Question

In: Accounting

Question 1: Company has two departments. Its first department (the Melting Department) shows the following data...

Question 1:

Company has two departments. Its first department (the Melting Department) shows the following data for the month of April:

Work in process, beginning:

Units in process

400

Stage of completion with respect to materials

60%

Stage of completion with respect to conversion

85%

Costs in the beginning inventory:

   Materials cost

$170

   Labour cost

$160

   Overhead cost

$300

Units started into production during the month

1,100

Units completed and transferred out

1,400

Costs added to production during the month:

   Materials cost

$1,300

   Labour cost

$800

   Overhead cost

$1,700

Work in process, ending:

    Units in process

???

    Stage of completion with respect to materials

70%

    Stage of completion with respect to conversion

80%

Required:

Using the weighted average method, prepare a production cost report for the company.

Solutions

Expert Solution

Answer:

RITCHIE COMPANY
Melting Department
Production Cost Report
For the Month Ended April 30
Equivalent Units
UNITS Physical Units Materials Labor Overhead
Units to be accounted for:
Work in process, beginning 400
Started into production 1100
Total units 1500
Units accounted for:
Completed and transferred out 1400 1400 1400 1400
Work in process, ending 100 70 80 80
Total units 1500 1470 1480 1480
COSTS
Unit costs: Materials Labor Overhead Total
Total costs in April $ 1470 960 2000 4430
Equivalent units 1470 1480 1480
Unit costs $ 1.00 0.65 1.35 3.00
Costs to be accounted for:
Work in process, beginning $ 170 160 300 630
Costs incurred during April 1300 800 1700 3800
Total costs to be accounted for $ 1470 960 2000 4430
Cost Reconciliation Schedule
Costs accounted for:
Cost of units completed and transferred out
Materials (1400 x $1.00) 1400 1400
Labor (1400 x $0.65) 910 910
Overhead (1400 x $1.35) 1890 1890
Total cost of units completed and transferred 4200
Cost of work in process, ending $
Materials (70 x $1.00) 70 70
Labor (80 x $0.65) 52 52
Overhead (80 x $1.35) 108 108
Total cost of ending work in process $ 230
Total costs accounted for $ 4430

Related Solutions

MVP Company has two departments. Its first department (the Melting Department) shows the following data for...
MVP Company has two departments. Its first department (the Melting Department) shows the following data for the month of August: Work in process, beginning: Units in process               400 Stage of completion with respect to materials 60%Stage of completion with respect to conversion 85% Costs in the beginning inventory:    Materials cost $170   Labour cost $160   Overhead cost $300 Units started into production during the month 1,100Units completed and transferred out 1,400Costs added to production during the month:     Materials cost $1,300   Labour...
Question 2: Traffic Control Systems makes bright rubber traffic cones. The company has two departments, Melting...
Question 2: Traffic Control Systems makes bright rubber traffic cones. The company has two departments, Melting and Forming. Raw materials are introduced at various stages throughout the melting process. The following is the department’s work in process T-Account for August:                    Work in Process – Melting Department Aug 1 balance: (200 kilograms; 80% complete as to materials, 70% complete as to conversion) 352 Completed and transferred to the packaging department (_?_ kilograms) ___?___ Costs added: Materials (2,050 kilograms) 890 Labour...
1. Brownley Company has two service departments and two operating (production) departments. The Payroll Department services...
1. Brownley Company has two service departments and two operating (production) departments. The Payroll Department services all three of the other departments in proportion to the number of employees in each. The Maintenance Department costs are allocated to the two operating departments in proportion to the floor space used by each. Listed below are the operating data for the current period: Service Depts. Production Depts. Payroll Maintenance Cutting Assembly Direct costs $ 32,400 $ 37,500 $ 88,500 $ 117,400 No....
Reciprocal Method Eilers Company has two producing departments and two support departments. The following budgeted data...
Reciprocal Method Eilers Company has two producing departments and two support departments. The following budgeted data pertain to these four departments: Support Departments Producing Departments General Factory Receiving Assembly Finishing Direct overhead $400,000 $150,000 $45,000 $71,000 Square footage — 2,700 5,400 5,400 Number of receiving orders 300 — 1,680 1,020 Direct labor hours — — 25,000 40,000 Required: 1. Allocate the overhead costs of the support departments to the producing departments using the reciprocal method. (Round allocation ratios to two...
Reciprocal Method Eilers Company has two producing departments and two support departments. The following budgeted data...
Reciprocal Method Eilers Company has two producing departments and two support departments. The following budgeted data pertain to these four departments: Support Departments Producing Departments General Factory Receiving Assembly Finishing Direct overhead $400,000 $150,000 $42,000 $71,000 Square footage — 2,700 5,400 5,400 Number of receiving orders 300 — 1,680 1,020 Direct labor hours — — 25,000 40,000 Required: 1. Allocate the overhead costs of the support departments to the producing departments using the reciprocal method. (Round allocation ratios to two...
Sequential Method Eilers Company has two producing departments and two support departments. The following budgeted data...
Sequential Method Eilers Company has two producing departments and two support departments. The following budgeted data pertain to these four departments: Support Departments Producing Departments General Factory Receiving Assembly Finishing Direct overhead $400,000 $150,000 $45,000 $75,000 Square footage — 2,700 5,400 5,400 Number of receiving orders 300 — 1,680 1,020 Direct labor hours — — 25,000 40,000 The support departments are ranked in order of highest cost to lowest cost. Required: 1. Allocate the costs of the support departments using...
Sequential Method Eilers Company has two producing departments and two support departments. The following budgeted data...
Sequential Method Eilers Company has two producing departments and two support departments. The following budgeted data pertain to these four departments: Support Departments Producing Departments General Factory Receiving Assembly Finishing Direct overhead $500,000 $170,000 $45,000 $75,000 Square footage — 2,700 5,400 5,400 Number of receiving orders 300 — 1,680 1,020 Direct labor hours — — 25,000 40,000 The support departments are ranked in order of highest cost to lowest cost. Required: 1. Allocate the costs of the support departments using...
Reciprocal Method Eilers Company has two producing departments and two support departments. The following budgeted data...
Reciprocal Method Eilers Company has two producing departments and two support departments. The following budgeted data pertain to these four departments: Support Departments Producing Departments General Factory Receiving Assembly Finishing Direct overhead $500,000 $150,000 $45,000 $75,000 Square footage — 2,700 5,400 5,400 Number of receiving orders 300 — 1,680 1,020 Direct labor hours — — 25,000 40,000 Required: 1. Allocate the overhead costs of the support departments to the producing departments using the reciprocal method. (Round allocation ratios to two...
Direct Method Eilers Company has two producing departments and two support departments. The following budgeted data...
Direct Method Eilers Company has two producing departments and two support departments. The following budgeted data pertain to these four departments: Support Departments Producing Departments General Factory Receiving Assembly Finishing Direct overhead $470,000 $150,000 $48,000 $76,000 Square footage — 2,200 4,400 4,400 Number of receiving orders 360 — 2,000 1,150 Direct labor hours — — 27,000 49,000 The company has decided to simplify its method of allocating support service costs by switching to the direct method. Required: 1. Allocate the...
Direct Method Eilers Company has two producing departments and two support departments. The following budgeted data...
Direct Method Eilers Company has two producing departments and two support departments. The following budgeted data pertain to these four departments: Support Departments Producing Departments General Factory Receiving Assembly Finishing Direct overhead $420,000 $150,000 $44,000 $76,000 Square footage — 2,200 4,400 4,400 Number of receiving orders 320 — 1,600 1,250 Direct labor hours — — 28,000 48,000 The company has decided to simplify its method of allocating support service costs by switching to the direct method. Required: 1. Allocate the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT