In: Accounting
Poma Manufacturing Corporation has a traditional costing system in which it applies manufacturing overhead to its products using a predetermined overhead rate based on direct labor-hours (DLHs). The company has two products, R78S and N32Y, about which it has provided the following data:
R78S | N32Y | |
---|---|---|
Direct materials per unit | $ 27.20 | $ 54.70 |
Direct labor per unit | $ 8.80 | $ 22.00 |
Direct labor-hours per unit | 0.4 | 1.0 |
Annual production (units) | 35,000 | 10,000 |
The company's estimated total manufacturing overhead for the year is $1,427,040 and the company's estimated total direct labor-hours for the year is 24,000.
The company is considering using a variation of activity-based costing to determine its unit product costs for external reports. Data for this proposed activity-based costing system appear below:
Activities and Activity Measures | Estimated Overhead Cost |
---|---|
Assembling products (direct labor-hours) | $ 672,000 |
Preparing batches (batches) | 255,840 |
Product support (product variations) | 499,200 |
Total | $ 1,427,040 |
Expected Activity | |||
---|---|---|---|
R78S | N32Y | Total | |
Direct labor-hours | 14,000 | 10,000 | 24,000 |
Batches | 816 | 1,152 | 1,968 |
Product variations | 840 | 408 | 1,248 |
The unit product cost of product N32Y under the activity-based costing system is closest to:
A: $136.16
B: $136.00
C: $76.70
D: $59.30
Solution:
Option B ($ 136.00 ) is the correct answer
Computation of unit product for Product N32Y cost based on activity based costing
Working notes :
Computation of activity rates:
Activity |
Activity cost |
Activity driver |
Activity driver rate |
Assembling products |
$ 6,72,000 |
24,000 hours (Number of direct labour hours) |
$ 28.00 ( $ 6,72,000 / 24,000 hrs) |
Preparing batches |
$ 2,55,840 |
1,968 batches (Number of batches) |
$ 130.00 ($ 2,55,840 / 1968 batches) |
Product Support |
$ 4,99,200 |
1248 variations (Number of product variations) |
$ 400 ($ 4,99,200/ 1248 variations) |
Computation of Unit product cost of Product N32Y based on activity based costing
Particulars |
N32Y |
Direct material cost |
$ 5,47,000 (10,000 units*$ 54.70) |
Direct labor |
$ 2,20,000 (10,000 units*$ 22.00) |
Assembling products |
$ 2,80,000 (10,000 hours *$ 28) |
Preparing batches |
$ 1,49,760 (1152 batches*$ 130) |
Product variations |
$ 1,63,200 (408 variations*$ 400) |
Total cost incurred (A) |
$ 13,59,960 |
Number of units (B) |
10,000 units |
Unit Cost per unit (A / B) |
$ 135.99 ($ 13,59,960 / 10,000 units) |
Unit cost per unit of Product N32Y as per Activity based costing is closest $ 136.00 ($ 135.99 rounded off to $ 136.00)
Conclusion :
From the above we can understand that OPTION B satisfies the given requirement in the question whereas remaining Options A,C,D do not satisfy the given requirement in question.
Thankyou !!!!