In: Accounting
Cordon Corporation set the following standard unit costs for its single product:
Direct materials (25 lbs @ $4 per lb) $100 per unit
Direct labor (6 hrs @ $8 per hr) 48 per unit
Factory overhead – variable (6 hrs @ $5 per hr) 30 per unit
Factory overhead – fixed (6 hrs @ $7 per hr) 42 per unit
Total Standard cost $220 per unit
The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 60,000 units per quarter. The following flexible budget information is available:
Operating levels
70% 80% 90%
Production in units 42,000 48,000 54,000
Standard direct labor hours 252,000 288,000 324,000
Budgeted overhead
Fixed MOH $2,016,000 $2,016,000 $2,016,000
Variable MOH 1,260,000 1,440,000 1,620,000
During the current quarter, the company operated at 70% of capacity and produced 42,000 units of product: direct labor hours worked were 250,000. Units
Produced were assigned the following standard costs:
Direct materials (1,050,000 lbs @ $4 per lb.) $4,200,000
Direct labor (252,000 hrs @ $8 per hr) 2,016,000
Factory overhead (252,000 hrs @ $12 per hr) 3,024,000
Total standard cost $9,240,000
Actual costs incurred during the current quarter follow:
Direct materials (1,000,000 @ $4.25 per lb) $4,250,000
Direct labor (250,000 hrs @ $7.75 per hr) 1,937,500
Fixed factory overhead costs 1,960,000
Variable factory overhead costs 1,200,000
Total actual costs $9,347,500
Required:
Prepare the level 3 variance analysis on Direct materials, and Direct labor. Include a description of what occurred.
Material Price Variance |
||||||
( |
Standard Rate |
- |
Actual Rate |
) |
x |
Actual Quantity |
( |
$ 4.00 |
- |
$ 4.25 |
) |
x |
1000000 |
-250000 |
||||||
Variance |
$ 250,000.00 |
Unfavourable-U |
Material Quantity Variance |
||||||
( |
Standard Quantity |
- |
Actual Quantity |
) |
x |
Standard Rate |
( |
1050000 |
- |
1000000 |
) |
x |
$ 4.00 |
200000 |
||||||
Variance |
$ 200,000.00 |
Favourable-F |
Material Spending Variance |
||||||
( |
Standard Cost |
- |
Actual Cost |
) |
||
( |
$ 4,200,000.00 |
- |
$ 4,250,000.00 |
) |
||
-50000 |
||||||
Variance |
$ 50,000.00 |
Unfavourable-U |
Labor Rate Variance |
||||||
( |
Standard Rate |
- |
Actual Rate |
) |
x |
Actual Labor Hours |
( |
$ 8.00 |
- |
$ 7.75 |
) |
x |
250000 |
62500 |
||||||
Variance |
$ 62,500.00 |
Favourable-F |
Labour Efficiency Variance |
||||||
( |
Standard Hours |
- |
Actual Hours |
) |
x |
Standard Rate |
( |
252000 |
- |
250000 |
) |
x |
$ 8.00 |
16000 |
||||||
Variance |
$ 16,000.00 |
Favourable-F |
Labor Spending Variance |
||||||
( |
Standard Cost |
- |
Actual Cost |
) |
||
( |
$ 2,016,000.00 |
- |
$ 1,937,500.00 |
) |
||
78500 |
||||||
Variance |
$ 78,500.00 |
Favourable-F |