In: Accounting
Applegate Enterprises produces premier raspberry jam. Output is measured in pints. Applegate uses the weighted average method. During January, Applegate had the following production data:
Units in process, January 1, 60% complete | 116,000 pints |
Units completed and transferred out | 760,000 pints |
Units in process, January 31, 40% complete | 225,000 pints |
Costs: | |
Work in process, January 1 | $116,000 |
Costs added during January | 734,000 |
Required:
1. Using the weighted average method, calculate
the equivalent units for January.
equivalents units
2. Calculate the unit cost for January. Round
your answer to the nearest cent.
$per unit
3. Assign costs to units transferred out and EWIP.
Cost of goods transferred out | $ | ||||||||||||||||
Ending work in process (EWIP) | $
Applegate Enterprises produces premier raspberry jam. Output is measured in pints. Applegate uses the weighted average method. During January, Applegate had the following production data:
Required: 1. Using the weighted average method, calculate
the equivalent units for January. 2. Calculate the unit cost for January. Round
your answer to the nearest cent. 3. Assign costs to units transferred out and EWIP.
|
Solution
Requirement 1
Equivalent Units of Production | 850,000 |
Requirement 2
Cost per equivalent Unit | $ 1.00 |
Requirement 3
Cost of goods transferred out | $ 760,000 |
Ending work in process (EWIP) | $ 90,000 |
Working
Statement of Equivalent Units(Weighted average) | |||||||
Units | Complete % | Equivalent units | |||||
Transferred out | 760,000 | 100% | 760,000 | ||||
Ending WIP | 225,000 | 40% | 90,000 | ||||
Total | 985,000 | Total | 850,000 |
.
Beginning WIP Inventory Cost (A) | $ 116,000 | |
Cost incurred during period (B) | $ 734,000 | |
Total Cost to be accounted for (C=A+B) | $ 850,000 | |
Total Equivalent Units(D) | 850,000 | |
Cost per Equivalent Units (E=C/D) | $ 1.00 |
.
Statement of cost (Weighted average) | |||||
Cost | Equivalent Cost/unit | Ending WIP | Transferred | ||
Units | Cost Allocated | Units | Cost Allocated | ||
All costs | $ 1.00 | 90,000 | $ 90,000.00 | 760,000 | $ 760,000.00 |