In: Accounting
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates:
| Machine-hours required to support estimated production | 156,000 | |
| Fixed manufacturing overhead cost | $ | 651,000 | 
| Variable manufacturing overhead cost per machine-hour | $ | 4.60 | 
Required:
1. Compute the plantwide predetermined overhead rate.
2. During the year, Job 400 was started and completed. The following information was available with respect to this job:
| Direct materials | $ | 370 | 
| Direct labor cost | $ | 290 | 
| Machine-hours used | 31 | |
Compute the total manufacturing cost assigned to Job 400.
3. If Job 400 includes 60 units, what is the unit product cost for this job?
4. If Moody uses a markup percentage of 110% of its total manufacturing cost, then what selling price per unit would it have established for Job 400?
-Predetermined overhead rateper MH?
If Job 400 includes 60 units, what is the unit product cost for this job?
total manufacturing costs?
If Moody uses a markup percentage of 110% of its total manufacturing cost, then what selling price per unit would it have established for Job 400?
What is selling price per unit?
| 
 A  | 
 Fixed manufacturing overhead cost  | 
 $ 651,000  | 
|
| 
 B  | 
 Machine hours required  | 
 156,000  | 
 machine hours  | 
| 
 C = A/B  | 
 Fixed overhead rate  | 
 $ 4.17  | 
 per machine hour  | 
| 
 D  | 
 Variable overhead rate  | 
 $ 4.60  | 
 per machine hour  | 
| 
 E = C+D  | 
 Plantwide Predetermined Overhead rate  | 
 $ 8.77  | 
 per machine hour  | 
| 
 A  | 
 Machine hours used  | 
 31  | 
|
| 
 B  | 
 Plantwide Predetermined Overhead rate  | 
 $ 8.77  | 
|
| 
 C = A x B  | 
 Total manufacturing cost assigned to Job 400  | 
 $ 272  | 
 Answer  | 
| 
 A  | 
 Direct materials  | 
 $ 370  | 
|
| 
 B  | 
 Direct labor cost  | 
 $ 290  | 
|
| 
 C  | 
 Total manufacturing cost assigned to Job 400  | 
 $ 272  | 
|
| 
 D = A+B+C  | 
 Total cost for the Job  | 
 $ 932  | 
|
| 
 E  | 
 Total units for Job 400  | 
 60  | 
|
| 
 F = D/E  | 
 Units product cost for Job 400  | 
 $ 15.53  | 
 Answer  | 
| 
 A  | 
 Units product cost for Job 400  | 
 $ 15.53  | 
|
| 
 B = A x 110%  | 
 Mark up at 110%  | 
 $ 17.09  | 
|
| 
 C = A+B  | 
 Selling price per unit  | 
 $ 32.62  | 
 Answer  |