ZAKI LLP is a networking entity.
Required
Using the data provided below
Note: Time is in Weeks and Cost in USD.
Activity | Normal time | Crash time | Normal cost | Crash cost |
1-2 | 10 | 7 | 1,000 | 1,600 |
1-3 | 15 | 10 | 2,000 | 3,000 |
2-4 | 8 | 6 | 1,800 | 2,600 |
2-5 | 20 | 16 | 4,500 | 5,300 |
3-6 | 30 | 20 | 7,200 | 9.600 |
4-5 | 14 | 12 | 5,000 | 6,000 |
5-6 | 12 | 9 | 3,300 | 4,500 |
b)
Activity | Normal Time | Normal Cost | Crash time | Crash cost | Cost slope |
1--2 | 10 | 1,000 | 7 | 1,600 | 200 |
1--3 | 15 | 2,000 | 10 | 3,000 | 200 |
2--4 | 8 | 1,800 | 6 | 2,600 | 400 |
2--5 | 20 | 4,500 | 16 | 5,300 | 200 |
3--6 | 30 | 7,200 | 20 | 9,600 | 240 |
4--5 | 14 | 5,000 | 12 | 6,000 | 500 |
5--6 | 12 | 3,300 | 9 | 4,500 | 400 |
24,800 |
C)
Step 1: The critical activity 1-3 has least cost slope of 200 USD. So we can crash it by one week. Then duration will be 44 weeks at as cost of 24800+200= 25000 USD
Step:2 The critical activity of 1-2 & 1-3 has least cost slope of 200USD. So we can crash each activity by 2 weeks.
Then duration will be 42 Weeks at a cost of 25000+400+400= 25900 USD
Therefore the minimum project completion time with the least cost is 42 weeks @ 25900 USD