Question

In: Accounting

On January 1, 2021, the company obtained a $3 million loan with a 10% interest rate.....

On January 1, 2021, the company obtained a $3 million loan with a 10% interest rate.. The building was completed on September 30, 2022. Expenditures on the project were as follows:

January 1, 2021 $ 1,000,000
March 1, 2021 600,000
June 30, 2021 800,000
October 1, 2021 600,000
January 31, 2022 270,000
April 30, 2022 585,000
August 31, 2022 900,000

On January 1, 2021, the company obtained a $3 million construction loan with a 10% interest rate. Assume the $3 million loan is not specifically tied to construction of the building. The loan was outstanding all of 2021 and 2022. The company’s other interest-bearing debt included two long-term notes of $4,000,000 and $6,000,000 with interest rates of 6% and 8%, respectively. Both notes were outstanding during all of 2021 and 2022. Interest is paid annually on all debt. The company’s fiscal year-end is December 31.

Required:

  1. Calculate the amount of interest that Mason should capitalize in 2021 and 2022 using the weighted-average method.
  2. What is the total cost of the building?
  3. Calculate the amount of interest expense that will appear in the 2021 and 2022 income statements.

Interest Capatilized 2021 2022

Interest Expense 2021 2022

Total Cost of building

Please let me know what these answers are to double check mine. In interest capatilized 2021 and 2022, interest expense 2021 and 2022 numbers and the total cost of building.

Solutions

Expert Solution

2021 2022
Interest Capitalized $              1,60,925 $         2,25,251
Interest Expense $              8,59,075 $         7,94,749
Total cost of building $            51,41,176
Workings:
Weighted Average rate of all debt:-
$            30,00,000 X 10% = $          3,00,000
$            40,00,000 X 6% = $          2,40,000
$            60,00,000 X 8% = $          4,80,000
$        1,30,00,000 $       10,20,000
Weighted Average rate of all debt = 7.85%
($1020000/ $13000000)
Expenditure for 2021
Jan 1,2021 $            10,00,000 X 12/12 = $       10,00,000
March 1, 2021 $              6,00,000 X 10/12 = $          5,00,000
June 30, 2021 $              8,00,000 X 6/12 = $          4,00,000
October 1, 2021 $              6,00,000 X 3/12 = $          1,50,000
$            30,00,000 $       20,50,000
Interest Capitalized in 2021
$            20,50,000 X 7.85% = $          1,60,925
Expenditure for 2022
Jan 1, 2022 ($3000000 + $160925) $            31,60,925 X 9/9 = $       31,60,925
Jan 31, 2022 $              2,70,000 X 8/9 = $          2,40,000
April 30, 2022 $              5,85,000 X 5/9 = $          3,25,000
August 31. 2022 $              9,00,000 X 1/9 = $          1,00,000
$            49,15,925 $       38,25,925
Interest Capitalized in 2022
$                      38,25,925 X 7.85% X 9/12 = $          2,25,251
Cost of Building
Expenditure for 2021 = $       30,00,000
Interest Capitalized in 2021 = $          1,60,925
Expenditure for 2022 = $       17,55,000
Interest Capitalized in 2022 = $          2,25,251
Total cost of building = $       51,41,176
Interest Expense for 2021:
Total Interest Incurred = $       10,20,000
Less : Interest Capitalized = $          1,60,925
2021 Expense = $          8,59,075
Interest Expense for 2022:
Total Interest Incurred = $       10,20,000
Less : Interest Capitalized = $          2,25,251
2022 Expense = $          7,94,749

Related Solutions

On January 1, 2021, the company obtained a $3 million loan with a 10% interest rate....
On January 1, 2021, the company obtained a $3 million loan with a 10% interest rate. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,300,000 March 1, 2021 720,000 June 30, 2021 340,000 October 1, 2021 640,000 January 31, 2022 450,000 April 30, 2022 765,000 August 31, 2022 1,260,000 On January 1, 2021, the company obtained a $3 million construction loan with a 10% interest rate. Assume the $3...
On January 1, 2021, the company obtained a $3 million loan with a 10% interest rate....
On January 1, 2021, the company obtained a $3 million loan with a 10% interest rate. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,300,000 March 1, 2021 750,000 June 30, 2021 300,000 October 1, 2021 650,000 January 31, 2022 495,000 April 30, 2022 810,000 August 31, 2022 1,350,000 On January 1, 2021, the company obtained a $3 million construction loan with a 10% interest rate. Assume the $3...
On January 1, 2021, the company obtained a $3 million loan with a 10% interest rate.....
On January 1, 2021, the company obtained a $3 million loan with a 10% interest rate.. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,000,000 March 1, 2021 600,000 June 30, 2021 800,000 October 1, 2021 600,000 January 31, 2022 270,000 April 30, 2022 585,000 August 31, 2022 900,000 On January 1, 2021, the company obtained a $3 million construction loan with a 10% interest rate. Assume the $3...
On January 1, 2021, the company obtained a $3 million loan with a 10% interest rate....
On January 1, 2021, the company obtained a $3 million loan with a 10% interest rate. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,300,000 March 1, 2021 750,000 June 30, 2021 300,000 October 1, 2021 650,000 January 31, 2022 495,000 April 30, 2022 810,000 August 31, 2022 1,350,000 On January 1, 2021, the company obtained a $3 million construction loan with a 10% interest rate. Assume the $3...
On January 1, 2021, the company obtained a $3 million loan with a 10% interest rate....
On January 1, 2021, the company obtained a $3 million loan with a 10% interest rate. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,300,000 March 1, 2021 750,000 June 30, 2021 300,000 October 1, 2021 650,000 January 31, 2022 495,000 April 30, 2022 810,000 August 31, 2022 1,350,000 On January 1, 2021, the company obtained a $3 million construction loan with a 10% interest rate. Assume the $3...
On January 1, 2021, the company obtained a $3 million loan with a 11% interest rate....
On January 1, 2021, the company obtained a $3 million loan with a 11% interest rate. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,000,000 March 1, 2021 840,000 June 30, 2021 480,000 October 1, 2021 680,000 January 31, 2022 630,000 April 30, 2022 945,000 August 31, 2022 1,620,000 On January 1, 2021, the company obtained a $3 million construction loan with a 11% interest rate. Assume the $3...
On January 1, 2021, the company obtained a $3 million loan with a 12% interest rate....
On January 1, 2021, the company obtained a $3 million loan with a 12% interest rate. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,330,000 March 1, 2021 780,000 June 30, 2021 230,000 October 1, 2021 660,000 January 31, 2022 540,000 April 30, 2022 855,000 August 31, 2022 1,440,000 On January 1, 2021, the company obtained a $3 million construction loan with a 12% interest rate. Assume the $3...
On January 1, 2021, the company obtained a $3 million loan with a 12% interest rate....
On January 1, 2021, the company obtained a $3 million loan with a 12% interest rate. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,240,000 March 1, 2021 660,000 June 30, 2021 450,000 October 1, 2021 650,000 January 31, 2022 900,000 April 30, 2022 1,215,000 August 31, 2022 2,160,000 On January 1, 2021, the company obtained a $3 million construction loan with a 12% interest rate. Assume the $3...
On January 1, 2021, the company obtained a $3 million loan with a 14% interest rate....
On January 1, 2021, the company obtained a $3 million loan with a 14% interest rate. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,050,000 March 1, 2021 870,000 June 30, 2021 390,000 October 1, 2021 690,000 January 31, 2022 675,000 April 30, 2022 990,000 August 31, 2022 1,710,000 On January 1, 2021, the company obtained a $3 million construction loan with a 14% interest rate. Assume the $3...
On January 1, 2021, the company obtained a $3 million loan with a 12% interest rate....
On January 1, 2021, the company obtained a $3 million loan with a 12% interest rate. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,050,000 March 1, 2021 630,000 June 30, 2021 710,000 October 1, 2021 610,000 January 31, 2022 315,000 April 30, 2022 630,000 August 31, 2022 990,000 On January 1, 2021, the company obtained a $3 million construction loan with a 12% interest rate. Assume the $3...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT