In: Accounting
Net Present Value
Use Exhibit 12B.1 and Exhibit 12B.2 to locate the present value of an annuity of $1, which is the amount to be multiplied times the future annual cash flow amount.
Each of the following scenarios is independent. Assume that all cash flows are after-tax cash flows.
Required:
1. Compute the NPV for Campbell Manufacturing,
assuming a discount rate of 12%. If required, round all present
value calculations to the nearest dollar. Use the minus sign to
indicate a negative NPV.
$
Should the company buy the new welding system?
No
2. Conceptual Connection: Assuming a required
rate of return of 8%, calculate the NPV for Evee Cardenas'
investment. Round to the nearest dollar. If required, round all
present value calculations to the nearest dollar. Use the minus
sign to indicate a negative NPV.
$
Should she invest?
What if the estimated return was $135,000 per year? Calculate
the new NPV for Evee Cardenas' investment. Would this affect the
decision? What does this tell you about your analysis? Round to the
nearest dollar.
$
The shop be purchased. This reveals that the decision to accept or reject in this case is affected by differences in estimated
3. What was the required investment for Barker
Company's project? Round to the nearest dollar. If required, round
all present value calculations to the nearest dollar.
$
Net Present Value = Present Value of Future cash flows - Initial Investment
1) NPV of Campbell Manufacturing
Initial Investment = $ 2,850,000
After Tax future cash flow per Year = $ 480,000 per Year
Discount Rate = 12%
Life of the Project = 10 Years
Present value of Future cashflow = Future Cash flows per Year * Present Value of Annuity factor of discount rate
( Here future cash flows are uniform for all years that's why we take present value of annuity factor to get present value of all future cash flows. It's easy way to do this. If future cash flows are different for each year this will be not possible.In that case we can calculate each year cash flows using corresponding year P.V factor. and sum up all year P.V cashflow.)
Present value of annuity of 12% for 10 Years = 5.6502 (Refer p.v annuity table )
Present value of Future cashflow = 480000 * 5.6502 = $ 2712096
NPV = 2712096 - 2850000 = - 137904
Here NPV is a negative value so this project must be rejected
2) A) NPV of Evee Cardenas
Initial Investment = $ 180,000
After Tax future cash flow per Year = $ 40,000 per Year
Discount Rate = 8%
Life of the Project = 6 Years
Present value of Future cashflow = Future Cash flows per Year * Present Value of Annuity factor of discount rate
Present value of annuity of 8% for 6 Years = 4.6229 (Refer p.v annuity table )
Present value of Future cashflow = 40000 * 4.6229 = $ 184916
NPV = 184916 - 180000 = $ 4916
Here NPV is a positive value. So she must accept this project
B) If future cash flows per year is $135000
Present value of Future cashflow = 135000 * 4.6229 = 624091.5= 624092
NPV = 624092 - 180000 = $ 444092
In both cases NPV remain positive so project must be accepted in both case. So there is no need to change the decision. In second case she can earn more when compare with first one.
3) Required investment for Barker Company's project
Initial Investment = ?
After Tax future cash flow per Year = $ 135,000 per Year
Discount Rate = 10 %
Life of the Project = 8 Years
NPV of project = 63900
Present value of annuity of 10% for 8 Years = 5.3349 (Refer p.v annuity table )
Present value of Future cashflow = 135000 *5.3349 = $ 720211.5 = $ 720212
Here we need to find out initial investment
Net Present Value = Present Value of Future cash flows - Initial Investment
Here NPV and PV of future cashflows are known So
63900 = 720212 - Initial investment
Initial Investment = 720212 - 63900 = 656312