which of the following describes the define the work scope step in building a performance measurement baseline?
the. budget must be allocated before it is possible to define the work space
the work scope is held in management reserve until it is defined
the schedule must be developed before it is possible to define the work space
the contractor uses the contract statement of work as a key scope defining document
Correct answer: the contractor uses the contract statement of work as a key scope defining document
Reason: In the 'Define the work scope' stage, the contractor is supposed to understand the overall scope of the project from the customer and breakdown it into smaller components using WBS. The schedule and budget must be prepared in the subsequent stages.