In: Accounting
Cordon Corporation set the following standard unit costs for its single product:
Direct materials (25 lbs @ $4 per lb) $100 per unit
Direct labor (6 hrs @ $8 per hr) 48 per unit
Factory overhead – variable (6 hrs @ $5 per hr) 30 per unit
Factory overhead – fixed (6 hrs @ $7 per hr) 42 per unit
Total Standard cost $220 per unit
The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 60,000 units per quarter. The following flexible budget information is available:
Operating levels
70% 80% 90%
Production in units 42,000 48,000 54,000
Standard direct labor hours 252,000 288,000 324,000
Budgeted overhead
Fixed MOH $2,016,000 $2,016,000 $2,016,000
Variable MOH 1,260,000 1,440,000 1,620,000
During the current quarter, the company operated at 70% of capacity and produced 42,000 units of product: direct labor hours worked were 250,000. Units
Produced were assigned the following standard costs:
Direct materials (1,050,000 lbs @ $4 per lb.) $4,200,000
Direct labor (252,000 hrs @ $8 per hr) 2,016,000
Factory overhead (252,000 hrs @ $12 per hr) 3,024,000
Total standard cost $9,240,000
Actual costs incurred during the current quarter follow:
Direct materials (1,000,000 @ $4.25 per lb) $4,250,000
Direct labor (250,000 hrs @ $7.75 per hr) 1,937,500
Fixed factory overhead costs 1,960,000
Variable factory overhead costs 1,200,000
Total actual costs $9,347,500
Required:
Prepare the level 3 variance analysis on Direct materials, and Direct labor. Include a description of what occurred.
| 
 Material Price Variance  | 
||||||
| 
 (  | 
 Standard Rate  | 
 -  | 
 Actual Rate  | 
 )  | 
 x  | 
 Actual Quantity  | 
| 
 (  | 
 $ 4.00  | 
 -  | 
 $ 4.25  | 
 )  | 
 x  | 
 1000000  | 
| 
 -250000  | 
||||||
| 
 Variance  | 
 $ 250,000.00  | 
 Unfavourable-U  | 
||||
| 
 Material Quantity Variance  | 
||||||
| 
 (  | 
 Standard Quantity  | 
 -  | 
 Actual Quantity  | 
 )  | 
 x  | 
 Standard Rate  | 
| 
 (  | 
 1050000  | 
 -  | 
 1000000  | 
 )  | 
 x  | 
 $ 4.00  | 
| 
 200000  | 
||||||
| 
 Variance  | 
 $ 200,000.00  | 
 Favourable-F  | 
||||
| 
 Material Spending Variance  | 
||||||
| 
 (  | 
 Standard Cost  | 
 -  | 
 Actual Cost  | 
 )  | 
||
| 
 (  | 
 $ 4,200,000.00  | 
 -  | 
 $ 4,250,000.00  | 
 )  | 
||
| 
 -50000  | 
||||||
| 
 Variance  | 
 $ 50,000.00  | 
 Unfavourable-U  | 
||||
| 
 Labor Rate Variance  | 
||||||
| 
 (  | 
 Standard Rate  | 
 -  | 
 Actual Rate  | 
 )  | 
 x  | 
 Actual Labor Hours  | 
| 
 (  | 
 $ 8.00  | 
 -  | 
 $ 7.75  | 
 )  | 
 x  | 
 250000  | 
| 
 62500  | 
||||||
| 
 Variance  | 
 $ 62,500.00  | 
 Favourable-F  | 
||||
| 
 Labour Efficiency Variance  | 
||||||
| 
 (  | 
 Standard Hours  | 
 -  | 
 Actual Hours  | 
 )  | 
 x  | 
 Standard Rate  | 
| 
 (  | 
 252000  | 
 -  | 
 250000  | 
 )  | 
 x  | 
 $ 8.00  | 
| 
 16000  | 
||||||
| 
 Variance  | 
 $ 16,000.00  | 
 Favourable-F  | 
||||
| 
 Labor Spending Variance  | 
||||||
| 
 (  | 
 Standard Cost  | 
 -  | 
 Actual Cost  | 
 )  | 
||
| 
 (  | 
 $ 2,016,000.00  | 
 -  | 
 $ 1,937,500.00  | 
 )  | 
||
| 
 78500  | 
||||||
| 
 Variance  | 
 $ 78,500.00  | 
 Favourable-F  | 
||||