Question

In: Finance

5. Consider the following project data: A 2 million feasibility study will be conducted at t...

5. Consider the following project data: A 2 million feasibility study will be conducted at t =0. If the study indicates potential, the firm will spend 10 million at t= 1 to build a prototype. The best estimate is that there is an 80% chance that the study will indicate potential and 20% chance that it will not. If reception of the prototype is good the firm will spend 350 million to build a production plant at t=2. The best estimate is that there is a 70% chance that the prototypes’ reception will be poor. If the plant is built, there’s a 60% chance of a t=3 cash inflow of 300 million and a 40% chance of 150 million cash inflow. If the inflow at t=3 is 300 million, there are 30% and 70% chances of 160 million and 90 million inflows respectively at t=4. If the inflow at t=3 is 150 million, there are 80% and 20% chances of 210 million and 140 million inflows respectively at t=4. The plant has a salvage value of 50 million at t=5. If the appropriate cost of capital is 15% what is the project’s expected NPV?

Solutions

Expert Solution

Time Cash-flows
0 -2
1 -8
2 -105
3 240
4 145
5 50

At t=0

Investment of 2 million

At t=1

If the study indicates potential  the firm will spend 10 million

80% chance that the study will indicate potential

Expected cash-flow = 0.8 * (-10) = -$8 million

At t=2

If reception of the prototype is good the firm will spend 350 million and the best estimate is that there is a 30% (100%-70%) chance that the prototypes’ reception will be good

Expected cash-flow = 0.3*(-350) = -$105 million

At t=3

There’s a 60% chance of a t=3 cash inflow of 300 million and a 40% chance of 150 million

Expected cash-flow = 0.6*300+0.4*150 = $240 million

At t=4

If the inflow at t=3 is 300 million, there are 30% and 70% chances of 160 million and 90 million inflows
respectively at t=4.

If the inflow at t=3 is 150 million, there are 80% and 20% chances of 210 million and 140 million inflows respectively at t=4.

Expected cash-flow = (0.6*0.3*160)+(0.6*0.7*90)+(0.4*0.8*210)+(0.4*0.2*140) = $145 million

At t=5

Salvage value of 50 million

Time Cash-flows (in $millions)
0 -2
1 -8
2 -105
3 240
4 145
5 50

We find the function NPV to find the Project's expected NPV

NPV = Initial investment + NPV(Cost of capital, Cash-flows from year 1-5)

Cost of capital = 15%

Time Cash-flows (in $millions)
0 -2
1 -8
2 -105
3 240
4 145
5 50
NPV (in $millions) 177.2153464

Hence the project's expected NPV = $177.2153464 million = $177,215,346.4


Related Solutions

5. Consider the following project data: A Shs 2 million feasibility study will be conducted at...
5. Consider the following project data: A Shs 2 million feasibility study will be conducted at t =0. If the study indicates potential, the firm will spend Shs 10 million at t= 1 to build a prototype. The best estimate is that there is an 80% chance that the study will indicate potential and 20% chance that it will not. If reception of the prototype is good the firm will spend Sh. 350 million to build a production plant at...
Consider the data in the following table, obtained from a cohort study conducted by Iso and...
Consider the data in the following table, obtained from a cohort study conducted by Iso and colleagues [Isa H, Date C, Yamamoto A, et al. Smoking cessation and mortality from cardiovascular disease among Japanese men and women. The JACC study. Am J Epidmeiol. 2005;161(2):170-179.]. Total Cardiovascular Disease According to Smoking Status Disease Current Smoker Cases Person-years Yes 882 — 220,965 No 673 — 189,254 Calculate the rate ratio and corresponding 95% confidence interval for these data. Express your answer to...
 A detailed overview of the feasibility study conducted at all three levels in relation to...
 A detailed overview of the feasibility study conducted at all three levels in relation to internet banking Technical Feasibility (“Can it be built?”)  Operational Feasibility (“Will it work?”) and  Financial/Economic Feasibility (“Does it generate reasonable net profits or does it bring net economic benefit?”)  Using at least TWO (2) appropriate investment appraisal tools, make recommendations on the why the particular project is feasible or otherwise. KINDLY ANSWER ASAP VERY IMPORTANT
5. Consider the following data from an independent measures study: Treatment 1          Treatment 2      n...
5. Consider the following data from an independent measures study: Treatment 1          Treatment 2      n = 4                        n = 4 mean = 4              mean = 11 SS = 96                   SS = 100 Is there a evidence for a treatment effect? (α = .05, two tails). 6. A sample of n = 16 difference scores from a repeated measures experiment has SS = 440. The average difference score is 3. For a two-tailed test, α = .05, is this a...
Consider a project with the following cash flows: $3,500 at t=1, $12,500 at t=2, $15,000 at...
Consider a project with the following cash flows: $3,500 at t=1, $12,500 at t=2, $15,000 at t=3, $15,000 at t=4. The Discounted Payback Period of this project is 3.3 years. The appropriate discount rate is 11%. Find the Net Present Value of the project. (Note that the cash flow for t=0 is not provided to you.) A.  $6,916.67 B.  ($11,852.73) C.  ($1,627.27) D.  $4,952.58 E.  Insufficient information.
Rate-study data In a study conducted at the same temperature, the following data for reaction producing...
Rate-study data In a study conducted at the same temperature, the following data for reaction producing nitrosyl bromide were collected. Trial Initial [NO] (M) Initial [Br2] (M) Initial rate (M/s) 1 0.150 0.240 48 2 0.300 0.240 191 3 0.300 0.480 383 Part C What is the rate of the reaction when the initial concentration of NO is 0.400 M and that of Br2 is 0.235 M ? Express your answer to three significant figures and include the appropriate units.
-Take a small project -and discuss the different phases of initiation feasibility study project selection Project...
-Take a small project -and discuss the different phases of initiation feasibility study project selection Project planning Project implantation Project monitoring and evaluation and discuss the different phases of 1. initiation 2. feasibility study 3. project selection 4. Project planning 5. Project implantation 6. Project monitoring and evaluation
Consider the following time series data. t 1 2 3 4 5 6 7 yt 10...
Consider the following time series data. t 1 2 3 4 5 6 7 yt 10 9 7 8 6 4 4 a. Construct a time series plot. What type of pattern exists in the data? b. Develop the linear trend equation for this time series. c. What is the forecast for t=8?
Consider the following studies: Study 1: A study was conducted to investigate the effects of alcohol...
Consider the following studies: Study 1: A study was conducted to investigate the effects of alcohol consumption on handeye co-ordination. 200 people were interviewed and their level of alcohol consumption over the previous five years was assessed and classified as either low, medium or high. Each person was then given a series of tasks resulting in a hand-eye co-ordination score. Study 2: A study was conducted to investigate the efficacy of a new iron tablet compared to a currently used...
A company is evaluating a project that would require a $5 million investment today (t = 0).
Using Excel (if applicable),A company is evaluating a project that would require a $5 million investment today (t = 0). The after-tax cash flows would depend on whether a new property tax is imposed. There is a 75% chance that the tax will pass and 25% chance that it won't. If the tax passes, the project will produce after-tax cash flows of $1,200,000 at the end of each of the next 5 years. If the tax doesn't pass, the after-tax...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT