Question

In: Accounting

Project 1 Prepare job costing information for the following: Joseph runs an electrical contracting business and...

Project 1 Prepare job costing information for the following: Joseph runs an electrical contracting business and employs six electricians. He is only involved in supervision but on occasion will assist if needed. He charges direct labour hours at $45.00 per hour. Three of Joseph’s electricians are working on a job that involves wiring and fitting fixtures in a new house for Mr and Mrs Fleet. All materials and fixtures used have come from inventory. Each electrician spends half an hour at the beginning of each day on administration tasks and travels for half an hour to get to the job. They also spend half an hour at the end of the day undertaking administrative tasks. If they finish a job late afternoon and there is not enough time to start another they return to base and fill the time with other administrative tasks. Geoff Smith is responsible for the initial wiring. He calculates that he will need two rolls of electrical cabling and that it will take him 12 hours to complete the job. He works on the job on 15/10/11 and 18/10/11. He completes a materials requisition form and the cost per roll of electrical cable is $85.00. Peter Jones is responsible for fitting all fixtures. He has to fit 23 double power points and 15 down lights. Takes seven hours, so he works for longer to get it done in one day (there are no overtime penalties to worry about). He works on the site on 18/10/11. His materials requisition form shows that the power points are $7.50 per unit and the down lights are $25 each. Brian Brown is the senior electrician and he wired the switchboard, the circuit breakers and checked the work undertaken by the others. He expected this to take about four hours but he was there for seven hours because of problems encountered. He began his work on 22/10/11 and completed the remaining four hours on 25/10/11. The switchboard cost was $190.00 and the circuit breakers were $19.00 each. Twelve were needed. Brian took the afternoon of the 22nd and the morning of the 25th off for recreation leave. He went straight from the job to take his leave and went to the job from his leave without going to the workshop. Recreation leave is costed as administration. Each electrician normally starts at 8.30 am and has lunch from 12.30 until 1.00 pm. At the beginning of the financial year Joseph examined all of his overhead costs; vehicle leases, rent on premises, inventory, replacement of specialised equipment, depreciation, indirect labour, indirect materials, salary on-costs and insurance. These include his fixed and his variable costs. He calculated overall costs to be $662,500. 1 If each of his six electricians worked 46 weeks at 40 hours per week, what are his overhead costs? Complete the jobsheets, the Job cost form for each electrician and the job cost form report.

Solutions

Expert Solution

Job order costing track and assign two types of costs in the cost sheet. Direct costs in the form of labor, materials etc. allocable directly to that particular job and the indirect ones that are not directly traceable to that job but incurs on an event are allocated based on an absorption rate.

First of all, we shall segregate the direct costs.

If they work for 40 hours a week it comes to 8 hours a day which usually starts from 8:30 a.m. and can continue till 6:30 p.m. in the evening. Of these time, first one hour is spent on administrative tasks and commute to the workplace. Work finishes at 6 ‘O clock in the evening and 6:00 to 6:30 p.m. is spent again on administrative setup. Workable hours lies between 9:30 a.m. to 6:00 p.m. with half an hour lunch-break in between (12:30 p.m. to 1:00 p.m.)

Geoff Smith:

Materials: 2 rolls x $85.00 = $170

Labor: 12 hours booked

Peter Jones:

Materials: Power points→ 23 nos. x $7.50 = $172.50

                 Down lights→ 15 nos. x $25.00 = $375.00

Labor: 7 hours booked

Brian Brown:

Materials: Switchboard→ 1 pc x $190.00 = $190.00

                 Circuit breakers→ 12 pcs x $19.00 = $228.00

Labor: 7 hours booked

Total overhead: $662500

Total labor hours: 46 weeks x 40 hours = 1840 hours.

Overhead cost per hour = $662500 / 1840 = $360.00 (approx..)


Related Solutions

Please prepare journal entries for the following cost flows. (1). Sharon Company uses job-order costing system....
Please prepare journal entries for the following cost flows. (1). Sharon Company uses job-order costing system. In July, direct labor cost incurred $90,000 and indirect labor cost incurred $80,000. (2). Sharon Company Job costing $52,000 according to their job cost sheets were completed during July and transferred to Finished Goods. (3). Sharon Company sold the $38,000 in Finished Goods Inventory to customers for $52,000 on account. (4). Process Cost Flows: The Flow of Applied Manufacturing Overhead Costs. Applied manufacturing overhead...
What is the role of information technology in job costing?
What is the role of information technology in job costing?
Basic Job Costing Project Reed Incorporated uses a job-order costing system and a predetermined overhead rate...
Basic Job Costing Project Reed Incorporated uses a job-order costing system and a predetermined overhead rate based on machine hours. At the beginning of the year, the company estimated manufacturing overhead for the year would be $240,000 and machine hours would be 8,000. The following information pertains to December of the current year: Job 10 Job 11 Job 12 Total Work-in-process, Dec. 1 $16,000 $26,000 $38,000 $80,000 The following transactions took place during the month of December: 1. Purchased raw...
Cost Accounting Project Part I Template Project Part I 1 An overview of the job-costing system...
Cost Accounting Project Part I Template Project Part I 1 An overview of the job-costing system is: 2 Budgeted manufacturing overhead divided by allocation base: a. Machining Department: b. Finishing Department: Show work 3 Machining Department overhead Finishing Department overhead Total manufacturing overhead allocated $0 4 Total costs of Job 431: Direct costs: Show work Direct materials Machining Department Finishing Department Direct manufacturing labor Machining Department Finishing Department 0 Indirect costs: Machining Department overhead Finishing Department overhead 0 Total costs...
This week you will prepare for your class project by using the information in Chapters 4 & 5 on job evaluation and analysis.
Under Project Prep in Weeks 1,2, & 3, you will find information that will help you complete your class Project dueWednesday of Week 4.  This week you will prepare for your class project by using the information in Chapters 4 & 5 on job evaluation and analysis. You will be developing a job description for your position in your chosen organization covering the following points:job titlejob summaryrelationships (report to whom, works with whom & external relationships)qualificationsessential responsibilities
   Q 1 Job Costing        You have the information related to Nasser Compagny:                       &nb
   Q 1 Job Costing        You have the information related to Nasser Compagny:                                                     Direct              Direct                Direct                                                   Materials       Labor Cost      Labor Hours Job 200               $200                $800                    40 Job 201                 250                  200                    10 Job 202                 500                  600                    32 Nasser Compagny uses job costing and applies overhead using a normal costing system using direct labor hours as the allocation base. The estimated overhead cost is $400,000, estimated direct labor cost is $500,000 and estimated direct labor hours are 25,000. The...
1. Prepare a job cost sheet for each job worked on during the month. 2. Prepare...
1. Prepare a job cost sheet for each job worked on during the month. 2. Prepare journal entries to record the events and transactions a through i. 3. Post the journal entries for the transactions to the following T-accounts, each of which started the month with a zero balance. 4. Prepare a report showing the total cost of each job in process and prove that the sum of their costs equals the Work in Process Inventory account balance. Prepare similar...
Joseph desired to use an internet domain addressfor his project management services business, and the domain...
Joseph desired to use an internet domain addressfor his project management services business, and the domain name included direct identification of the Project Management Institute (PMI), joetrain.pmi.org. Since he wanted to use the PMI.org domain, Joseph requested the ability to do so from PMI. PMI declined his request since it would lead people to believe that PMI endorsed or otherwise recommended Joseph’s training, and the decision was upsetting to Joseph. Joseph contacted PMI and stated that he felt PMI’s decision...
Joseph desired to use an internet domain addressfor his project management services business, and the domain...
Joseph desired to use an internet domain addressfor his project management services business, and the domain name included direct identification of the Project Management Institute (PMI), joetrain.pmi.org. Since he wanted to use the PMI.org domain, Joseph requested the ability to do so from PMI. PMI declined his request since it would lead people to believe that PMI endorsed or otherwise recommended Joseph’s training, and the decision was upsetting to Joseph. Joseph contacted PMI and stated that he felt PMI’s decision...
1) Explain the benefits to be gained from using the following costing systems: Job costing Process...
1) Explain the benefits to be gained from using the following costing systems: Job costing Process Costing Activity based Costing b) Discuss the ethical issues in the use of costing systems above (Hint: what elements of these systems require judgement or choice by management and therefore leave open the possibility of manipulation)
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT