In: Accounting
Accessory World makes floor mats for the automobile industry.
Finished sets of mats must pass
through two departments: Cutting and Coating. Large sheets of
synthetic material are cut to size in
the Cutting Department and then transferred to the Coating
Department, where each set is sprayed
with a chemical coating for improved durability. The following
information pertains to May activity
in the Cutting Department:
EXERCISE 18.10
Process Costing through
Two Departments:
Department I
LO18-2 through LO18-5
Cost data:
Total cost of beginning inventory on May 1 . . . . . . . . . . . .
. . . . . . . . . . . . . $45,300
Direct materials costs incurred in May. . . . . . . . . . . . . . .
. . . . . . . . . . . . . . 11,925
Conversion costs incurred in May . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . 84,525
Cut sets transferred in during May. . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . ?
Physical units data:
Units in process, May 1 . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . 6,000 sets
Units started in May . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . ? sets
Units in process, May 31 . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . 9,000 sets
Percentage of completion data:
Direct materials, May 1. . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . 60%
Conversion, May 1 . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . 80
Cut sets transferred in, May 1 . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . ?
Direct materials, May 31. . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . 70%
Conversion, May 31 . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . 90
Cut sets transferred in, May 31 . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . ?
Cost data:
Total cost of beginning inventory on May 1 . . . . . . . . . . . .
. . . . . . . . . . . . . $ 44,800
Direct materials costs incurred in May. . . . . . . . . . . . . . .
. . . . . . . . . . . . . . 200,000
Conversion costs incurred in May . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . 87,200
Physical units data:
Units in process, May 1 . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . 8,000 sets
Units started in May . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . 50,000 sets
Units in process, May 31 . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . 10,000 sets
Percentage of completion data:
Direct materials, May 1. . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . 100%
Conversion, May 1 . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . 80
Direct materials, May 31. . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . 100%
Conversion, May 31 . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . 20
a. Prepare a schedule showing: (1) the number of mat sets
transferred from the Cutting Department
to the Coating Department in May, and (2) the number of mat sets
started and completed
by the Cutting Department in May.
b. Compute the equivalent units of input resources for the Cutting
Department in May.
c. Compute the cost per equivalent unit of input resource for the
Cutting Department in May.
d. Prepare the summary journal entry required to transfer the cost
of completed mat sets from the
Cutting Department to the Coating Department in May.
e. Compute the total cost assigned to the Cutting Department’s
ending inventory on
FIFO method | |||
Beggining units | 8000 | Transferred out | 48,000 |
Started into production | 50000 | Ending units | 10,000 |
58000 | 58000 | ||
Equivalent units | Material | Conversion | |
Beginning units | 8000 | 8000 | |
Completion in current period | 0% | 20% | |
A | 0 | 1600 | |
Units started and completed | 40000 | 40000 | |
Completion | 100% | 100% | |
B | 40000 | 40000 | |
Ending Units | 10,000 | 10,000 | |
Completion | 100% | 20% | |
C | 10000 | 2000 | |
Total units A+B+C | 50000 | 43600 | |
Cost per equivalent units | |||
Per unit cost | Cost | Total units | Per unit cost |
Material cost | 200000 | 50000 | 4.00 |
Conversion cost | 87200 | 43600 | 2.00 |
Total | 287200 | 6.00 |
Beginning work in progress A | 44800 | ||
Beginning inventory completed | |||
Completion | 0% | 20% | |
Per unit cost | 4.00 | 2.00 | |
Units | 8000 | 8000 | |
Total cost B | 0 | 3200 | 3200 |
Units started and completed | |||
Completion | 100% | 100% | |
Per unit cost | 4.00 | 2.00 | |
Units | 40000 | 40000 | |
Total cost C | 160000 | 80000 | 240000 |
Total cost A+B+C | 160000 | 83200 | 288000 |
Ending work in progress | |||
Completion | 100% | 20% | |
Per unit cost | 4.00 | 2.00 | |
Units | 10,000 | 10,000 | |
Total cost | 40000 | 4000 | 44000 |
Total cost accounted for | 332000 | ||
287200 |