Question

In: Operations Management

PART A Task 1 – Prepare the Approval to Proceed Document Note: This task is to...

PART A

Task 1 – Prepare the Approval to Proceed Document

Note: This task is to take the place of Element 1 – Establish Project 1 from BSBPMG521 – Manage Project Integration.

You are to complete the Approval to Proceed template carefully as it outlines the project parameters that you are to work within. If this is an active project, then you should complete this with your project sponsor. If not, then you will have to complete it yourself.

This document will take the place of the Project Charter (an important project initiation document) and must be approved by your assessor before you can progress any further with your chosen project. Your assessor will approve this document if he/she feels there is sufficient information to enable you to write the detailed project plan. Therefore, it is best to get this document in early to give you time to develop the rest of the project plan required to complete this diploma qualification.

Once approved, you will be able to begin preparing your Scope Management Plan and Change Management Plan (see Question 3 in Part B).

Task 2 – Conduct Project Authorisation Activities

This task is co-assessed with Question 1 from BSBPMG520 – Manage Project Governance.

In Table 1 below identify who has the role to authorise all project plans, financial and procurement delegations for your chosen project. Ensure these align with those provided in your governance procedure from BSBPMG520.

Examples only are provided in the table shaded below. Change them to reflect your project requirements.

Authorisation or Delegation

Details

Person

Comments

Approval of Project

Scope, Schedule, HR, Baseline Plans

John Smith

Once plans are written and checked by Project Manager they are to be authorised within 24 hours. The project cannot proceed without these authorisations

Financial Delegation

< $5,000

Project Manager – Col Ray

All financial delegations up to this amount. See below for delegations above this amount

Table 1 – Project Authorisations and Delegations

Solutions

Expert Solution

Answer: The approval of the project details and project stages are assigned to the key stakeholder of the organization who has the overall responsibilitiesof the organization in terms of project sposoring, new project introduction, business development , R&D - engineering and senior management team with financial directors. So all these are the key people in the organization who use to approve the project stages in the organzation for projects.

Project Charter : Project charter is the first approvaldocument and it needs to be approved by following key people as below

  • Project Manager
  • Project Sponser/ Director Progam Management
  • Director -Engineering
  • Director - Sales and Business Development
  • Director - Manufaturing and Supply Chain
  • Director- Finance

Project Contract : Project charter is the second key stage approval document and it needs to be approved by following key people as below

  • Project Manager
  • Project Sponser / Director Progam Management
  • Director -Engineering
  • Director - Sales and Business Development
  • Director - Manufaturing and Supply Chain
  • Director- Finance
  • Director - Customer care and service

Project Plan :This is the key docuemnt and it needs to be approved by following peoples

  • Project Manager
  • Project Sponser / Director Progam Management
  • Director -Engineering
  • Director - Sales and Business Development
  • Director - Manufaturing and Supply Chain
  • Director - Customer care and service

Task 2 :

Approval of the Project : The priject apporval needs to be authorized and approved by below key people in the organization as below

  • Project Manager
  • Project Sponser / Director Progam Management
  • Director -Engineering
  • Director - Sales and Business Development
  • Director - Manufaturing and Supply Chain
  • Director- Finance
  • Director - Customer care and service
  • Business Head

Financial Delegation <$5000 : This financial approval to be obtained from the below people in below order -

  1. Project Manager
  2. Project Sonsor
  3. Director Finance
  4. Director Supply chain and manufacturing
  5. Business Head

Related Solutions

What is the name of the document that a firm will need to get ASIC’s approval...
What is the name of the document that a firm will need to get ASIC’s approval before they can conduct an IPO? How is that document lodged and approved?
18.         As a project manager of a certain project you note that the project cannot proceed...
18.         As a project manager of a certain project you note that the project cannot proceed as planned due to several issues. In order to ensure the project objectives are met you should take the following measures except: Select one: A. Notify the project team about the issues and guiding them to resolve issues B. Alert the project sponsor about the issues and seeking their advice D. Change the business case of the project to match the alterations occurred due...
Which part of an HTML5 file specifies the document language? The document character set? The document...
Which part of an HTML5 file specifies the document language? The document character set? The document character encoding? For all 3 question above show the HTML code. Consider UTF-8 and UTF-16 character encodings. Why do we say UTF-8 is ASCII preserving. Are there situations when a correctly specified table has rows containing different number of td elements? Explain. Using notepad ++ Practice row and column spanning by creating an HTML table to present the mirror image of the following: <table...
Binary Search Tree (Part 1): Note: This is the first part of a 2-part lab. Only...
Binary Search Tree (Part 1): Note: This is the first part of a 2-part lab. Only this part is due on Oct 29. But please get it working or you will struggle with the second part. For the second part, the data type will be changing. For now, it is a string. Contents Explanation: 2 BST.cpp: 2 Code you must write: 2 bool insert(string s) (7): 2 TNode *find(string s) (4): 2 void printTreeIO(Tnode *n)(3): 2 void printTreePre(Tnode *n) (3):...
Conducting a Bank Reconciliation Note: Part 1 is the bank reconciliation itself and Part 2 is...
Conducting a Bank Reconciliation Note: Part 1 is the bank reconciliation itself and Part 2 is for the adjusting entries. Instructions: Using the information below, complete the bank reconciliation for both the "book" and the "bank" sides and create all necessary adjusting journal entries. Details: Cash balance per company's records as of July 31st was $66,955. Bank statement balance as of July 31st was $15,875. A deposit in the amount of $52,000 was deposited into the night depository of the...
Part 1: netstat Run the 'netstat' command and review the output. Note that the first part...
Part 1: netstat Run the 'netstat' command and review the output. Note that the first part of the output is a list of active Internet connections, and the second part is a list of active sockets. The format of each part is different (i.e. different number of columns per line, and different column headers). 1. Write a bash command line that will display the number of active Internet connections as reported by 'netstat'. Your output should be a single number....
Prove that all regular languages are context free. Note: Proof must proceed by structural induction on...
Prove that all regular languages are context free. Note: Proof must proceed by structural induction on regular expressions Please prove by Structural Induction. Will Upvote for correct answer. Thanks
Part I - Prepare and standardize a solution of Sodium Thiosulfate 1. Prepare 250 mL of...
Part I - Prepare and standardize a solution of Sodium Thiosulfate 1. Prepare 250 mL of a solution which is approximately 0.025 M Na2S2O3• 5H20. Because sodium thiosulfate is a hydrate, it cannot be used as a primary standard. It must be standardized in order to determine its exact concentration. (Note for Su’17: this solution has already been prepared for you). 2. Pipet 10.0 mL of 0.01 M KIO3 into a 150 mL Erlenmeyer flask. Add about 20 mL of...
1. List the mortgage approval process from pre-approval through to the deed to the property 2....
1. List the mortgage approval process from pre-approval through to the deed to the property 2. What is the Loan Processor role? Why is it significant to the Home Loan process? Who do they interact with and pass their findings to? 3. What is the Underwriter role? Why is it significant to the Home Loan process? Who do they interact with and pass their findings to? Why are they important to the loan process? 4. Discuss the important pieces of...
Based on information given in the attached Excel document, 1. Prepare journal entries and adjusting entries...
Based on information given in the attached Excel document, 1. Prepare journal entries and adjusting entries for September 2019 for your company. 2. Set up T-accounts and post your journal entries and adjusting entries to T-accounts. 3. Prepare your company’s pre-closing trial balance, as of September 30, 2019. 4. Prepare an income statement, in a good format, for the month of September 2019 for your company. 5. Prepare a statement of retained earnings, in a good format, for the same...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT