In: Accounting
Assembly Department uses a process cost accounting systm and a weighted-average cost flow assumption. The department adds minerals at the beginning of the process and incur conversion costs uniformly throughout the process. During July, $190,000 of materials cost and $135,000 in conversion costs were charged to the department. The beginning work in process inventory was $93,000 on July 1, comprised of $80,000 of materials costs and $13,000 of conversion costs.
Other Data for the month of July are as follows:
Beginning work in process Inventory 7/1 25,000 units
(40% complete)
Units completed and transferred out. 90,000 units
Ending work in process inventory 7/31
30,000 units (30% complete)
Instructions
1. How many physical units have to be accounted for in July?
2. What are the equivalent units of production for materials and
for conversion costs for the month of July?
3. What is the total cost assigned to the 90,000 units that were
transferred out of the process in July?
4. What is the remaining total cost of inventory within the
Assembly department as of July 31?
1.
Units charged to production | |
Work in process beginning | 25,000 |
Started into production | 95,000 |
Total units accounted for by the Assembly department | 120,000 |
2.
Whole Unit | Direct Materials | Conversion | |
Transferred to finished goods in Nov | 90,000 | 90000 | 90000 |
Inventory in process, Nov 30 | 30,000 | 30000 | 9000 |
Equivalent units | 120,000 | 120000 | 99000 |
Cost per equivalent unit | Direct Materials | Conversion |
Work in process beginning | 80000 | 13000 |
Costs added during June | 190000 | 135000 |
Total costs for Assembly Dept | 270000 | 148000 |
Total equivalent units | 120000 | 99000 |
Cost per equivalent unit | 2.25 | 1.49 |
3.
Costs accounted for | |||
Transferred out | 337045 | [90,000*(2.25+1.49) |
4.
Work in Process, July 31 | |||
Materials | 67500 | [30000*2.25] | |
Conversion costs | 13455 | 80955 | [9000*1.49] |
Workings:
Costs accounted for | |||
Transferred out | 337045 | [90,000*(2.25+1.49) | |
Work in Process, July 31 | |||
Materials | 67500 | [30000*2.25] | |
Conversion costs | 13455 | 80955 | [9000*1.49] |
Total costs | 418000 |
Any doubt please comment, If it helped you, please give a thumbs up.