Question

In: Accounting

Direct materials: 7 microns per toy at $0.34 per micron Direct labor: 1.3 hours per toy...

Direct materials: 7 microns per toy at $0.34 per micron

Direct labor: 1.3 hours per toy at $6.70 per hour

During July, the company produced 4,800 Maze toys. The toy's production data for the month are as follows:

Direct materials: 73,000 microns were purchased at a cost of $0.31 per micron. 31,000 of these microns were still in inventory at the end of the month.

Direct labor: 6,640 direct labor-hours were worked at a cost of $46,480.

Required:

1. Compute the following variances for July: (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values. Do not round intermediate calculations. Round final answer to the nearest whole dollar amount.)

a. The materials price and quantity variances.

b. The labor rate and efficiency variances.

Solutions

Expert Solution

Answer a

Given:

Standard Price $   0.34
Standard quantity 33,600 4800 * 7
Actual price $   0.31
Actual Quantity 42,000 73000 - 31000

Now,

Material Price Variance = (Standard Price - Actual price) * Actual Quantity
Material Price Variance = ( $ 0.34 - $ 0.31) * 73000
Material Price Variance = $ 2190 Favorable

Also,

Material Quantity Variance = (Standard quantity - Actual Quantity) * Standard Price
Material Quantity Variance = (33600 - 42000) * $ 0.34
Material Quantity Variance = $ 2,856 Unfavorable

Answer b

Given:

Standard Rate $ 6.70
Standard hours 6,240 4800*1.3
Actual rate $ 7.00 $ 46480 / 6640
Actual hours 6,640
Labor Rate Variance = (Standard Rate - Actual Rate) * Actual hours
Labor Rate Variance = ( $ 6.7 - $ 7) * 6640
Labor Rate Variance = $  1,992 Unfavorable
Labor Efficiency Variance = (Standard hours - Actual hours) * Standard rate
Labor Efficiency Variance = (6240 - 6640) * $ 6.7
Labor Efficiency Variance = $ 2,680 Unfavorable

In case of any doubt or clarification, you're welcome to come back via comments.


Related Solutions

Direct materials: 8 microns per toy at $0.30 per micron Direct labor: 1.2 hours per toy...
Direct materials: 8 microns per toy at $0.30 per micron Direct labor: 1.2 hours per toy at $7.10 per hour During July, the company produced 5,500 Maze toys. The toy's production data for the month are as follows: Direct materials: 74,000 microns were purchased at a cost of $0.27 per micron. 19,000 of these microns were still in inventory at the end of the month. Direct labor: 6,900 direct labor-hours were worked at a cost of $51,060. Required: 1. Compute...
direct materials: 8 microns per toy at .32 direct labor 1.2 hours per toy at 6.80...
direct materials: 8 microns per toy at .32 direct labor 1.2 hours per toy at 6.80 per hour during July the company produced 5200 maze toys direct material 80,000 microns were purchased at a cost of .29 per micro . 28000 of these microns were still in inventory at the end of the month. direct labor 6740 direct labor hours were worked at a cost of 48528. compute the following variance for July a. the material price and quantity variance...
12. The per-unit standards for direct labor are 1.5 direct labor hours at $15 per hour....
12. The per-unit standards for direct labor are 1.5 direct labor hours at $15 per hour. If in producing 3400 units, the actual direct labor cost was $69750 for 4500 direct labor hours worked, the total direct labor variance is $2250 unfavorable. $6750 unfavorable. $6750 favorable. $3400 unfavorable. 13. A company purchases 10000 pounds of materials. The materials price variance is $7000 favorable. What is the difference between the standard and actual price paid for the materials? $1.43 $0.70 $7.00...
Direct Materials and Direct Labor Variances At the beginning of June, Bezco Toy Company budgeted 15,000...
Direct Materials and Direct Labor Variances At the beginning of June, Bezco Toy Company budgeted 15,000 toy action figures to be manufactured in June at standard direct materials and direct labor costs as follows: Direct materials $15,750 Direct labor 12,600 Total $28,350 The standard materials price is $0.7 per pound. The standard direct labor rate is $14 per hour. At the end of June, the actual direct materials and direct labor costs were as follows: Actual direct materials $14,600 Actual...
Direct Materials and Direct Labor Variances At the beginning of June, Kimber Toy Company budgeted 22,000...
Direct Materials and Direct Labor Variances At the beginning of June, Kimber Toy Company budgeted 22,000 toy action figures to be manufactured in June at standard direct materials and direct labor costs as follows: Direct materials $46,200 Direct labor 23,100 Total $69,300 The standard materials price is $0.60 per pound. The standard direct labor rate is $15.00 per hour. At the end of June, the actual direct materials and direct labor costs were as follows: Actual direct materials $43,300 Actual...
Direct Materials and Direct Labor Variances At the beginning of June, Kimber Toy Company budgeted 11,000...
Direct Materials and Direct Labor Variances At the beginning of June, Kimber Toy Company budgeted 11,000 toy action figures to be manufactured in June at standard direct materials and direct labor costs as follows: Direct materials $11,550 Direct labor 6,600 Total $18,150 The standard materials price is $0.70 per pound. The standard direct labor rate is $10.00 per hour. At the end of June, the actual direct materials and direct labor costs were as follows: Actual direct materials $10,700 Actual...
Howard Company has established the following standards: Direct materials: 2.0 pounds at $4.80 Direct labor: 1.3...
Howard Company has established the following standards: Direct materials: 2.0 pounds at $4.80 Direct labor: 1.3 hours at $10 per hour Additional information was extracted from the accounting records: Actual production: 20,000 completed units Direct materials purchased: 47,000 pounds at $4.40, or $206,800 Direct materials consumed: 41,000 pounds Actual labor incurred: 25,000 hours at $9.4, or $235,000 Direct-labor rate variance: $53,000 favorable Direct-labor efficiency variance: $28,000 unfavorable Assume that the company computes variances at the earliest point in time. Required:...
The standards for product G78V specify 6.1 direct labor-hours per unit at $14.10 per direct labor-hour....
The standards for product G78V specify 6.1 direct labor-hours per unit at $14.10 per direct labor-hour. Last month 1,800 units of product G78V were produced using 11,030 direct labor-hours at a total direct labor wage cost of $146,220. Required: a. What was the labor rate variance for the month? b. What was the labor efficiency variance for the month? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero...
MAnufacturing overhead is applied on the basis of direct labor hours. The direct labor hours for...
MAnufacturing overhead is applied on the basis of direct labor hours. The direct labor hours for the period are 500 and the estimated manufacturing overhead is 2000. actual direct labor hours were 160 and actual overhead was 1000. Compute the manufacturing overhead applied during this period.
Actual quantity of direct labor 5,000 hours Actual direct labor rate $10 per hour Total direct...
Actual quantity of direct labor 5,000 hours Actual direct labor rate $10 per hour Total direct labor variance $8,600 Unfavorable . Direct labor rate variance $4,000 Unfavorable . Standard hours allowed per unit produced 2 hours Required: Find the following unknowns. a. Direct labor efficiency variance b. Standard rate per direct labor hour c. Actual quantity produced
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT