Question

In: Finance

Which one of following is not a major method of managing risk? A. Loss identification B....

Which one of following is not a major method of managing risk?

A. Loss identification

B. Loss financing

C. Loss control

D. Internal risk reduction

Solutions

Expert Solution

Answer is - B. Loss financing

Loss financing is method to bring finance for the loss which has already occurred. It is not a major risk management method


Related Solutions

Securitization can help in the following: Select one: a. Managing the credit risk b. Managing the...
Securitization can help in the following: Select one: a. Managing the credit risk b. Managing the interest rate risks c. All of these d. Raising funds
Which of the following measure is NOT used for managing credit risk a. Netting arrangements b....
Which of the following measure is NOT used for managing credit risk a. Netting arrangements b. Margin and collateral requirements c. Capital gain tax d. Periodic Settlements
Which of the following is NOT a method of source reduction? Select one: a. Recycling b....
Which of the following is NOT a method of source reduction? Select one: a. Recycling b. Making packages that weigh less c. Incineration d. Municipal composting
1.Which of the following describes a project managers responsibility? Select one: a. Task Delegation b. Managing...
1.Which of the following describes a project managers responsibility? Select one: a. Task Delegation b. Managing communication between team members c. Getting the project done on time. d. All of the above 2. When people first look at a web page, their eye goes to the: Select one: a. Top right-hand corner b. Bottom left-hand corner c. Bottom right-hand corner d. Top left-hand corner 3. A website’s call to action will work best: Select one: a. At the end of...
b.Describe one nonfinancial method for managing economic-exposure
b.Describe one nonfinancial method for managing economic-exposure
Which of the following best measures an asset's risk? Select one: a. Expected return b. The...
Which of the following best measures an asset's risk? Select one: a. Expected return b. The cash return c. The standard deviation d. The probability distribution You are considering buying some stock in Continental Breakfast. Which of the following is an example of nondiversifiable risk? Select one: a. Risk resulting from a news release that there are issues with Continental's production b. Risk resulting from an explosion in a factory owned by Continental c. Risk resulting from a general decline...
Which of the following is not a major risk associated with outsourcing? Employees in the host...
Which of the following is not a major risk associated with outsourcing? Employees in the host country fear/feel their jobs may be outsourced next, creating job insecurity lack of coordination between home country and host country Political risks in the host country, increasing costs Increased hidden costs associated with having to buy expensive, highly specialized infrastructure and equipment
List 4 methods of managing risk and give an example of each. Method of responding to...
List 4 methods of managing risk and give an example of each. Method of responding to risk Example Reduce risk
Write about the risk management plan which includes identification of risk, analysis, prioritization, mitigation and avoidance,...
Write about the risk management plan which includes identification of risk, analysis, prioritization, mitigation and avoidance, monitoring, reporting. Also prepare the risk register.(According to PMBOK) Risk management plan should be regarding the project of "supplying off-grid power energy to the local farms for the agricultural cultivation."
Which of the following is not a method to prevent loss to follow-up? A.Use complicated questionnaires....
Which of the following is not a method to prevent loss to follow-up? A.Use complicated questionnaires. It is important to collect as much detailed data as possible, regardless of how difficult the questionnaire might be for the participant to understand B. Keep participants motivated. Make them feel that the study is important C. Use participants who are easy to track D. Provide incentives to your participants
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT