Tech Enterprises is considering a new project that will require $325,000 for fixed assets, $160,000 for inventory, and $35,000 for accounts receivable. Short-term debt is expected to increase by $100,000. The project has a life of 5 years. The fixed assets will be depreciated straight-line to a zero book value over the life of the project. Ignore bonus depreciation. At the end of the project, the fixed assets can be sold for 25 percent of their original cost and the net working capital will return to its original level. The project is expected to generate annual sales of $554,000 with costs of $430,000. The tax rate is 21 percent and the required rate of return is 15 percent. What is the net present value of this project?

Solutions

Expert Solution

Net present value is calculated as present value of cash inflow less present value of cash outflow
Calculate net present value
Year 0 1 2 3 4 5
Purchase of fixed assets -$325,000
Working capital (160,000+35,000-100000) -$95,000
Sales revenue $554,000 $554,000 $554,000 $554,000 $554,000
Costs -$430,000 -$430,000 -$430,000 -$430,000 -$430,000
Depreciation (325000/5) -$65,000 -$65,000 -$65,000 -$65,000 -$65,000
Net income before taxes $59,000 $59,000 $59,000 $59,000 $59,000
Less: Taxes @ 21% -$12,390 -$12,390 -$12,390 -$12,390 -$12,390
Net income $46,610 $46,610 $46,610 $46,610 $46,610
Add: Depreciation $65,000 $65,000 $65,000 $65,000 $65,000
Operating cash flow $111,610 $111,610 $111,610 $111,610 $111,610
Salvage value after tax (325000*25%)*(1-0.21) $64,188
Working capital stated to original $95,000
Net cash flow -$420,000 $111,610 $111,610 $111,610 $111,610 $270,798
Discount factor @ 15% 1.00000 0.86957 0.75614 0.65752 0.57175 0.49718
Present value -$420,000 $97,052 $84,393 $73,385 $63,813 $134,634
Net present value $33,278.35
Thus, net present value is $33,278.35

Related Solutions

Tech Enterprises is considering a new project that will require $325,000 for fixed assets, $160,000 for...
Tech Enterprises is considering a new project that will require $325,000 for fixed assets, $160,000 for inventory, and $35,000 for accounts receivable. Short-term debt is expected to increase by $100,000. The project has a life of 5 years. The fixed assets will be depreciated straight-line to a zero book value over the life of the project. Ignore bonus depreciation. At the end of the project, the fixed assets can be sold for 25 percent of their original cost and the...
Dysound Inc. is considering a new project. The project will require $325,000 for new fixed assets,...
Dysound Inc. is considering a new project. The project will require $325,000 for new fixed assets, $95,000 for additional inventory and accounts receivable (working capital). The project has a 5-year life. The fixed assets belong to a 30% CCA class. At the end of the project there is no salvage cost. The net working capital returns to its original level at the end of the project. The project is expected to generate annual sales of $554,000 and costs of $430,000....
Dysound Inc. is considering a new project. The project will require $325,000 for new fixed assets,...
Dysound Inc. is considering a new project. The project will require $325,000 for new fixed assets, $95,000 for additional inventory and accounts receivable (working capital). The project has a 5-year life. The fixed assets belong to a 30% CCA class. At the end of the project there is no salvage cost. The net working capital returns to its original level at the end of the project. The project is expected to generate annual sales of $554,000 and costs of $430,000....
TechSquare. LLC. is considering a 5-year new project. The project will require $325,000 for fixed assets...
TechSquare. LLC. is considering a 5-year new project. The project will require $325,000 for fixed assets and $95 of working capital. The fixed assets will be depreciated straight-line to a zero-book value over 5 year. At the end of the project, the fixed assets can be sold for 25% of their original cost. The project is expected to generate annual sales of $554,000 with costs of $430,000. The tax rate is 21% and the required rate of return is 15%....
TechSquare. LLC. is considering a 5-year new project. The project will require $325,000 for fixed assets...
TechSquare. LLC. is considering a 5-year new project. The project will require $325,000 for fixed assets and $95,000 of working capital. The fixed assets will be depreciated straight-line to a zero-book value over 5 year. At the end of the project, the fixed assets can be sold for 25% of their original cost. The project is expected to generate annual sales of $554,000 with costs of $430,000. The tax rate is 21% and the required rate of return is 15%....
TechSquare. LLC. is considering a 5-year new project. The project will require $325,000 for fixed assets...
TechSquare. LLC. is considering a 5-year new project. The project will require $325,000 for fixed assets and $95000 of working capital. The fixed assets will be depreciated straight-line to a zero-book value over 5 year. At the end of the project, the fixed assets can be sold for 25% of their original cost. The project is expected to generate annual sales of $554,000 with costs of $430,000. The tax rate is 21% and the required rate of return is 15%....
Margarite’s Enterprises is considering a new project. The project will require $200,000 for new fixed assets...
Margarite’s Enterprises is considering a new project. The project will require $200,000 for new fixed assets and $15,000 for additional investments in net working capital. The project has a 3-year life. The fixed assets will be depreciated using 3-year MACRS to a zero book value over the life of the project. At the end of the project, the fixed assets can be sold for 5 percent of their original cost. The net working capital returns to its original level at...
Western Tech is considering a new project that will require $118,000 of fixed assets and net...
Western Tech is considering a new project that will require $118,000 of fixed assets and net working capital of $16,000. The fixed assets will be depreciated on a straight-line basis to a zero salvage value over three years. Ignore bonus depreciation. This project is expected to produce an operating cash flow of $45,000 the first year with that amount decreasing by 5 percent annually for two years before the project is shut down. The fixed assets can be sold for...
Firm A’s new project needs $325,000 for new fixed assets (long term assets), $160,000 for additional...
Firm A’s new project needs $325,000 for new fixed assets (long term assets), $160,000 for additional inventory and $35,000 for additional accounts receivable. This is a five year project. Use straight line depreciation approach to calculate the depreciation expenses. By the end of the fifth year, the value of the fixed assets = 0. However, the market value of the assets = 25% of their original cost. At the end of the project, the net working capitals tend to return...
Ivy is considering a new project. The project will require $2,000,000 for new fixed assets. There...
Ivy is considering a new project. The project will require $2,000,000 for new fixed assets. There is a total of 75,000combjned increase in inventories and account receivables which is partly financed by 25,000 increase is accounts payables. The project has a 6 yr life span. The fixed assets will be depreciated using 7 year MACRS to zero book value over the life of the project. At the end of the project, the fixed assets can be sold for 10% of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT