In: Finance
Suppose Tapley Inc. uses a WACC of 8% for below-average risk projects, 10% for average-risk projects, and 12% for above-average risk projects. Which of the following independent projects should Tapley accept, assuming that the company uses the NPV method when choosing projects?
A). Project A, which has average risk and an IRR = 9%.
B). Project B, which has below-average risk and an IRR = 8.5%.
C). Project C, which has above-average risk and an IRR = 11%.
D). Without information about the projects' NPVs we cannot determine which one or ones should be accepted.
E). All of these projects should be accepted as they will produce a positive NPV.
Answer = project B should be accepted
Explanation:
Any project whose WACC So, when WACC is more then the IRR
of the project, it cannot be accepted when npv method is used Hence, Only Project b has IRR more than
WACC, hence it could be considered and accepted. Project A and C
will be rejected . .