Material cost = $40 per unit
Labor hours = 10 per unit for the first unit, Labor cost = $10/hour
List the material and labor cost and labor + material cost for the first 8 units when the supplier utilizes a learning curve of 85%.
PLEASE PROVIDE THE FORMULA SO I ACTUALLY KNOW HOW TO DO THIS STUFF.
Unit |
Material Cost |
Labor Cost |
Total Cost |
1 |
$40 |
||
2 |
$80 |
||
3 |
120 |
||
4 |
$160 |
||
5 |
$200 |
||
6 |
$240 |
||
7 |
$280 |
||
8 |
$320 |