Question

In: Accounting

1. Price (rate) variance is: a.the difference between the actual and standard unit price of an...

1.

Price (rate) variance is:

a.the difference between the actual and standard unit price of an input multiplied by the standard input.

b.the difference between the actual and standard unit price of an input multiplied by the number of inputs used.

c.the difference between the actual and standard input used multiplied by the standard unit price of the input.

d.the difference between the actual and standard input used multiplied by the actual unit price of the input.

2.

Which of the following equations is used to determine standard hours allowed?

a.Standard Hours Allowed = Unit Labor Standard × Actual Output

b.Standard Hours Allowed = Unit Labor Standard × Standard Output

c.Standard Hours Allowed = Unit Labor Actual × Standard Output

d.Standard Hours Allowed = Unit Labor Actual × Actual Output

3.

Which of the following variances is the difference between actual fixed overhead and budgeted fixed overhead?

a.The fixed overhead spending variance

b.The fixed overhead efficiency variance

c.The fixed overhead volume variance

d.The fixed overhead capacity variance

4.

Material usage variance is:

a.the difference between actual and standard price multiplied by actual input.

b.the difference between actual and standard input multiplied by standard price.

c.the difference between actual and standard input multiplied by actual price.

d.the difference between actual and standard price multiplied by standard input.

5.

Gamma Inc. manufactures Product X using a single raw material. The standard quantity of input for the month of February was 3,000 units of raw material for 1,000 units of Product X. The actual output for the month of February was 1,500 units. Compute the standard quantity of raw material for actual output (SQ) of Product X.

a.1,500 units

b.1,500 units

c.4,500 units

d.3,000 units

6.

Which of the following is true of control limits?

a.Control limits identify variances that fall outside an acceptable range.

b.Control limits should be based only on past experience and intuition.

c.The lower control limit is the standard plus the allowable deviation.

d.The upper control limit is the standard minus the allowable deviation.

Solutions

Expert Solution

1. Price rate difference is the difference between the actual and standard unit price of an input multiplied by the actual number of inputs used.

Therefore, option b is the correct answer.

2. Standard hours allowed is the number of hours of production time that should have been used during an accounting period, which is based on the actual number of units produced, multiplied by the standard hours per unit.

Therefore, option a is the correct answer.

3. The fixed overhead spending variance is the difference between actual and budgeted fixed overhead costs.

Therefore, option a is the correct answer.

4. Material usage variance is the difference between actual and standard input multiplied by standard price.

Therefore, option b is the correct answer.

5.

First of all we need to calculate standard quantity of Raw Material per finished goods

Standard quantity of Raw Material per finished goods = Total units Raw Material Used/Total Finished goods

= 4,500/1,500 = 3 units

Standard quantity of raw material for actual output (SQ) of Product X = Actual Quantity * Standard quantity of Raw Material per finished goods

=1,500 units * 3 =4,500 units

Therefore, option c is the correct answer.

6. Control limits are used to detect signals in process data that indicate that a process is not in control and, therefore, not operating predictably.

Control limits, also known as natural process limits, are horizontal lines drawn on a statistical process control chart, usually at a distance of ±3 standard deviations of the plotted statistic from the statistic's mean.

Therefore from above definition it is clear that control limits identify variances that fall outside an acceptable range.

Therefore, option a is the correct answer.


Related Solutions

A variance is the difference between a budgeted, planned, or standard cost and the actual amount...
A variance is the difference between a budgeted, planned, or standard cost and the actual amount incurred/sold. Variances can be computed for both costs and revenues. Identify and explain the types of variance analysis tools, which can be used in a production department of a manufacturing company, which specialises in spare parts for cars
18. The spending variance measures a. the difference between expected expenditures for the actual number of...
18. The spending variance measures a. the difference between expected expenditures for the actual number of outputs and the expected expenditures for the planning budgeted number of outputs b. the difference between expected expenditures for the actual number of outputs and the actual expenditures for the actual number of outputs. c. the difference between budgeted expenditures and actual expenditures for the planned number of outputs. d. what the costs and revenues should have been for the budgeted number of outputs....
The difference between the Actual cost and the Standard cost for direct labor is called: Select...
The difference between the Actual cost and the Standard cost for direct labor is called: Select one: A. Direct Labor Rate Variance B. Direct Labor Efficiency Variance C. Direct Labor Split Variance D. Direct Labor Flexible Budget Variance E. None of the above part 2 The difference between the split cost and the actual cost for direct materials is called the: Select one: A. Materials Price Variance B. Materials Efficiency Variance C. Materials Usage Variance D. Materials Budget Variance E....
1) Describe an example of how an unfavorable variance between actual and budget amounts in a...
1) Describe an example of how an unfavorable variance between actual and budget amounts in a fixed static (master) budget can become a favorable variance in a flexible budget report. 2) Also, since flexible budget is more accurate in measuring performance, can company just develop flexible budget without the static budget? Why or why not?
The general model for calculating a quantity variance is: Multiple Choice Actual price × (Actual quantity...
The general model for calculating a quantity variance is: Multiple Choice Actual price × (Actual quantity of inputs used − Standard quantity allowed for output). Standard price × (Actual quantity of inputs used − Standard quantity allowed for output). (Actual quantity of inputs used × Actual price) − (Standard quantity allowed for output × Standard price). Actual quantity of inputs used × (Actual price − Standard price). The following standards have been established for a raw material used to make...
A company’s standard cost information for last year follows: Standard Quantity Standard Price Rate Standard Unit...
A company’s standard cost information for last year follows: Standard Quantity Standard Price Rate Standard Unit Cost Direct materials 1.5 lbs. $1.75 per lb. $3.05 Direct labor 1.5 hrs. $10 per hr. $16.00 Variable manufacturing overhead (based on DL hrs) 1.5 hrs. $1.25 per hr. $2.38 The company had the following actual results for the past year: Number of units produced and sold 175,000 Number of pounds of raw materials used 310,000 Cost of raw materials $496,000 Number of labor...
Which of the following formulas is used to calculate thematerials price variance? a. (Actual price...
Which of the following formulas is used to calculate the materials price variance? a. (Actual price × Actual quantity) – (Standard price × Actual quantity) b. (Actual price × Actual quantity) – (Standard price × Standard quantity) c. (Fixed price × Average quantity) – (Standard price × Actual quantity) d. (Variable price × Actual quantity) – (Total price × Actual quantity) e. None of these choices are correct.
What are the formula of Standard costs for variance Analysis (Effieciency Variance and Price Variance) ?
What are the formula of Standard costs for variance Analysis (Effieciency Variance and Price Variance) ?
standard labor hours per unit 4.5 hours standard labor rate $17 per hour actual hours worked...
standard labor hours per unit 4.5 hours standard labor rate $17 per hour actual hours worked 2,000 hours actual labor $38,000 actual output 500 units What is the labor efficiency variance? $4,250 favorable $1,500 unfavorable $4,250 unfavorable $1,500 favorable Which is correct?
The primary difference between a FUTA and SUTA periodic report is: a.the FUTA report is an...
The primary difference between a FUTA and SUTA periodic report is: a.the FUTA report is an annual tax return, whereas the SUTA reports are filed quarterly. b.the SUTA report is filed with the IRS, whereas the FUTA report is filed with the Social Security Administration. c.the FUTA report is quarterly, whereas the SUTA reports are filed annually. d.there is no difference, they are replicated reports. Buckwheat Musical Instruments LLC (not in a credit reduction state) made all of its SUTA...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT