Question

In: Finance

5. Consider the following project data: A 2 million feasibility study will be conducted at t...

5. Consider the following project data: A 2 million feasibility study will be conducted at t =0. If the study indicates potential, the firm will spend 10 million at t= 1 to build a prototype. The best estimate is that there is an 80% chance that the study will indicate potential and 20% chance that it will not. If reception of the prototype is good the firm will spend 350 million to build a production plant at t=2. The best estimate is that there is a 70% chance that the prototypes’ reception will be poor. If the plant is built, there’s a 60% chance of a t=3 cash inflow of 300 million and a 40% chance of 150 million cash inflow. If the inflow at t=3 is 300 million, there are 30% and 70% chances of 160 million and 90 million inflows respectively at t=4. If the inflow at t=3 is 150 million, there are 80% and 20% chances of 210 million and 140 million inflows respectively at t=4. The plant has a salvage value of 50 million at t=5. If the appropriate cost of capital is 15% what is the project’s expected NPV?

Solutions

Expert Solution

Time Cash-flows
0 -2
1 -8
2 -105
3 240
4 145
5 50

At t=0

Investment of 2 million

At t=1

If the study indicates potential  the firm will spend 10 million

80% chance that the study will indicate potential

Expected cash-flow = 0.8 * (-10) = -$8 million

At t=2

If reception of the prototype is good the firm will spend 350 million and the best estimate is that there is a 30% (100%-70%) chance that the prototypes’ reception will be good

Expected cash-flow = 0.3*(-350) = -$105 million

At t=3

There’s a 60% chance of a t=3 cash inflow of 300 million and a 40% chance of 150 million

Expected cash-flow = 0.6*300+0.4*150 = $240 million

At t=4

If the inflow at t=3 is 300 million, there are 30% and 70% chances of 160 million and 90 million inflows
respectively at t=4.

If the inflow at t=3 is 150 million, there are 80% and 20% chances of 210 million and 140 million inflows respectively at t=4.

Expected cash-flow = (0.6*0.3*160)+(0.6*0.7*90)+(0.4*0.8*210)+(0.4*0.2*140) = $145 million

At t=5

Salvage value of 50 million

Time Cash-flows (in $millions)
0 -2
1 -8
2 -105
3 240
4 145
5 50

We find the function NPV to find the Project's expected NPV

NPV = Initial investment + NPV(Cost of capital, Cash-flows from year 1-5)

Cost of capital = 15%

Time Cash-flows (in $millions)
0 -2
1 -8
2 -105
3 240
4 145
5 50
NPV (in $millions) 177.2153464

Hence the project's expected NPV = $177.2153464 million = $177,215,346.4


Related Solutions

5. Consider the following project data: A Shs 2 million feasibility study will be conducted at...
5. Consider the following project data: A Shs 2 million feasibility study will be conducted at t =0. If the study indicates potential, the firm will spend Shs 10 million at t= 1 to build a prototype. The best estimate is that there is an 80% chance that the study will indicate potential and 20% chance that it will not. If reception of the prototype is good the firm will spend Sh. 350 million to build a production plant at...
Consider the following project data: A Shs 4 million feasibility study will be conducted at t...
Consider the following project data: A Shs 4 million feasibility study will be conducted at t =0. If the study indicates potential, the firm will spend Shs 20 million at t= 1 to build a prototype. The best estimate is that there is an 80% chance that the study will indicate potential and 20% chance that it will not. If reception of the prototype is good the firm will spend Sh. 700 million to build a production plant at t=2....
The life of the project is 5 years.  A feasibility study has been undertaken at...
The life of the project is 5 years.  A feasibility study has been undertaken at a cost of $2 million. The study concluded that at the end of the project the cost of restoring the environment of the mine would be approximately $ 1.2 million.  The project would require capital equipment of $8 million. The shipping and installation costs for this equipment are around $40,000. This equipment will be depreciated on a straight‐line basis over the life of...
Consider the data in the following table, obtained from a cohort study conducted by Iso and...
Consider the data in the following table, obtained from a cohort study conducted by Iso and colleagues [Isa H, Date C, Yamamoto A, et al. Smoking cessation and mortality from cardiovascular disease among Japanese men and women. The JACC study. Am J Epidmeiol. 2005;161(2):170-179.]. Total Cardiovascular Disease According to Smoking Status Disease Current Smoker Cases Person-years Yes 882 — 220,965 No 673 — 189,254 Calculate the rate ratio and corresponding 95% confidence interval for these data. Express your answer to...
 A detailed overview of the feasibility study conducted at all three levels in relation to...
 A detailed overview of the feasibility study conducted at all three levels in relation to internet banking Technical Feasibility (“Can it be built?”)  Operational Feasibility (“Will it work?”) and  Financial/Economic Feasibility (“Does it generate reasonable net profits or does it bring net economic benefit?”)  Using at least TWO (2) appropriate investment appraisal tools, make recommendations on the why the particular project is feasible or otherwise. KINDLY ANSWER ASAP VERY IMPORTANT
After paying $3 million for a feasibility study, Stanley wrote a proposal with the following cash...
After paying $3 million for a feasibility study, Stanley wrote a proposal with the following cash flow estimates for a 25-year capital project. Equipment cost: $34 million, Shipping costs: $1 million, Installation: $19 million, Salvage: $4, Working capital investment: $2 million, Revenues are expected to increase by $20 million per year and cash operating expenses by $9 million per year. The firm’s marginal tax rate is 40 percent, its weighted average cost of capital is 9%, and the firm requires...
5. Consider the following data from an independent measures study: Treatment 1          Treatment 2      n...
5. Consider the following data from an independent measures study: Treatment 1          Treatment 2      n = 4                        n = 4 mean = 4              mean = 11 SS = 96                   SS = 100 Is there a evidence for a treatment effect? (α = .05, two tails). 6. A sample of n = 16 difference scores from a repeated measures experiment has SS = 440. The average difference score is 3. For a two-tailed test, α = .05, is this a...
Consider a project with the following cash flows: $3,500 at t=1, $12,500 at t=2, $15,000 at...
Consider a project with the following cash flows: $3,500 at t=1, $12,500 at t=2, $15,000 at t=3, $15,000 at t=4. The Discounted Payback Period of this project is 3.3 years. The appropriate discount rate is 11%. Find the Net Present Value of the project. (Note that the cash flow for t=0 is not provided to you.) A.  $6,916.67 B.  ($11,852.73) C.  ($1,627.27) D.  $4,952.58 E.  Insufficient information.
Rate-study data In a study conducted at the same temperature, the following data for reaction producing...
Rate-study data In a study conducted at the same temperature, the following data for reaction producing nitrosyl bromide were collected. Trial Initial [NO] (M) Initial [Br2] (M) Initial rate (M/s) 1 0.150 0.240 48 2 0.300 0.240 191 3 0.300 0.480 383 Part C What is the rate of the reaction when the initial concentration of NO is 0.400 M and that of Br2 is 0.235 M ? Express your answer to three significant figures and include the appropriate units.
Consider the following time series data. t 1 2 3 4 5 6 7 yt 10...
Consider the following time series data. t 1 2 3 4 5 6 7 yt 10 9 7 8 6 4 4 a. Construct a time series plot. What type of pattern exists in the data? b. Develop the linear trend equation for this time series. c. What is the forecast for t=8?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT