cut sets transferred in during May. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ?
Physical units data:
Units in process, May 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6,000 sets
Units started in May . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ? sets
Units in process, May 31 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9,000 sets
Percentage of completion data:
Direct materials, May 1. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 60%
Conversion, May 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 80
Cut sets transferred in, May 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ?
Direct materials, May 31. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 70%
Conversion, May 31 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 90
Cut sets transferred in, May 31 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ?
Cost data:
Total cost of beginning inventory on May 1 . . . . . . . . . . . . . . . . . . . . . . . . . $ 44,800
Direct materials costs incurred in May. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 200,000
Conversion costs incurred in May . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 87,200
Physical units data:
Units in process, May 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8,000 sets
Units started in May . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 50,000 sets
Units in process, May 31 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10,000 sets
Percentage of completion data:
Direct materials, May 1. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 100%
Conversion, May 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 80
Direct materials, May 31. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 100%
Conversion, May 31 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
a. Prepare a schedule showing: (1) the number of mat sets transferred from the Cutting Department
to the Coating Department in May, and (2) the number of mat sets started and completed
by the Cutting Department in May.
b. Compute the equivalent units of input resources for the Cutting Department in May.
c. Compute the cost per equivalent unit of input resource for the Cutting Department in May.
d. Prepare the summary journal entry required to transfer the cost of completed mat sets from the
Cutting Department to the Coating Department in May.
e. Compute the total cost assigned to the Cutting Department’s ending inventory on

Solutions

Expert Solution

FIFO method
Beggining units 8000 Transferred out 48,000
Started into production 50000 Ending units 10,000
58000 58000
Equivalent units Material Conversion
Beginning units 8000 8000
Completion in current period 0% 20%
A 0 1600
Units started and completed 40000 40000
Completion 100% 100%
B 40000 40000
Ending Units 10,000 10,000
Completion 100% 20%
C 10000 2000
Total units A+B+C 50000 43600
Cost per equivalent units
Per unit cost Cost Total units Per unit cost
Material cost 200000 50000 4.00
Conversion cost 87200 43600 2.00
Total 287200 6.00
Beginning work in progress A 44800
Beginning inventory completed
Completion 0% 20%
Per unit cost 4.00 2.00
Units 8000 8000
Total cost   B 0 3200 3200
Units started and completed
Completion 100% 100%
Per unit cost 4.00 2.00
Units 40000 40000
Total cost    C 160000 80000 240000
Total cost A+B+C 160000 83200 288000
Ending work in progress
Completion 100% 20%
Per unit cost 4.00 2.00
Units 10,000 10,000
Total cost     40000 4000 44000
Total cost accounted for 332000
287200

Related Solutions

Accessory World makes floor mats for the automobile industry. Finished sets of mats must pass through...
Accessory World makes floor mats for the automobile industry. Finished sets of mats must pass through two departments: Cutting and Coating. Large sheets of synthetic material are cut to size in the Cutting Department and then transferred to the Coating Department, where each set is sprayed with a chemical coating for improved durability. The following information pertains to May activity in the Cutting department: Cost data: Total cost of beginning inventory on May 1 . . . . . ....
Myer’s Treats makes institutional cakes. Finished cakes must pass through two departments: Mixing and Baking. Vats...
Myer’s Treats makes institutional cakes. Finished cakes must pass through two departments: Mixing and Baking. Vats of cake batter are processed in the Mixing Department and then transferred to the Baking Department, where individual cakes are baked, cooled, and frosted. There were 500 gallons of partially mixed batter in the Mixing Department’s inventory on August 1. The batter was 100 percent complete with respect to direct materials, but only 30 percent complete with respect to conversion. Manufacturing costs assigned to...
Myer’s Treats makes institutional cakes. Finished cakes must pass through two departments: Mixing and Baking. Vats...
Myer’s Treats makes institutional cakes. Finished cakes must pass through two departments: Mixing and Baking. Vats of cake batter are processed in the Mixing Department and then transferred to the Baking Department, where individual cakes are baked, cooled, and frosted. There were 500 gallons of partially mixed batter in the Mixing Department’s inventory on August 1. The batter was 100 percent complete with respect to direct materials, but only 30 percent complete with respect to conversion. Manufacturing costs assigned to...
Another student must pass through 12 sets of traffic lights on his way to university each...
Another student must pass through 12 sets of traffic lights on his way to university each day. Suppose that each of the lights is green 36% of the time, yellow 5% of the time, and red 59% of the time. Suppose it is known that the traffic lights function independently. (a) What is the probability that the student encounters exactly five red lights on his way to university one day? (b) What is the probability that the student encounters at...
12 structures light must pass through in order to get through the eye and reach the...
12 structures light must pass through in order to get through the eye and reach the actual photoreceptors called cones the first ten are: Bulbar Conjunctiva Cornea Aqueous Humor Lens Vitreous Humor Ganglion Cell layer Inner synaptic layer Bipolar Layer Outer Synaptic Layer Photoreceptor Layer are there any im missing or what would be the last two. i have to have twelve.
A commuter must pass through five traffic lights on her way to work and will have...
A commuter must pass through five traffic lights on her way to work and will have to stop at each one that is red. She estimates the probability model for the number of red lights she hits (x), as shown below: x 0 1 2 3 4 5 p(x) 0.04 0.23 p 0.1 0.1 0.1 a)Find the probability that she hits at most 3 red lights. Answer to 2 decimal places. b)Find the probability that she hits at least 3...
A commuter must pass through five traffic lights on her way to work and will have...
A commuter must pass through five traffic lights on her way to work and will have to stop at each one that is red. She estimates the probability model for the number of red lights she hits (x), as shown below: x 0 1 2 3 4 5 p(x) 0.03 0.21 p 0.1 0.1 0.05 Find the probability that she hits at most 3 red lights. Answer to 2 decimal places. Tries 0/5 Find the probability that she hits at...
My topic is an automobile Industry Please write between 500-600 world and put citations in APA...
My topic is an automobile Industry Please write between 500-600 world and put citations in APA format at the end. Thank you If you were to hire an operations manager for your chosen business (assume that your business has scaled in size so that you would need an ops manager), what would their duties be, and what skills and abilities would you have been looking for when you hired them? Be sure to cite.
All airport passengers at the Capital City Airport must pass through a security screening area before...
All airport passengers at the Capital City Airport must pass through a security screening area before proceeding to the boarding area. The airport has three screening stations available, and the facility managers must decide how many to open at any particular time. The average time for processing one passenger at each screening station is 0.5 minutes. On Saturday morning the arrival rate is 3.3 passengers per minute. Assume that processing times at each screening station follow an exponential distribution and...
All airplane passengers at the Lake City Regional Airport must pass through a security screening area...
All airplane passengers at the Lake City Regional Airport must pass through a security screening area before proceeding to the boarding area. The airport has three screening stations available, and the facility manager must decide how many to have open at any particular time. The service rate for processing passengers at each screening station is 2.5 passengers per minute. On Monday morning the arrival rate is 3 passengers per minute. Assume that processing times at each screening station follow an...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT