In: Accounting
URGENT!!
5.From the following, prepare a cost sheet and the price to be
quoted.
1.1.2018 31.12.2018
Raw materials 20,000 32,000
Work-in-progress 26,500 14,000
Finished Goods 16,000 18,000
Purchases of raw materials 90,000 Carriage inwards
2,000 Direct wages 40,000
Direct expenses 15,000 Works overheads 22,500
Administration overheads 10,000
Selling and distribution overheads 14,000 Sales
2,20,000.
The Company wants to Quote the price for the order
received from the customer, where the
material required is 4000 and labour 3000. Expected
profit 25% margin on sales.
Statement of Cost sheet on 31.12.2018
Particulars | Amount |
Opening stock of Raw material | 20000 |
Add:Purchase of Raw materials(inculding carrige inward) | 92000 |
Less:Closing stock of raw materials | -32000 |
Raw material consumed | 80000 |
Add:Direct wages | 40000 |
Add:Direct Expenses | 15000 |
Prime costs | 135000 |
Add: Works overheads | 22500 |
Gross factory costs | 157500 |
Add:opening work in progress | 26500 |
Less:ending work in progress | 14000 |
Net factory costs | 170000 |
Add:Administration overheads | 10000 |
Cost of Production | 180000 |
Add:Opening stock of finish goods | 16000 |
Less:Ending stock of finish goods | 18000 |
Cost of goods sold | 178000 |
Add:selling & distribution overheads | 14000 |
Cost of Sales | 192000 |
Profits (balancing figure) | 28000 |
Sales | 220000 |
Statement showing the price to be charged for order received from customer
Particulars | Amounts |
Material Required | 4000 |
Labour Required | 3000 |
Total costs | 7000 |
Add:Profits 25%on sales or 1/4 on sales,1/3 on costs (7000/3) | 2333 |
Selling price or quoted price for order | 9333 |