Leo Company has identified the following overhead costs and cost
drivers for next year:
Overhead Item
Expected Costs
Cost Driver
Maximum Quantity
Setup costs
$1,152,000
Number of setups
4,800
Ordering costs
320,000
Number of orders
40,000
Maintenance
1,600,000
Machine-hours
64,000
Power
160,000
Kilowatt-hours
400,000
The following is one of the jobs completed during the year:
Job 201
Direct materials
$18,000
Direct labor
$24,000
Units completed
750
Direct labor-hours
180
Number of setups
12
Number of orders
16
Machine-hours
360
Kilowatt-hours...