Jensen Fences uses job order costing. Manufacturing overhead is charged to individual jobs through the use of a predetermined overhead rate based on direct labor costs. The following information appears in the company’s Work in Process Inventory account for the month of June.

Debits to account:
Balance, June 1 $ 5,000
Direct materials 19,000
Direct labor 12,100
Manufacturing overhead (applied to jobs as 125% of direct labor cost) 15,125
Total debits to account $ 51,225
Credits to account:
Transferred to Finished Goods Inventory account 44,000
Balance, June 30 $ 7,225

Required:

a. Assuming that the direct labor charged to the jobs still in process at June 30 amounts to $1,600, compute the amount of manufacturing overhead and the amount of direct materials that have been charged to these jobs as of June 30.

b. Prepare general journal entries to summarize:

1. The manufacturing costs (direct materials, direct labor, and overhead) charged to production during June.

2. The transfer of production completed during June to the Finished Goods Inventory account.

3. The cash sale of 80 percent of the merchandise completed during June at a total sales price of $48,000. Show the related cost of goods sold in a separate journal entry.

Solutions

Expert Solution

Computation of Manufacturng Overhead and Direct Material Chargd to Job
Overhead application rate * 125%
Manufacturing overhead applied to Jobs( 1600 * 125/100) = $ 2,000
Manufacturing Overhead = $2000
Direct Material Charged to Job= Total cost of Job in Progress- Direct Labour - Manufacturing Overhead
$7225-$1600-$2000= $3625
Hence Direct Material Charged to Job would be $3625
S. No. Accoun Tittle Debit Credit
1 Work in Process Inventory $46,225.00
Material Inventory $19,000.00
Diirect Labour $12,100.00
Manufacturing Overhead $15,125.00
To record costs charged to job during June.
2 Finished Goods Inventory $44,000.00
Work in progress Inventory $44,000.00
3 cash $48,000.00
Sales $48,000.00
To record cash sale of 80% of goods completed in June.
Cost of goods sold ( $ 48000 * 80/100)= $38,400.00
Finished Goods Inventory $38,400.00
To record cost of goods sold.

Kindly rate it positively it would help me lot.


Related Solutions

Jensen Fences uses job order costing. Manufacturing overhead is charged to individual jobs through the use...
Jensen Fences uses job order costing. Manufacturing overhead is charged to individual jobs through the use of a predetermined overhead rate based on direct labor costs. The following information appears in the company’s Work in Process Inventory account for the month of June. Debits to account: Balance, June 1 $ 5,000 Direct materials 18,000 Direct labor 12,000 Manufacturing overhead (applied to jobs as 125% of direct labor cost) 15,000 Total debits to account $ 50,000 Credits to account: Transferred to...
Greenway Irrigation Systems uses job order costing and applies manufacturing overhead to individual jobs by using...
Greenway Irrigation Systems uses job order costing and applies manufacturing overhead to individual jobs by using predetermined overhead rates. In the Fabrication Department, overhead is applied on the basis of machine-hours, and in the Installation Department, it is applied on the basis of direct labor hours. At the beginning of the current year, management made the following budget estimates as a step toward determining the overhead application rates. Fabrication Installation Direct labor $ 132,000 $ 300,000 Manufacturing overhead $ 600,000...
The Collins Company uses a job-order costing system and applies manufacturing overhead cost to jobs on...
The Collins Company uses a job-order costing system and applies manufacturing overhead cost to jobs on the basis of the cost of materials used in production. At the beginning of the most recent year, the following estimates were made as a basis for computing the predetermined overhead rate for the year: Manufacturing overhead cost: $200,000 Direct materials cost: $160,000 The following transactions took place during the year (all purchases and services were acquired on account): a.) Raw materials purchased: $86,000....
ABC, Corp. is a manufacturing firm that uses job-order costing. The company applies overhead to jobs...
ABC, Corp. is a manufacturing firm that uses job-order costing. The company applies overhead to jobs using a predetermined overhead rate based on machine-hours. At the beginning of the year, the company estimated that it would work 50,000 machine-hours and incur $450,000 in manufacturing overhead cost. The following transactions were recorded for the year: a. Raw materials were purchased, $325,000. b. Raw materials were requisitioned for use in production, $175,000 ($100,000 direct and $75,000 indirect). c. The following employee costs...
Job Order Costing: Wadadli Products uses a job-order costing system Overhead costs are applied to jobs...
Job Order Costing: Wadadli Products uses a job-order costing system Overhead costs are applied to jobs on the basis of machine-hours. At the beginning of the year, management estimated that 170,000 machine-hours would be required for the periods estimated level of production. The company also estimated $212,500 of fixed manufacturing overhead expenses for the coming period and variable manufacturing overhead of $1.50 per machine hour. Required: 1. Compute the company’s predetermined overhead rate. 2. Assume that during the year of...
1. Benner Company uses a job-order costing system and applies manufacturing overhead to jobs using a...
1. Benner Company uses a job-order costing system and applies manufacturing overhead to jobs using a predetermined overhead rate based on direct labor hours. Manufacturing overhead and direct labor hours were estimated at $66,000 and 22,000 hours, respectively. In June, Job #461 was completed. Materials costs on the job totaled $4,923 and labor costs totaled $2,325 at $7.50 per hour (310 hours worked on this job). At the end of the year, it was determined that the company worked 23,975...
NH Company uses a job-order costing system. The company applies manufacturing overhead to jobs using a...
NH Company uses a job-order costing system. The company applies manufacturing overhead to jobs using a predetermined overhead rate based on direct labor-hours. Last year, manufacturing overhead and direct labor-hours were estimated at $80,000 and 16,000 hours respectively, for the year. In June, Job #300 was completed. Materials costs on the job totaled $1,500 and labor costs totaled $2,400 at $6 per hour. At the end of the year, it was determined that the company worked 15,000 direct labor-hours for...
The company uses a job-order costing system in which overhead is applied to jobs on the...
The company uses a job-order costing system in which overhead is applied to jobs on the basis of direct labor cost. Its predetermined overhead rate is based on a cost formula that estimated $94,500 of manufacturing overhead for an estimated activity level of $45,000 direct labor dollars. At the beginning of the year, the inventory balances were as follows: Raw materials $ 10,800 Work in process $ 4,400 Finished goods $ 8,900 During the year, the following transactions were completed:...
hardwood company uses a job order costing system that applies overhead cost to jobs on the...
hardwood company uses a job order costing system that applies overhead cost to jobs on the basis of machine hours. The companys predetermined overhead rate of $2.50 Per machine hour was based on the cost formula that estimates $237,500 of total manufacturing overhead for an estimated activity level of 95,000 machine hours. 1. Manufacturing Overhead Maintenance                          36,000                        ???                (a) Indirect Materials                    9,500 Indirect Labor                         75,000 Utilities                                    44,000 Insurance                                8,500 Depreciation                            56,000 Balance:                                    ???         Work in Process: Direct Materials              860,000 Direct...
Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs....
Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $81,900 Number of moves 3,500 Engineering 135,150 Number of change orders 8,500 Other overhead 240,000 Direct labor hours 48,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job 13-45 Job 13-46 Beginning balance...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT