Question

In: Finance

Exercise 5.7 (Algorithmic) Characteristics of Production Process, Cost Measurement Vince Melders, of EcoScape Company, designs and...

Exercise 5.7 (Algorithmic)

Characteristics of Production Process, Cost Measurement

Vince Melders, of EcoScape Company, designs and installs custom lawn and garden irrigation systems for homes and businesses throughout the state. Each job is different, requiring different materials and labor for installing the systems. EcoScape estimated the following for the year:

Number of direct labor hours 6,710
Direct labor cost $87,230
Overhead cost $50,325

During the year, the following actual amounts were experienced:

Number of direct labor hours 6,030
Direct labor incurred $84,420
Overhead incurred $50,049.00

Required:

1. Should EcoScape use process costing or job-order costing?

- Select your answer -Process costingJob-order costingItem 1

2. If EcoScape uses a normal costing system and overhead is applied on the basis of direct labor hours,

What is the overhead rate? Round your answer to the nearest cent.

$  per direct labor hour

What is the average actual wage rate?

$  per direct labor hour

What is the cost of an installation that takes $3,240 of direct materials and 20 direct labor hours?

$

Hide Feedback

Partially Correct

Check My Work Feedback

1. Job-order costing system accumulates costs by job. The key feature of this costing system is that the cost of one job differs from that of another job and must be monitored separately. Process costing system is used when units are homogenous, or massed produced.

2. Predetermined OH rate = budgeted OH costs ÷ budgeted amount of driver

Average wage rate = Direct labor used ÷ direct labor hours

Check My Work

Solutions

Expert Solution

(1). EcoScape should use job-order costing because in case of job-order costing costs can be specifically identified with each job and it is given in the question that EcoScape Company, designs and installs custom lawn and garden irrigation systems for homes and businesses throughout the state that is why this company should use job-order costing and not should use process costing.

(2).

Predetermined overhead rate = Total estimated overhead costs / Estimated direct labor hours

Total estimated overhead costs = $50325

Estimated direct labor hours = 6710

Thus, Predetermined overhead rate ($50325 / 6710) = $7.50 per direct labor hour

(3).

Average actual wage rate = Actual labor costs / Actual direct labor hours

Actual labor costs = $84420

Actual direct labor hours = 6030

Thus, Average actual wage rate ($84420 / 6030) = $14 per direct labor hour

(4). Cost of installation = $3670

Explanation;

Cost of installation will be calculated as follow;

Direct material costs

$3240

Direct labor costs (20 * $14)

$280

Overhead costs (20 * $7.50)

$150

Cost of installation

$3670


Related Solutions

Characteristics of Production Process, Cost Measurement Vince Melders, of EcoScape Company, designs and installs custom lawn...
Characteristics of Production Process, Cost Measurement Vince Melders, of EcoScape Company, designs and installs custom lawn and garden irrigation systems for homes and businesses throughout the state. Each job is different, requiring different materials and labor for installing the systems. EcoScape estimated the following for the year: Number of direct labor hours 6,720 Direct labor cost $67,200 Overhead cost $50,400 During the year, the following actual amounts were experienced: Number of direct labor hours 6,045 Direct labor incurred $66,495 Overhead...
Characteristics of Production Process, Cost Measurement Vince Melders, of EcoScape Company, designs and installs custom lawn...
Characteristics of Production Process, Cost Measurement Vince Melders, of EcoScape Company, designs and installs custom lawn and garden irrigation systems for homes and businesses throughout the state. Each job is different, requiring different materials and labor for installing the systems. EcoScape estimated the following for the year: Number of direct labor hours 6,720 Direct labor cost $67,200 Overhead cost $50,400 During the year, the following actual amounts were experienced: Number of direct labor hours 6,045 Direct labor incurred $66,495 Overhead...
Characteristics of Production Process, Cost Measurement Vince Melders, of EcoScape Company, designs and installs custom lawn...
Characteristics of Production Process, Cost Measurement Vince Melders, of EcoScape Company, designs and installs custom lawn and garden irrigation systems for homes and businesses throughout the state. Each job is different, requiring different materials and labor for installing the systems. EcoScape estimated the following for the year: Number of direct labor hours 6,720 Direct labor cost $67,200 Overhead cost $50,400 During the year, the following actual amounts were experienced: Number of direct labor hours 6,045 Direct labor incurred $66,495 Overhead...
Characteristics of Production Process, Cost Measurement Vince Melders, of EcoScape Company, designs and installs custom lawn...
Characteristics of Production Process, Cost Measurement Vince Melders, of EcoScape Company, designs and installs custom lawn and garden irrigation systems for homes and businesses throughout the state. Each job is different, requiring different materials and labor for installing the systems. EcoScape estimated the following for the year: Number of direct labor hours 6,720 Direct labor cost $67,200 Overhead cost $50,400 During the year, the following actual amounts were experienced: Number of direct labor hours 6,045 Direct labor incurred $66,495 Overhead...
Cornerstone Exercise 6.10 (Algorithmic) Cost Information and the Weighted Average Method Morrison Company had the equivalent...
Cornerstone Exercise 6.10 (Algorithmic) Cost Information and the Weighted Average Method Morrison Company had the equivalent units schedule and cost information for its Sewing Department for the month of December, as shown below. Direct Materials Conversion Costs Units completed 43,000 43,000 Add: Units in ending work in process ×      Percentage complete:         15,000 × 100% direct materials 15,000 —         15,000 × 45% conversion materials — 6,750 Eqivalent units of output 58,000 49,750 Costs:         Work in process, December...
Cornerstone Exercise 6.10 (Algorithmic) Cost Information and the Weighted Average Method Morrison Company had the equivalent...
Cornerstone Exercise 6.10 (Algorithmic) Cost Information and the Weighted Average Method Morrison Company had the equivalent units schedule and cost information for its Sewing Department for the month of December, as shown below. Direct Materials Conversion Costs Units completed 41,000 41,000 Add: Units in ending work in process × Percentage complete: 14,000 × 100% direct materials 14,000 — 14,000 × 45% conversion materials — 6,300 Eqivalent units of output 55,000 47,300 Costs: Work in process, December 1: Direct materials $68,000...
eBook Cornerstone Exercise 6.10 (Algorithmic) Cost Information and the Weighted Average Method Morrison Company had the...
eBook Cornerstone Exercise 6.10 (Algorithmic) Cost Information and the Weighted Average Method Morrison Company had the equivalent units schedule and cost information for its Sewing Department for the month of December, as shown below. Direct Materials Conversion Costs Units completed 46,000 46,000 Add: Units in ending work in process × Percentage complete: 20,000 × 100% direct materials 20,000 — 20,000 × 45% conversion materials — 9,000 Eqivalent units of output 66,000 55,000 Costs: Work in process, December 1: Direct materials...
Cornerstone Exercise 6.8 (Algorithmic) Cost Information and FIFO Gunnison Company had the following equivalent units schedule...
Cornerstone Exercise 6.8 (Algorithmic) Cost Information and FIFO Gunnison Company had the following equivalent units schedule and cost information for its Sewing Department for the month of December: Direct Materials Conversion Costs Units started and completed 40,000 40,000 Add: Units in beginning work in process × Percentage complete: 6,000 × 0% direct materials — 6,000 × 50% conversion Costs 3,000 Add: Units in ending work in process × Percentage complete: 11,000 × 100% direct materials 11,000 — 11,000 × 35%...
Pfd Company has debt with a yield to maturity of 5.7%​, a cost of equity of...
Pfd Company has debt with a yield to maturity of 5.7%​, a cost of equity of 13.5%​, and a cost of preferred stock of 8.7%. The market values of its​ debt, preferred​ stock, and equity are $10.2 ​million, $2.6 ​million, and $15.2 ​million, respectively, and its tax rate is 40%. What is this​ firm's after-tax​ WACC?
Cornerstone Exercise 7-18 (Algorithmic) Acquisition Cost Cox Company recently purchased a machine by paying $13,600 cash...
Cornerstone Exercise 7-18 (Algorithmic) Acquisition Cost Cox Company recently purchased a machine by paying $13,600 cash and signing a 6-month, 10% note for $10,000. In addition to the purchase price, Cox incurred the following costs related to the machine: freight charges, $720; interest charges, $500; special foundation for machine, $400; installation costs, $1,100. Required: Determine the cost of the machine. ($25820 was wrong.) Exercise 7-59 (Algorithmic) Disposal of Tangible Capital Asset Pacifica Manufacturing retired a computerized metal stamping machine on...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT