Question

In: Finance

Below are the estimated cash flows for two projects: S and L. The WACC is 10%....

Below are the estimated cash flows for two projects: S and L. The WACC is 10%.

Time 0 1 2 3
Project L -100 10 60 80
Project S -100 70 50 20

1a. What is the payback period? Find the paybacks for Projects L and S.

1b..What is the rationale for the payback method? According to the payback criterion, which project(s) should be accepted if the firm’s maximum acceptable payback is 2 years, if Projects L and S are independent? If Projects L and S are mutually exclusive?

1c. What is the difference between the regular and discounted payback methods? What is Project L’s discounted payback, assuming a 10% cost of capital?

1d.Define the term net present value (NPV). What is each project’s NPV?

1e. What is the rationale behind the NPV method? According to NPV, which project(s) should be accepted if they are independent? Mutually exclusive?

1f. Define the term internal rate of return (IRR). What is each project’s IRR?

1g. What is the logic behind the IRR method? According to IRR, which project(s) should be accepted if they are independent? Mutually exclusive?

1h. If a project with normal cash flows has an IRR greater than the WACC, the project must also have a positive NPV.

Solutions

Expert Solution

1a.Project L

Payback period= full years until recovery + unrecovered cost at the start of the year/cash flow during the year

= 2 years + ($100 - $70)/ $80

= 2 years + $30/ $80

   = 2 years + 0.3750

= 2.38 years.

Project S

Payback period= full years until recovery + unrecovered cost at the start of the year/cash flow during the year

= 1 year + ($100 - $70)/ $50

= 1 year + $30/ $50

= 1 year + 0.60

= 1.60 years.

1b. In the payback period method,  the time period to recover the initial cost of investment is calculated. The lower the payback period, the better.

If projects L and S are independent, only project S is accepted since it's payback period is less than the maximum allowable payback of 2 years.

If projects L and S are mutually exclusive, only project S is accepted since it's payback period is less than the maximum allowable payback of 2 years.

1c. Both methods, payback and discounted payback time period to recover the initial cost of investment. But discounted payback also accounts for the time value of money.

Project L

Discounted payback period= full years until recovery + unrecovered cost at the start of the year/ discounted cash flow during the year

= 2 years + ($100 - $58.68)/ $60.11

= 2 years + $41.32/ $60.11

= 2 years + 0.69

= 2.69 years.

Project S

Discounted payback period= full years until recovery + unrecovered cost at the start of the year/ discounted cash flow during the year

= 1 year + ($100 - $63.64)/ $41.32

= 1 year + $36.36/ $41.32

= 1 year + 0.88

= 1.88 years.

1d. In The net present value, cash flows are determined and they are discounted back to present values. The project with the highest net present value is selected.

Project L

Net present value can be solved using a financial calculator. The steps to solve on the financial calculator:

  • Press the CF button.
  • CF0= -$100. Indicate the initial cash flow by a negative sign since it is a cash outflow.  
  • Cash flow for each year should be entered.
  • Press Enter and down arrow after inputting each cash flow.
  • After entering the last cash flow cash flow, press the NPV button and enter the cost of capital of 10%.
  • Press enter after that. Press the down arrow and CPT buttons to get the net present value.  

Net present value at 10% cost of capital is $18.78.

Project S

Net present value can be solved using a financial calculator. The steps to solve on the financial calculator:

  • Press the CF button.
  • CF0= -$100. Indicate the initial cash flow by a negative sign since it is a cash outflow.  
  • Cash flow for each year should be entered.
  • Press Enter and down arrow after inputting each cash flow.
  • After entering the last cash flow cash flow, press the NPV button and enter the cost of capital of 10%.
  • Press enter after that. Press the down arrow and CPT buttons to get the net present value.  

Net present value at 10% cost of capital is $19.99

1e.The net present value measures the value added by the project accepted.

According to the net present value, both projects can be accepted if the projects are independent since both generated a positive net present value and project S should be accepted if the projects are mutually exclusive since it has the highest net present value.

1f.Internal rate of return is the rate of return that makes the net present value of all cash flows of a certain investment equal to zero. It is helpful in comparing investments and making capital budgeting decisions.

Project L

Internal rate of return can be calculated using a financial calculator by inputting the below:

  • Press the CF button.
  • CF0= -$100. The initial cash flow is indicated by a negative sign since it is a cash outflow.  
  • Cash flow for each of the fifteen years should be entered.
  • Press Enter and down arrow after inputting each cash flow.
  • After entering the last cash flow cash flow, press the IRR and CPT button to get the IRR of the project.

The IRR of the project is 18.13%.

Project S

Internal rate of return can be calculated using a financial calculator by inputting the below:

  • Press the CF button.
  • CF0= -$100. The initial cash flow is indicated by a negative sign since it is a cash outflow.  
  • Cash flow for each of the fifteen years should be entered.
  • Press Enter and down arrow after inputting each cash flow.
  • After entering the last cash flow cash flow, press the IRR and CPT button to get the IRR of the project.

The IRR of the project is 23.56%.

1g. If the internal rate of return is higher or equal to the cost of capital, the project should be accepted. If the internal rate of return is lesser than the cost of capital, the project should be rejected.

According to IRR, if the projects are independent, both the project should be accepted since the internal arte of return computed is higher than the cost of capital.

If the projects are mutually exclusive, project S is accepted since it has the highest internal rate of return.

1h.The statement which says that If a project with normal cash flows has an IRR greater than the WACC, the project must also have a positive NPV is true.

In case of any query, kindly comment on the solution.


Related Solutions

A firm is considering Projects S and L, whose cash flows are shown below. These projects...
A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? WACC: 6.75% 0 1 2 3 4 CFS -$1,025 $380 $380 $380 $380 CFL -$2,150...
A firm is considering Projects S and L, whose cash flows are shown below. These projects...
A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? WACC: 7.75% 0 1 2 3 4 CF S -$1,025 $380 $380 $380 $380 CF...
A company is considering Projects S and L, whose cash flows are shown below. These projects...
A company is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO believes the IRR is the best selection criterion, while the CFO advocates other methods. If the decision is made by choosing the project with the higher IRR, how much, if any, value will be forgone, i.e., what's the: NPV and IRR of the chosen project(s). What is the Payback period, discounted payback period, and...
A firm is considering Projects S and L, whose cash flows are shown below. These projects...
A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? WACC: 6.75% 0 1 2 3 4 CFS -$1,025 $380 $380 $380 $380 CFL -$2,150...
A firm is considering Projects S and L, whose cash flows are shown below. These projects...
A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? Interest rate: 10.00% Year 0 1 2 3 4 CFS -$1,000 $380 $380 $380 $380...
Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher MIRR rather than the one with the higher NPV, how much value will be forgone? Note that under some conditions choosing projects on the basis of the MIRR will cause $0.00 value to be lost. WACC: 10.75% 0 1 2 3 4 CFS -$1,100...
Kosovski Company is considering Projects S and L, whose cash flows are shown below. These projects...
Kosovski Company is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and are not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under some conditions choosing projects on the basis of the IRR will cause $0.00 value to be lost. WACC: 7.75 CFs Y0: $-1050 Y1 $675 $650 CFl Y0 $-1050 Y1 $360 Y2 360 Y3$360...
Yonan Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
Yonan Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the shorter payback, some value may be forgone. How much value will be lost in this instance? Note that under some conditions choosing projects on the basis of the shorter payback will not cause value to be lost WACC 11.75% 0 1 2 3 4 CFs...
Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher MIRR rather than the one with the higher NPV, how much value will be forgone? Note that under some conditions choosing projects on the basis of the MIRR will cause $0.00 value to be lost. WACC: 10.75% 0 1 2 3 4 CFS -$1,100...
Tesar Chemicals is considering Projects S and L, whose cash flows are shown below. These projects...
Tesar Chemicals is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO believes the IRR is the best selection criterion, while the CFO advocates the NPV. If the decision is made by choosing the project with the higher IRR rather than the one with the higher NPV, how much, if any, value will be forgone, i.e., what's the chosen NPV versus the maximum possible NPV? Note...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT