In: Accounting
Please by detiels !!
Miramar, Inc. uses a weighted-average process costing system which recognizes normal spoilage as 5% of good output. During the current period, 14,000 units were started and 10,000 units completed. Materials are added at the beginning of the process, conversion costs occur uniformly, and the inspection point is at the 70% point. Beginning work in process was 6,000 units, 40% complete, and ending work in process 9,000 units, 80% complete. The cost per equivalent unit for material was $1.00 and for conversion costs $3.00.
Required: compute the following
1. The number of units if abnormal spoilage
2. The cost of good units completed
Particulars | Amount (in $) | Particulars | Amount (in $) |
Beginning Work in process | 6000 | Units Completed | 10,000 |
Units Started | 14,000 | Normal Spoilage - 5% |
500 (10,000 x 5%) |
Abnormal Spoilage (Balance to tally Account) |
500 | ||
Ending Work in Inventory | 9,000 | ||
Total | 20,000 | 20,000 | |
Number of units in Abnormal Spoilage = 500 Units | |||
Cost of good units completed = (
Material costs + Conversion costs ) x Completed Units = ( $1 + $3) x 10,000 = $40,000 |
|||
Cost of good units completed = $40,000 |