In: Accounting
Brenda enterprise had the following information for FY 2018:
Work in process -1/1/18 100,000 units
Units started into production 575,000 units
Work in process -12/31/18 75,000 units
Direct material put into production $575,000
Conversions costs put into production $843,750
The beginning work in process was 100% complete as to direct materials and 75% complete as to conversion costs
The beginning work in process consisted of:
Direct material $943,750
Conversion cost $303,750
Brenda Enterprise uses the weighted-average method.
1. the equivalent units of production for direct materials
2. the cost per equivalent unit for materials
3. the equivalent units of production for conversion
4. the cost per equivalent unit for conversion
5. the cost that should be assigned to Brenda enterprise work in process at the end
Solution-1) Equivalent units of production for direct materials: 675,000
Solution-2) Cost per equivalent unit for materials: $2.25
Solution-3) Equivalent units of production for conversion: 637,500
Solution-4) Cost per equivalent unit for conversion: $1.80
Solution-5) Cost that should be assigned to Brenda enterprise work in process at the end: $236,250
?
Working:
Schedule-Equivalent Units |
||
Particulars |
Material |
Conversion |
Beginning WIP @ 100,000 (75% complete for CC) |
100,000 |
100,000 |
Started and Complete during the month (500,000 units) |
500,000 |
500,000 |
Ending WIP @ 75,000 (50% complete for CC) |
75,000 |
37,500 |
???? Totals |
675,000 |
637,500 |
Schedule - Unit Cost Computation |
|||
Item: |
Total Costs |
Equivalent Units |
Per Unit Cost |
Material Costs |
$1,518,750 |
675,000 u |
$2.25 |
Conversion Costs |
$1,147,500 |
637,500 u |
$1.80 |
???? Totals amount |
$2,666,250 |
$4.05 |
Material Costs: ?BWIP = $943,750; Month =?575,000; Total?=?$1,518,750
Conversion Costs: ?BWIP =?$303,750; Month =?$843,750; Total?=?$1,147,500
Schedule - Cost Allocation |
||
Completed and Transferred Out: |
||
??????? 600,000 units X $4.05 per unit |
$2,430,000 |
|
Ending WIP, |
||
?????? Material Cost (75,000 units X $2.25 per unit ) |
$168,750 |
|
?????? Conversion Costs (75,000 units X 50% complete X $1.80 per unit) |
$67,500 |
|
?? Total Ending WIP |
$236250 |
|
Total Costs to Account for: |
$2,666,250 |