In: Accounting
The following data relate to a manufacturing department for a period:
Budgeted data for the coming year are as follows:
Direct labour hours 60,000 hours
Direct labour cost $110,000
Direct material cost $125,000
Production overhead $70,400
Actual data for the period are as follows:
Direct labour hours 55,500 hours
Direct labour cost $125,000
Direct material cost $150,000
Production overhead $67,800
Required:
(7A) Calculate the production overhead absorption rate predetermined for the period based on :
(7B) Two pieces of furniture are to be manufactured for customers. Direct costs are as follows:
Job 400 Job 401
Direct material $15,400 $10,800
Direct labour 210 hours Dept. A @$16/ hour: 160 hours Dept. A @20/hour
120 hours Dept. B @$12/hour; 100 hours Dept. B @$18/hour
100 hours Dept. C @$14/hour; 140 hours Dept. C@$10/hour
Selling and administrative overheads for each job are 10% of factory cost.
Required:
(7C) Calculate the total costs of each job using all the two bases in question (7A) above.
(7D) If the firm quotes prices to customers that reflect a required profit of 25 per cent on selling price, calculate the quoted selling price for each job.
Answer :
(7A)(1) Computation of production overhead absorption rate based on Percentage of direct material cost
= production overhead*100/ Direct material cost
= $ 70400*100 / $ 125000
= 56.32 % of Direct material cost
(7A)(2) Computation of production overhead absorption rate based on Direct labor hour
= Production overhead / Budgeted direct labor hour
= $ 70400 / 60000 hour
= $ 1.17 ( approx up to 2 decimal place )
(7C) Computation of total costs of each job using all the two bases in question (7A) above.
Total cost as per Direct material cost | Total cost as per Direct labor hour | |||
Job 400 | Job 401 | Job 400 | Job 401 | |
Direct Material | $ 15400 | $ 10800 | $ 15400 | $ 10800 |
Direct labor | ||||
Dep -A |
$ 3360 ( 210*16 ) |
$ 3200 ( 160*20) |
$ 3360 | $ 3200 |
Dep - B |
$ 1440 ( 120*12) |
$ 1800 ( 100*18) |
$ 1440 | $ 1800 |
Dep - C |
$ 1400 ( 100*14) |
$ 1400 ( 140*10) |
$ 1400 | $ 1400 |
Production overhead |
$ 8673.28 ( 15400*56.32%) |
$ 6082.56 ( 10800*56.32%) |
$ 503.10 ( 430*1.17) |
$ 468 (400*1.17) |
Factory cost | $ 30273.28 | $ 23282.56 | $ 22103.10 | $ 17668 |
Selling and administrative ex | $ 3027.33 | $ 2328.26 | $ 2210.31 | $1766.80 |
Total cost | $ 33300.61 | $ 25610.82 | $ 24313.41 | $ 19434.80 |
(7D) Computation of Selling price of each Job
Total cost as per Direct material cost | Total cost as per Direct labor hour | |||
Job 400 | Job 401 | Job 400 | Job 401 |
Total cost | $ 33300.61 | $ 25610.82 | $ 24313.41 | $ 19434.80 |
Selling price (cost + cost *33.33%) | $ 44399.70 | $ 34146.91 | $ 32417.07 | $ 25912.42 |
Working note -1
profit = 25 % on selling price
Let selling price = 100
profit = 100*25 % = 25
Cost = sales - profit
= 100 -25 = 75
Profit % on cost = 25*100/75 = 33.33 %