Question

In: Accounting

The following data is given for the XYZ Company:       Budgeted production                         &nbsp

The following data is given for the XYZ Company:

      Budgeted production                                                          26,000 units

      Actual production                                                               27,500 units

      Materials:                                                                          

       Standard price per ounce                                                 $6.50

       Standard ounces per completed unit                                 8

       Actual ounces purchased and used in production              228,000

       Actual price paid for materials                                          $1,504,800

      Labor:                                                                                

       Standard hourly labor rate                                                $22 per hour

       Standard hours allowed per completed unit                      6.6

       Actual labor hours worked                                                183,000

       Actual total labor costs                                                     $4,016,850

Required:

a.   Calculate the materials variances and indicate whether they are favorable or unfavorable

b.         Calculate the labor variances and indicate whether they are favorable or unfavorable

Solutions

Expert Solution

Budgeted Standard Actual
Quantity/Hrs Rate Amount Quantity/Hrs Rate Amount Quantity/Hrs Rate Amount
Material 8 6.5 52 220000 6.5 1430000 228000 6.6 1504800
Labour 6.6 22 145.2 181500 22 3993000 183000 21.95 4016850
a) Material cos variance = Standard material cost - actual material cost
   =1430000 - 1504800
         74,800 Unfavorable
Material Price Variance = (Standard Price - Actual Price ) Actual Quantity Purchased
                                              = (6.5 - 6.6 ) *228000
         22,800 Unfavorable
Material Quantity Variance = (Standard quantity - Actual Quantity ) Standard Price
                                                       = (220000 -228000 )*6.5
         52,000 Unfavorable
b) Labor cost variance = standard labor cost - actual labor cost
   =3993000 - 4016850
         23,850 Unfavorable
Labour Rate Variance = (Standard Rate - Actual Rate) Actual Hrs Worked
                                       = (22 - 21.95)* 183000
           9,150 Favorable
Labour Efficiency Variance = (Standard Hrs. - Actual Hrs) Standard Rate
                                                = (181500 - 183000 )*22
         33,000 Unfavorable

Related Solutions

The following data is given for the Stringer Company: Budgeted production 954 units Actual production 1,030...
The following data is given for the Stringer Company: Budgeted production 954 units Actual production 1,030 units Materials: Standard price per ounce $1.92 Standard ounces per completed unit 12 Actual ounces purchased and used in production 12,731 Actual price paid for materials $26,099 Labor: Standard hourly labor rate $14.49 per hour Standard hours allowed per completed unit 4.8 Actual labor hours worked 5,304.5 Actual total labor costs $80,894 Overhead: Actual and budgeted fixed overhead $1,031,000 Standard variable overhead rate $25.00...
The following data are given for Harry Company: Budgeted production 1,056 units Actual production   900 units...
The following data are given for Harry Company: Budgeted production 1,056 units Actual production   900 units Materials:     Standard price per ounce $1.758     Standard ounces per completed unit 11     Actual ounces purchased and used in production 10,197     Actual price paid for materials $20,904 Labor:     Standard hourly labor rate $14.09 per hour     Standard hours allowed per completed unit 4.4     Actual labor hours worked 4,635     Actual total labor costs $75,319 Overhead:     Actual and budgeted fixed overhead $1,054,000     Standard variable overhead rate $24.00 per...
The following data are given for Stringer Company: Budgeted production 959 units Actual production   1,063 units...
The following data are given for Stringer Company: Budgeted production 959 units Actual production   1,063 units Materials:     Standard price per ounce $1.9     Standard ounces per completed unit 10     Actual ounces purchased and used in production 10,949     Actual price paid for materials $22,445 Labor:     Standard hourly labor rate $14.96 per hour     Standard hours allowed per completed unit 4.6     Actual labor hours worked 5,474.45     Actual total labor costs $83,485 Overhead:     Actual and budgeted fixed overhead $1,186,000     Standard variable overhead rate $27.00 per...
16.The following data is given for the Stringer Company: Budgeted production 906 units Actual production   1,059...
16.The following data is given for the Stringer Company: Budgeted production 906 units Actual production   1,059 units Materials:     Standard price per ounce $1.84     Standard ounces per completed unit 10     Actual ounces purchased and used in production 10,908     Actual price paid for materials $22,361 Labor:     Standard hourly labor rate $14.81 per hour     Standard hours allowed per completed unit 4.1     Actual labor hours worked 5,453.85     Actual total labor costs $83,171 Overhead:     Actual and budgeted fixed overhead $1,002,000     Standard variable overhead rate $25.00...
You are given the following budgeted and actual data for the Grey Company for each of...
You are given the following budgeted and actual data for the Grey Company for each of the months January through June of the current year. In December of the prior year, sales were forecasted as follows: January, 105 units; February, 100 units; March, 107 units; April, 112 units; May, 119 units; June, 127 units. In January of the current year, sales for the months February through June were reforecasted as follows: February, 95 units; March, 107 units; April, 107 units;...
You are given the following budgeted and actual data for the Grey Company for each of...
You are given the following budgeted and actual data for the Grey Company for each of the months January through June of the current year. In December of the prior year, sales were forecasted as follows: January, 93 units; February, 88 units; March, 95 units; April, 100 units; May, 107 units; June, 115 units. In January of the current year, sales for the months February through June were reforecasted as follows: February, 83 units; March, 95 units; April, 95 units;...
XYZ Company has budgeted production of Item #123 for April, May, and June of 2,400, 3,200,...
XYZ Company has budgeted production of Item #123 for April, May, and June of 2,400, 3,200, and 2,800 units, respectively. XYZ Company currently pays a standard rate of $3 per foot for raw material A and $5 per sheet for raw material B. Each unit produced requires 4 feet of raw material A and 2 sheets of raw material B. Each unit produced also requires 30 minutes of cutting direct labor time at a standard rate of $16 per hour...
1.      XYZ Company produces widgets. XYZ Company calculates the following costs for the production of 1...
1.      XYZ Company produces widgets. XYZ Company calculates the following costs for the production of 1 widget. Direct materials:           $250 Direct labor:                   $400 Variable overhead:      $125 Fixed overhead:            $200 Variable selling:            $50 Fixed selling:                  $35 Assuming that XYZ uses a 25% markup on the cost of producing 1 unit, calculate the sales price per unit charged by XYZ. a.      $812.50 b.      $1,325 c.       $848 d.      $1,218.75
A company that manufactures a single product supplied the following budgeted details: Budgeted production and factory...
A company that manufactures a single product supplied the following budgeted details: Budgeted production and factory overheads costs were 4 000 units and N$80 000, respectively. selling price per unit is N$150, variable cost per unit: Direct material N$30, Direct labour N$ 40, Variable overheads N$20, fixed overheads per month N$60 000. During the past month 3000 units were manufactured while only 600 units were on hand. The profit for the month according to the absorption costing method was:
Q4. The following data pertains to the month of October for ElmCo.when production was budgeted to...
Q4. The following data pertains to the month of October for ElmCo.when production was budgeted to be 5,000 units of P90. P90 has standard costs per unit of: 3 lbs. of Direct Materials at a cost of $7.00 per lb.; 0.20 hours of Direct Labor at $18.00 per hour; and Variable Overhead assigned on the basis of 0.05 machine hours at a rate of $50 per machine hour. In October the production of P90 totaled 4,600 units, using 15,100 lbs...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT