In: Accounting
Canvas Corp. is a large construction company that reports under IFRS. They have recently signed a contract with Ontario Tech University to build an addition to the library. Canvas began work on the contract at the beginning of 2020. Contract information and estimates are as follows: Contract price ……………………………………………….. $ 2,000,000 Estimated costs Labour.................................................................................. $ 435,000 Materials and subcontracts ................................................. 765,000 Indirect costs........................................................................ 300,000 1,500,000 Estimated gross profit................................................................... $ 500,000 At the end of 2020, the following was the actual status of the contract: Progress Billings to date ......................... $ 1,115,000 Costs incurred to date: Labour.................................................................................. $ 207,000 Materials and subcontracts ................................................. 468,000 Indirect costs........................................................................ 75,000 Latest forecast of total costs of project (no change).................... $ 1,500,000 At the end of 2021, progress billings to date totalled $1,900,000 and costs incurred to date totalled $1,395,000 with a forecast of $155,000 remaining costs to complete. Cash collected was $980,000 during 2020 and $1,000,000 during 2021. Job is expected to be completed in 2022 Instructions a) Calculate the gross profit that would be reported on this contract for 2020 and 2021. b) Prepare all journal entries for 2020. c) Indicate the account(s) and the amount(s) that would be shown on Canvas’ statement of d) Assume all the same facts, except that the forecast of remaining costs in 2021 is not $155,000, but $555,000. How much income (loss) would Canvas then report for the year 2021? e) Assume you are a shareholder of Canvas Corp. Do you think that recognizing revenue over time rather than at a point in time makes the financial statements more useful? Explain your answer.
Contract Price | 2000000 | |||||
Less: Estimated Cost | ||||||
Labour | 435000 | |||||
Material & subcontracts | 765000 | |||||
Indirect Cost | 300000 | -1500000 | ||||
Total Gross Profit | 500000 | |||||
End of 2020 | ||||||
Progress Billing to Date | 1115000 | |||||
Cost Incurred to date | ||||||
Labour | 207000 | |||||
Material & subcontracts | 468000 | |||||
Indirect Cost | 75000 | -750000 | ||||
No change in forcast | ||||||
Cost incurred to date | 750000 | |||||
Cost still to be incurred | 750000 | |||||
1500000 | ||||||
Degree of completion | 750000/1500000*100 | 50% | ||||
Cost method | ||||||
Contract Revenue | 2000000*50% | 1000000 | ||||
Gross Profit in 2020 | 1000000-750000 | 250000 | ||||
End of 2021 | ||||||
Progress Billing to Date | 1900000 | |||||
Cost Incurred to date | 1395000 | |||||
Cost still to be incurred | 155000 | |||||
Total cost | 1550000 | |||||
Degree of completion | 1395000/1550000*100 | 90% | ||||
Cost method | ||||||
Contract Revenue | 2000000*90% | 1800000 | ||||
Less Revenue recognised in 2020 | -1000000 | |||||
Contract Revenue in 2021 | 800000 | |||||
Contract Cost | 1395000 | |||||
Less Cost recognised in 2020 | -750000 | |||||
Contract Cost in 2021 | 645000 | |||||
Gross Profit in 2021 | 155000 |
Journal Entries in 2020 | ||||||
01-Jan-20 | On date of Agreement | No Entry | ||||
31-Dec-20 | Labour A/c Dr | 207000 | ||||
Material & subcontracts A/c Dr | 468000 | |||||
Indirect Cost A/c Dr | 75000 | |||||
To Bank | 750000 | |||||
Being Cost Incurred | ||||||
31-Dec-20 | Debtor A/c Dr | 1115000 | ||||
To Contract Revenue | 1115000 | |||||
Being Progress billing done | ||||||
31-Dec-20 | Bank A/c Dr | 980000 | ||||
To Debtor | 980000 | |||||
Being Debtor realised | ||||||
31-Dec-20 | Contract A/c Dr | 1000000 | ||||
To Contract Revenue | 1000000 | |||||
Being revenue recognised | ||||||
31-Dec-20 | Contract Cost A/c Dr | 750000 | ||||
To Contract | 750000 | |||||
Being contract cost recognised |
Contract A/c | |||
To Bank | 750000 | By Debtor | 1115000 |
To Bal C/d | 365000 | ||
1115000 | 1115000 | ||
To Contract Revenue | 1000000 | By Bal B/d | 365000 |
To Bal c /d | 115000 | By Contract Cost | 750000 |
1115000 | 1115000 |
FORCAST OF REMAINING COST 555000 instead of 155000 | |||||
Contract Price | 2000000 | ||||
Contract Cost | |||||
Cost Incurred to date | 1395000 | ||||
Changes in cost due to forcast | 555000 | -1950000 | |||
Contract Profit | 50000 | ||||
Contract profit recognised in 2020 before forcast | 500000 | ||||
Contract profit to be reversed in 2021 | 500000-50000*50% | 475000 | |||
Contract profit to be recognised in 2021 | 50000*90%-25000 | 20000 | |||
Net Contract Loss in 2021 | (-475000)+20000 | -455000 | |||
Contract Profit in 2022 | 50000*10% | 5000 |
Since The contract period is 3 Year |
So Contract revenue and contract cost to be recognised over the period of time instead of at a point of time |
It reflects the true and fair view of Financial statement as per applicable IFRS |
Shareholder will get better financial results and make its decision accordingly |